Kicker of reinforced concrete cantilever retaining walls, Civil Engineering

Assignment Help:

Q. Kicker of reinforced concrete cantilever retaining walls located at the position of largest moment and shear force - why?

Generally for reinforced concrete cantilever retaining walls, there is a 75mm kicker at the junction wall stem and base slab to facilitate the fixing of formwork for concreting of wall stems. If a higher kicker (which is more than 75mm height) is provided instead, at the time of concreting of base slab the hydraulic pressure built up at kicker of fresh concrete cause great problem in forming a uniform and level base slab.  

Even though the fact that position of kicker in a cantilever retaining wall is the place of largest shear andflexure, there isn't any option left however to provide the kicker at this position.


Related Discussions:- Kicker of reinforced concrete cantilever retaining walls

Fore bearing, find out the interior angleS with diagrame LINE AB, BC, CD, D...

find out the interior angleS with diagrame LINE AB, BC, CD, DE, EA Fore bearing 60''30" , 122'' , 46'' , 205''30" , 300''

Arrangement of piles in a pile cap to reduce bending moment, Arrangement of...

Arrangement of piles in a pile cap to reduce bending moment induced in piles Let's consider that piles are designed to intersect at a single common point in a pile cap. The re

Hexagon, how to draw a regular hexagon using semicircle method

how to draw a regular hexagon using semicircle method

Explain detention or retention ponds - hydrology, Explain Detention or Rete...

Explain Detention or Retention Ponds Detention/Retention Ponds: Designed to reduce and contain the peak runoff from developed areas (more impervious). Attempt to limit the runo

Determine the concept of resultant force at a section, Resultant force at a...

Resultant force at a section We can determine stresses at top and bottom fibres, at a section of a beam, due to pre-stressing force and external loads. Using them, we can draw

Determine the project duration and critical path, Critical Path - Activity ...

Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start

SA-2, Problem with structure analysis-2

Problem with structure analysis-2

School building, from surveying to school building finish

from surveying to school building finish

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd