Installation of meters and verification of connections, Electrical Engineering

Assignment Help:

Installation of Meters and Verification of Connections

Apart from testing and calibrating the meters they must be properly installed as per the links diagram. The points in which must be kept in view although meters are installed are given below.

Installation of Meters

a) Position of meter should be such in which reading is simply visible.

b) Mounting of meter should be on solid wall or DP structure or on panel board.

c) Vertical mounting of meters should be ensured. The utility engineer should use a plumb bob and mark a vertical line prior to installation. He could also use a spirit level and put on the top of the meter after hanging on the screw hole. Instead, he should put spirit level on the edge of the terminal block to ensure vertical mounting.

d) For HT metering equipment, CTs should be right on the incoming side before the point of isolation.

e) The meter box should be sealed.

f) The meter recording should be checked at site.


Related Discussions:- Installation of meters and verification of connections

Covalent bonding, Covalent Bonding Exhibited through the diamond la...

Covalent Bonding Exhibited through the diamond lattice semiconductors. Each atom enclosed by four nearest neighbors, each comprising four electrons in the outermost orbi

Show cmos logic families, Both DTL and TTL are based on the saturating BJT ...

Both DTL and TTL are based on the saturating BJT inverter. The transistor acts as a switch that connects or disconnects the collector and emitter. The switch is closed when suffici

Express the differential equation, A network function is given by ...

A network function is given by (a) For x(t) = δ(t), obtain y(t). (b) For x(t) = u(t), obtain y(t). (c) For x(t) = e -4t , obtain y(t). (d) Express the differenti

What is power gain, Q. What is power gain? Power gain is the ratio of p...

Q. What is power gain? Power gain is the ratio of power delivered to the load to power delivered to the amplifier is the power gain. A p =P o /P i     =V o I o /V i I s

Interpretation and analysis using remote sensing, Q. Interpretation and ana...

Q. Interpretation and analysis using remote sensing? Interpretation and analysis using remote sensing Various characteristics of a river can be understood by studying its planf

What is a darlington pair, Q. What is a darlington pair?               ...

Q. What is a darlington pair?                             The Darlington circuit consists of two cascaded emitter followers with infinite emitter resistance in the first stage.

Assigment, what is p-n junction and how its work

what is p-n junction and how its work

Hilda output - externally initiated signals , HILDA ( Output) It is ...

HILDA ( Output) It is  called hold acknowledge signals it is active  high  i e it  goes high when  microprocessor receives HOLD signal.

D.C. generator, I have made a wind turbine with vertical blades. I want to ...

I have made a wind turbine with vertical blades. I want to rotate magnets on the rotor with the coils being stationary.How do I wind the coils and must the magnets be N/S opposite

Determine the efficiency of the transformer, 1.    A 230/1000V 50 Hz, singl...

1.    A 230/1000V 50 Hz, single phase transformer has the following test data: Open circuit test (L.V.) Primary voltage = 230V Primary current = 1.30 A Input power

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd