Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Pin shift return spring-gear complaints, pin shift return spring : Check p...

pin shift return spring : Check pin shift return spring for proper torque.

Show drain systems used in plant, Q. Show drain systems used in plant? ...

Q. Show drain systems used in plant? Process/power plants usually have a variety of different drain systems to collect the different types of liquid effluent. One of these is u

Discover the angle of twist - uniformly varying shaft, Discover the angle o...

Discover the angle of twist - uniformly varying shaft: A uniformly varying shaft of length 2 m is subjected to a torque of 2 kN-m. The diameter at the ends shall be 60 mm and

Mechanical, mostly what aspects trouble mechanical engineers?

mostly what aspects trouble mechanical engineers?

Example of shear force and bending moment diagram, Example of Shear force a...

Example of Shear force and bending moment diagram: Q: Draw the Shear Force and bending moment diagram for the simply supported beam loaded as shown in the figure given belo

Kinematics and Dynamics of Machinery, I have Four (4) questions related to ...

I have Four (4) questions related to Kinematics and Dynamics of Machinery . I need them exactly after 30 hours. Thanks and please do let me know.

Compute amplitude and frequency of the particle, Compute amplitude and freq...

Compute amplitude and frequency of the particle: The displacement of a particle is described by x = 5 + 3 cos 3 t. Determine the position of the particle at t = 3 seconds. Com

Explain action and reaction of force , Explain action and reaction of force...

Explain action and reaction of force: Two bodies A and B are in contact at point ' O '. Body A Press against body B. Thus action of body A on the body B is F . React

Under damping, Under Damping If    the restoring force is larger than ...

Under Damping If    the restoring force is larger than friction, and the oscillation is classified as under-damped. In this case,  ω  is real and behaves exactly like the solu

Pressure relief valve application, Q. Pressure Relief Valve Application? ...

Q. Pressure Relief Valve Application? A general comparison of operational characteristics is given for the different types of pressure relief valves in common industrial use.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd