The joint bevels shall be prepared in accordance with the registered and approved weld procedure. Internal and external surfaces to be welded shall be clean and free from paint, oil, rust and scale.

Stamp the welder's identification symbol adjacent to all pressure welds with low stress stamp in carbon and low alloy steels with wall thickness of 6.4 mm (1/4") or greater. For flanged joints where the pipe wall thickness is less than 6.4 mm (1/4"), stamp the welders identification on the edge of the flange. When both members of a weld are less than 6.4 mm (1/4") thick, the welder's identity shall be recorded in a permanent written record.

For austenitic stainless steels, high alloy steels and non-ferrous metals, the welder's symbol shall be applied with waterproof paint.

The permanent marking material used on austenitic stainless steels and non-ferrous alloys shall not contain any harmful metal, metal salts, or elements such as zinc, lead, chlorides, sulphur, and other low melting point metals. Submit type of paint or ink including analysis of the above elements for OWNER's approval.


Related Discussions:- Joint preparation and identification

Injection molding, finishing operation of telephone outer body after inject...

finishing operation of telephone outer body after injection molding

Relative motion, the jet transport B is flying at the velocity of 600km/h w...

the jet transport B is flying at the velocity of 600km/h when a smaller aircraft A passes underneath the transport headed in the 60 degree direction. To passengers in B, however ap

Steam generator load balancing, Q. Steam Generator Load Balancing? The ...

Q. Steam Generator Load Balancing? The pressure controller output is cascaded to individual stations, one for each boiler. These allow selective increase or decrease of the du

Welding head, Welding Head Submerged arc welding head consists of the wir...

Welding Head Submerged arc welding head consists of the wire spool, wire feed system, flux delivery hopper and electrical contact nozzle. The electrode wire is unwound from the s

Final year project, Project is about Heat exchanger kit named TE 93.....Pro...

Project is about Heat exchanger kit named TE 93.....Project guide has told us to do something with it..without modifying the project largely.....i came up with change of material o

Flash butt welding, Flash Butt Welding The two pieces to be welded are ...

Flash Butt Welding The two pieces to be welded are pressed against each other by applying a pressure. To whatever finish the faces are machined, there will be some protuberance

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd