Inspection of girder bridge, Civil Engineering

Assignment Help:

Q. As an AEN in charge, what inspection will you under taken at the time of inspection of Girder Bridge 3 x 60 feet.

Please explain the important items to be observed while inspecting a multi span plat Girder Bridge of 18.3 m span.

Ans.

The Assistant Engineer shall inspect every bridge on the sub division including road and foot over bridges once a year after monsoon during the prescribed months and record results in ink in the Bridge inspection register.

Bridges the condition of which warrant special attention should be inspected more frequently.

In case of Girder Bridge 3 x 60 feet Bridge classified on major Bridge. For major bridges entries of bridge inspection should made under the following heads -

i. Foundation & flooring - Extent or scour and damage.

ii. Masonry - Condition and extent of defects.

iii. Protective works - Scour slips or settlement.

iv. Bed Blocks - Tendency to movement and cracking.

v. Bearing and expansion arrangements - Defects in seatings and expansion arrangements.

vi. Steel work - Structural condition of girders and Paint.

vii. Sleepers - Condition and renewals required.

viii. Track - Defects in line and level.

Under each head the first entry should state whether the previous year's notes have been attended.


Related Discussions:- Inspection of girder bridge

Steady and uniform flow, During steady and uniform flow through an open cha...

During steady and uniform flow through an open channel of uniform cross section, a person claims that the specific energy of the fluid remains constant. A second person claims that

Phyisc, describe abot the michelson interfrance

describe abot the michelson interfrance

Impact of possible energy, a) Take into consideration the boiler efficiency...

a) Take into consideration the boiler efficiency, and verify the cost of heating the building, during the heating season, using present oil and gas prices.  b) Investigate the i

What is uniformly distributed surcharge, A retaining wall with a smooth ve...

A retaining wall with a smooth vertical back, 4.5 m high, retains a dry cohesionless backfill level with the top of the wall. γ = 18.6 kN/m 3 and φ = 30°. The backfill carries a u

Draw sketch for track in a cutting on a mainline route, Q. Draw a neat dim...

Q. Draw a neat dimensioned cross-sectional sketches of a - i. New single Line B.G. track in a cutting on a mainline route. ii. New double Line B. G. track on a trunk route ha

Surface dressing - road pavements, Surface Dressing: Surface dressing...

Surface Dressing: Surface dressing is an application of a thin film of bituminous binder followed by a coat of aggregates of single size, rolled into position. Surface dressi

Define recommendations for ptfe, Define Recommendations for PTFE? (a) I...

Define Recommendations for PTFE? (a) It can be either of the two forms given below: (i) Dimpled large sheet It may be circular or rectangular divided maximum into four pa

Water piped scheme, how to use mood diagram to get f and other Re

how to use mood diagram to get f and other Re

Concrete cracking, Attached information shows construction details of a wat...

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped

Determine the permissible stresses in steel, Permissible Stresses in Steel ...

Permissible Stresses in Steel As per the Indian code, the permissible stresses in the tendons at the time of initial prestressing should not exceed 80% of the characteristic t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd