In marine pile type of steel tubular piles with reinforced concrete infill, least toe level is frequently specified in contract drawings. What is the purpose in your views?
Answer Main Purpose of minimum toe level is two-fold-
(i) In detailed designing stage, ground investigation should be conducted and approximate level of rock head is known. So, to avoid marine piles to be founded prematurely on boulders, smallest amount toe levels of marine driven piles are specified in contract.
(ii) It offers enough length of soils for lateral and uplift conflict.
Question What is key distinction in arranging pumps in series and in parallel? Answer For same pumps with similar functions, if pumps arranged in series, total head
For IRC Class AA loading in existing industrial areas, what is load (kN/m) has to applied base don the wheel loads. especially raft foundation & roads are at same level.
explanation for damping ration
Explain Influence lines-reactions 1. Remove the support under investigation 2. Displace the beam vertically a distance of 1 unit. The resulting beam shape will be the sha
Culverts, Causeway and Bridges: Roads have to cross several natural streams like - rivers and canals. They also have to cross railway lines and cross-roads. The structures nee
Q. Direction of placing the main weight of reinforcement in concrete pavement? The reinforcement of concrete pavement is typically in the form of longmesh type. A road generall
distance between concrete columns in 5 story building and if there is distance 15 feet than what should be the column size and how many bars and diameter of each bar ?
Tendon splices Tendon splices are used to join tendons when continuous prestressed concrete , members require long tendons to achieve continuity. Several types of tendon splic
Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an ultimate settlement of 250 mm. The average pressure increment in the clay stra
A sand deposit of 12 m thick overlies a clay layer. The water table is 3 m below the ground surface. In a field permeability pump-out test, the water is pumped out at a rate of 540
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd