Installation of meters and verification of connections, Electrical Engineering

Assignment Help:

Installation of Meters and Verification of Connections

Apart from testing and calibrating the meters they must be properly installed as per the links diagram. The points in which must be kept in view although meters are installed are given below.

Installation of Meters

a) Position of meter should be such in which reading is simply visible.

b) Mounting of meter should be on solid wall or DP structure or on panel board.

c) Vertical mounting of meters should be ensured. The utility engineer should use a plumb bob and mark a vertical line prior to installation. He could also use a spirit level and put on the top of the meter after hanging on the screw hole. Instead, he should put spirit level on the edge of the terminal block to ensure vertical mounting.

d) For HT metering equipment, CTs should be right on the incoming side before the point of isolation.

e) The meter box should be sealed.

f) The meter recording should be checked at site.


Related Discussions:- Installation of meters and verification of connections

Find the rms induced voltage, A two-pole, three-phase, 60-Hz, wye-connected...

A two-pole, three-phase, 60-Hz, wye-connected, round-rotor synchronous generator has N a = 12 turns per phase in each armature phase winding and flux per pole of 0.8Wb. Find the r

Hardware requirement - gis technology, Hardware Requirement- Se...

Hardware Requirement- Server of adequate sizing for enterprise-wide deployment for storing maps and geospatial data. Application server and web server. Desktops

Explain the and gates - microprocessor, Explain the AND GATES - Microproces...

Explain the AND GATES - Microprocessor? The AND GATE has a logic 1 or high output if the entire inputs are high. The boolean and symbol expression for a 3-input AND gate is sho

Develop and execute a pspice program, Develop and execute a PSpice program ...

Develop and execute a PSpice program to solve for the current I 2 in Figure.

Obtain the node voltages and current through each element, Q. For the circu...

Q. For the circuit shown in Figure, develop and execute a PSpice program to obtain the node voltages and the current through each element.

Variation of energy bands with alloy composition, Variation of Energy Bands...

Variation of Energy Bands with Alloy Composition The  band  structures  of  III-V  ternary  and  quaternary  compounds  modifies  as  their composition is varied. There

Lift control unit, You are required to design and document  the hardware de...

You are required to design and document  the hardware design  for a 68HC12D60 based Lift Control Unit (LCU). This design includes  the Input/Output hardware for interfacing with  l

What is the function of ct and p.t, Q. What is the function of CT and P.T a...

Q. What is the function of CT and P.T and where they are used? Ans: The full form of CT is Current transformer and is used for calculating of current. The full form of PT is

Compute sending - end voltage current and real power, Q. Athree-phase, 60-H...

Q. Athree-phase, 60-Hz transmission line has a total series impedance of 22.86 62.3°  per phase. It delivers 2.5 MW at 13.8 kV to a load connected to its receiving end. Compute th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd