Line balancing procedure in assembly layout, Project Management

Assignment Help:

Line Balancing Procedure in Assembly Layout

  • step1: Determine what tasks must be performed to complete one unit of a finished product and the sequence in which the tasks must be performed draw the precedence diagram.
  • Step 2: Estimate the task time amount of time it takes a worker to perform each task)
  • Step 3: Determine the cycle time (the amount of that would elapse between products coming off the end of the assembly line, if the desired hourly production were being produced)
  • Step 4: Assign each task to a worker and balance the assembly line. This process results in determining the scope of each worker job or which tasks that the he or she will perform.

Related Discussions:- Line balancing procedure in assembly layout

Address the issue of time, J Company is a retailer of fashion goods operati...

J Company is a retailer of fashion goods operating in a highly competitive market place. The Board of the company has given the go-ahead to redesign the company's website to make i

LIne balancing, Q3. What do you understand by “line balancing”? What happen...

Q3. What do you understand by “line balancing”? What happens if balance doesn’t exist?

What if i need more money for my project, Q. What if I need more money? ...

Q. What if I need more money? The similar applies here as in Question 17. Though the options that are open will depend on how far the project has already advanced. In general t

What is delegation of authority, What is delegation of authority? Del...

What is delegation of authority? Delegation: There is a restriction to what an individual can do single-handed. After a point, another person working within the organisat

Pm, short note on partnering

short note on partnering

Entities and variables, There are three main entities in our model. There i...

There are three main entities in our model. There is Ambulance Patients entity which represents all patients coming to the hospital by ambulance cars. The second entity indicates t

Risk.., explain what is meant by scope risk

explain what is meant by scope risk

Decision analysis, how to perform decision tree analysis for case study of ...

how to perform decision tree analysis for case study of transformation replacement..

WBS and Network diagram, Network Diagram for my course project based upon t...

Network Diagram for my course project based upon the WBS. The Network Diagram should include the Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), Latest Finish (LF), a

Initial project plan, o Does the project plan clearly identify a set of fun...

o Does the project plan clearly identify a set of functional increments leading to project completion? o Is the sequence of objectives consistent with both the risk priority and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd