Length is constructed in first phase of construction, Civil Engineering

Assignment Help:

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construction?


Related Discussions:- Length is constructed in first phase of construction

Dam, how can i prepare a project on dam

how can i prepare a project on dam

Retaining wall, whether the wall has adequate sliding resistance

whether the wall has adequate sliding resistance

Explain the hydraulic radius, Explain the Hydraulic Radius (R) A fluid'...

Explain the Hydraulic Radius (R) A fluid's cross-sectional area in flow divided by the wetted perimeter. For a circular channel flowing full and ½ full, R = D/4.

Sanitary, Design a sewer network

Design a sewer network

Wmm, wmm how can test depth wise

wmm how can test depth wise

What is the withdrawal force of steel nails, In engineering, the code-allow...

In engineering, the code-allowable withdrawal force is zero, due to the wood expands and contracts over time and the nail pullout force can decrease to zero

Pulverized fly ash as cement replacement, Q. Pulverized fly ash as cement r...

Q. Pulverized fly ash as cement replacement? Pulverized fly ash is a type of pozzolans. It is analuminous or siliceous material that possesses no binding ability by itself. Whe

Define the thiem equations for confined aquifers, Define the Thiem Equation...

Define the Thiem Equations for Confined Aquifers   Using natural log:  Q = 2pKm(h 2 - h 1 )/ln(r 2 /r 1 )   Using log 10 :    Q = 2Km(h 2 - h 1 )/((1055)log(r 2 /r 1 ))

Coatings at the back faces of abutments, Q. Coatings at the back faces of a...

Q. Coatings at the back faces of abutments? There are many views on the necessity of application of protective coatings (can be in the form of two coats of paint) to the back f

12/5/2013 6:44:00 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

12/5/2013 6:45:29 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd