Installation of meters and verification of connections, Electrical Engineering

Assignment Help:

Installation of Meters and Verification of Connections

Apart from testing and calibrating the meters they must be properly installed as per the links diagram. The points in which must be kept in view although meters are installed are given below.

Installation of Meters

a) Position of meter should be such in which reading is simply visible.

b) Mounting of meter should be on solid wall or DP structure or on panel board.

c) Vertical mounting of meters should be ensured. The utility engineer should use a plumb bob and mark a vertical line prior to installation. He could also use a spirit level and put on the top of the meter after hanging on the screw hole. Instead, he should put spirit level on the edge of the terminal block to ensure vertical mounting.

d) For HT metering equipment, CTs should be right on the incoming side before the point of isolation.

e) The meter box should be sealed.

f) The meter recording should be checked at site.


Related Discussions:- Installation of meters and verification of connections

3-phase 180 degree mode vsi , 3-phase 180 0 mode VSI In 1800 mode VSI...

3-phase 180 0 mode VSI In 1800 mode VSI  each thyristor  conduct  for 1800 and two  thyristor  are fired  at 600 interval. For  example  if thyristor  T1  is fired at 00 then

Sommerfield’s free electron theory, Write down basic postulates of sommerfi...

Write down basic postulates of sommerfield’s free electron gas model. Show that the number of energy states per unit energy is given by g(E) = 4Rv/h 3 (2m) 3/2 E 1/2 .  What is

Determine the two possible ssb am signals, Let the modulating signal m(t) b...

Let the modulating signal m(t) be a sinusoid of the form m(t) = cos 2πf m t, f m c , and let the carrier signal be cos(2πf c t + φc). (a) Determine the conventional AM signal,

Determine the speed of prime mover of the generator, A synchronous generato...

A synchronous generator has a rotor with six poles and operates at 60 Hz. (a) Determine the speed of prime mover of the generator. (b) Repeat part (a) if the generator has 12

Develop a general expression for the force, Consider an electromagnet, as s...

Consider an electromagnet, as shown in Figure, which is used to support a solid piece of steel and is excited by a coil of N = 1000 turns carrying a current i = 1.5 A. The cross-se

Mode 1 - buck converter , Mode 1 ( 0 By  applying a positive  output ...

Mode 1 ( 0 By  applying a positive  output  pulse  of the pulse  width modulator to  the  transistor Q 1 it gets turned on.  An input  current  in flows  through V in   Q 1

Open-loop control system, Q. Open-loop control system? An open-loop sys...

Q. Open-loop control system? An open-loop system is one in which the control action is independent of the output or desired result, whereas a closed-loop (feedback) system is o

Electric automobile system specifications, The automobile shall not rely on...

The automobile shall not rely on fossil fuel for energy. The automobile shall be designed using available and emerging technology. The automobile shall seat at least five

Determine thevinin and norton equivalent circuit, Design and simulate by us...

Design and simulate by using multisim software a series voltage regulator to supply 1A to a load at a constant voltage of 9V. The supply voltage to regulator is 15V±10%. The minimu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd