Infrastructure railway design, Civil Engineering

Assignment Help:

The objective of this module is:-

- For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibility study for a proposed line speed increase between London and Derby

This will require:

-  A working knowledge of the track design handbook including construction standards, design mathematics and clearances,

-  Discussion with senior railway engineering staff involved with track design, track renewal production, enhancement works and maintenance activities (including track geometry)

-  Understanding of curving rules, track forces, their implications and requirement for good track quality

Background

A section of the Midland Main Line runs from London St Pancras to Derby some 128 miles in length. This is predominately two track with a four track section between Bedford and London

Both passenger and freight trains run over the route currently with maximum speeds of 110mph for passenger and 75mph for freight. The feasibility study is to examine if 125 mph running is possible using conventional or tilting trains

Current Passenger trains are predominately 'Meridian' or HST (High speed Trains) both of which have differing acceleration and braking profiles

The line has many sections of straight and curved track and also passes over several hill sections. There are several major stations on the route (e.g. Derby, Leicester, Kettering, Bedford etc) that were built in the Victorian era and are situated on sharp curves

Throughout the route there are a number of structures including viaducts, overbridges and underbridges. Many of these exist from when the line was constructed and have tight clearances

The track runs over various geological situations from chalk in areas at the south end to granite at the northern end of this section.

South of Bedford the line is 4 track and has an overhead electrification system.


Related Discussions:- Infrastructure railway design

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Levelling, what is the types of levelling

what is the types of levelling

Main purpose of conducting load test for piling works, Question What is...

Question What is main purpose of conducting load test for piling works ? Answer Pile load test gives information on ultimate bearing ability but not settlement be

Classification of timber based on grading, Classification Based on Grading:...

Classification Based on Grading: IS 883-1970 classifies the structural timber into 3 grades-select grade, grade I and grade II. The classification is depend on, defects, permi

REport, CASTE DISCRIMANIMATION

CASTE DISCRIMANIMATION

Explain the geophysical methods, Why are undisturbed samples needed? Descri...

Why are undisturbed samples needed? Describe any one procedure of obtaining undisturbed samples for a multi-storeyed building project. For what purpose are geophysical methods u

Calculate the settlement at the centre of the mat, A mat foundation of 15...

A mat foundation of 15 m x 15 m and weighing 20000 N/m 2 is to be constructed on the surface of a soil strata. The profile is given in Figure. The number of squares enclosed i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd