Implementation of material requirement planning, Mechanical Engineering

Assignment Help:

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.


Related Discussions:- Implementation of material requirement planning

Locomotive boiler, What are the advantages and disadvantaged of locomotive ...

What are the advantages and disadvantaged of locomotive boilers

Pure torsion, Pure Torsion: What do you mean by pure Torsion?       ...

Pure Torsion: What do you mean by pure Torsion?                                                                                                       In general two typ

Present marketing information, Question: (a) When you are provide a de...

Question: (a) When you are provide a design brief, marketing forms an important aspect that involves researching and computing a potential opportunity to enter a market. What

Effects of air resistance. , Traveling at a speed of 16.0 m/s, the driver o...

Traveling at a speed of 16.0 m/s, the driver of an automobile suddenly locks the wheels by slamming on the brakes. The coefficient of kinetic friction between the tires and the roa

Welding, Why is the quality of welds produced by submerged arc welding very...

Why is the quality of welds produced by submerged arc welding very good#Minimum 100 words accepted#

Mchanical vibration, the base of a spring -mass- damper system is subjected...

the base of a spring -mass- damper system is subjected to the periodic displacement. determine the response of the mass using the principle of superposition

Corrosive properties of caustic, Q. Corrosive properties of caustic? So...

Q. Corrosive properties of caustic? Sodium hydroxide, more commonly known as Caustic Soda or simply ‘Caustic', is widely used in the petrochemical industry to neutralize acidic

What do you mean by filler metals, Q. What do you mean by Filler metals? ...

Q. What do you mean by Filler metals? Use filler metal that is similar in chemistry, corrosion resistance, and mechanical properties of the base metal being welded. Filler m

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd