Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

What is thermoplastic plastics, Q. What is thermoplastic plastics ? Thes...

Q. What is thermoplastic plastics ? These plastic soften under heat, harden on cooling, and can be resoften under heat. Thus, they retain their fusibility, solubility, an

Define the process of step community, Define the process of STEP community ...

Define the process of STEP community The STEP community is in the process of defining and standardizing a number of domain-specific (mechanical or electrical) Application Proto

Describe about carbon steel, Q. Describe about Carbon Steel? Steel havi...

Q. Describe about Carbon Steel? Steel having no specified minimum quantity for any alloying element (other than commonly accepted amounts of manganese, silicon, and copper) and

.high lead copper alloy castings, I have faced a serious problem of Lead se...

I have faced a serious problem of Lead segregation and porosity in Copper Tin Zn alloy containing 26-30 % lead sand castings.Can anybody throw light on this

Determine the air standard efficiency, Compare the efficiency of Diesel, ot...

Compare the efficiency of Diesel, otto and Dual combustion cycle on the basis of same compression ratio and same heat input. In an otto cycle air at 17 o c and 1 bar is compressed

SFD AND BMD, what is SFD and BMD? EXPLAIN

what is SFD and BMD? EXPLAIN

Impeller design, The function of the impellers is to: (i) reduce bubble siz...

The function of the impellers is to: (i) reduce bubble size thereby increasing the surface area for oxygen transfer, and (ii) maintain a uniform environment, nutrient supply and he

Prove the bending equation, Can you give me the Prove of the bending Equati...

Can you give me the Prove of the bending Equation M/I=E/R=σ/Y

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd