Line balancing procedure in assembly layout, Project Management

Assignment Help:

Line Balancing Procedure in Assembly Layout

  • step1: Determine what tasks must be performed to complete one unit of a finished product and the sequence in which the tasks must be performed draw the precedence diagram.
  • Step 2: Estimate the task time amount of time it takes a worker to perform each task)
  • Step 3: Determine the cycle time (the amount of that would elapse between products coming off the end of the assembly line, if the desired hourly production were being produced)
  • Step 4: Assign each task to a worker and balance the assembly line. This process results in determining the scope of each worker job or which tasks that the he or she will perform.

Related Discussions:- Line balancing procedure in assembly layout

Too much too soon, What is operational and behavioural symptoms

What is operational and behavioural symptoms

Project management, what is the nine key competencies that project manager ...

what is the nine key competencies that project manager must develop? explain in detail of each and individual for the key competencies

Calculate the elapsed time of the critical path project, Calculate the elap...

Calculate the elapsed time of the critical path project when A Critical path of ACDEFGIJ is given below and the elapsed time of the project is 25 weeks. Th

What are the key stages to risk management, Question 1: You have been r...

Question 1: You have been requested by top management to develop projects for enhancing the effectiveness of human resources within your company. Write down a proposal in resp

Performance measurement - elements of tqm, Performance measurement: Pe...

Performance measurement: Performance measurement needs to be based upontimely measures of, and feedback on, performance. It provides information ontoday's service and gives an

Project Management Organization Framework, The Big Dig has often been criti...

The Big Dig has often been critiqued due to costs and challenges. To what extent do you think is it possible to identify risks associated with the project early in the project''s l

What are its core features of mpmm, MPMM is a body of project management co...

MPMM is a body of project management content, wrapped in an easy, simple to use software tool. This tool contains such core features as a Navigation Panel, Display Panel, Page Summ

Determine elapsed time of critical path, Determine elapsed time of critical...

Determine elapsed time of critical path when The critical path is given by points BCFG and the elapsed time 17 weeks. There D can over running by up to 3 weeks without

What is the estimated cost of the whole project, Question 1: (a) Using...

Question 1: (a) Using information from Table 1, build a network diagram for the project. (b) Perform a Forward Pass on the network diagram and deduce the duration of the p

Explain about the project management systems, Explain about the project man...

Explain about the project management systems. Project management systems: Each project must have a plan and a set of goals or performance measures to achieve this. Contro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd