Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Design evacuation systems for plant, Q. Design evacuation systems for plant...

Q. Design evacuation systems for plant? The plant will have designated Muster areas where personnel can go during an emergency and be accounted for and from which they can then

Evaluate heat transfer and internal energy, (a) Describe that internal ener...

(a) Describe that internal energy is property of the system. (b) one kg of air at 1 bar and 300k is compressed adiabatically till its pressure becomes 5 times the original press

Determine the efficiency of bell coleman cycle, (a) Derive a mathematical e...

(a) Derive a mathematical expression to determine the efficiency of Bell Coleman Cycle. (b) A dense air refrigeration cycle acts between pressures of 4 bar and 16 bar. The air t

Calculate sif of crack - beam, Calculate sif of crack - beam: An edge ...

Calculate sif of crack - beam: An edge cracked beam carries crack in its central plane whose lengths is 5 mm. A load of 1000 N is applied opposite to crack so that crack would

Upward compatibilityof iges, Upward Compatibilityof IGES Upward Compati...

Upward Compatibilityof IGES Upward Compatibility : The need for generations of processors to parse files compliant with earlier versions of IGES thwarted the breadth and rate o

Calculate the machine power factor, A 3-phase, 15-kV, 4-pole, cylindrical r...

A 3-phase, 15-kV, 4-pole, cylindrical rotor synchronous generator is connected to a 50-Hz infinite bus. The synchronous reactance of the machine is X s = 0.6 ohms per phase and th

Calculate the temperature at the center of the pipe, Heat generated uniform...

Heat generated uniformly in Stainless steel plate having k=20 W/m. 0 C. The thickness of the plate is 1cm and the heat generation rate is 500 MW/m 3 . If the two sides of the plate

Determine the topological information of b-rep, Topological information of ...

Topological information of b-rep It provide the relationships among vertices, edges and faces similar to that used in a wire-frame model. In addition to connectivity, topologi

Arc welding power sources-arc characteristics, ARC CHARACTERISTICS In ...

ARC CHARACTERISTICS In order to understand the different output characteristics that are required by the welding power source it is necessary to understand the load which is f

What is value engineering, Value engineering & Value analysis VA may b...

Value engineering & Value analysis VA may be defined as looking at an existing product or a product already in production to see if changes in design or process can reduce prod

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd