Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Methods of analysis of trusses, Methods of analysis of trusses: What ...

Methods of analysis of trusses: What are the methods of analysis of trusses? What is found when the analysis of a system is done? Sol.:  The forces in the members of

Third service and fourth service, Third Service and Fourth Service ...

Third Service and Fourth Service Prepare a list and explain the mandatory checks to be carried out during third and fourth service of a motorcycle.

Speed Limit Governors, Why is porter governor more sensitive than Watt Gove...

Why is porter governor more sensitive than Watt Governor even the former has got an additional weight which will require more force to move sleeve than Watt governor?

Evaluate the support required by body on plane, Evaluate the Support requir...

Evaluate the Support required by body on plane: A body having weight 50KN rests in limiting equilibrium on rough plane, whose slope is 30º. The plane is raised to a slope of

Corollaries of first law of thermodynamics, example of 2nd corollary of fir...

example of 2nd corollary of first law of thermodynamics

Damping, physical meaning of viscous damping

physical meaning of viscous damping

Disadvantages of two stroke engine, Disadvantages of two stroke engine: ...

Disadvantages of two stroke engine: The following are some of the disadvantages of two stroke engine when compared with four stroke engine: 1. As firing takes place in ever

Welding, difference between blow hole and porosity

difference between blow hole and porosity

Fuel and steam generator, Boiler efficiency and heat losses, heat Balence s...

Boiler efficiency and heat losses, heat Balence sheet, boiler draught, high pressure boiler

Types of coated electrodes-rutile electrode, Rutile Electrode This type h...

Rutile Electrode This type has thicker coating than cellulosic coated and the flux is mainly composed of rutile (titanium di - oxide) and silicates, with a negligible amount of c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd