Immersed tube method for underwater crossings, Civil Engineering

Assignment Help:

Immersed tube method for underwater crossing includes the following basic construction steps:

(i)  Prefabricating long tunnel units (concrete orsteel shell) in a dry-dock or shipyard

(ii) Floating and towing the units with removable bulkhead to site

(iii)Immerse the units in a pre-dredged trench

(iv)Connect the units one by one

(v) Covering completed tunnel with backfill

Steel immersed tunnel is a number of times adopted due to the ease of fabrication and its relative lightness. Furthermore shorter construction time is essential when compared with concrete immersed tubes.


Related Discussions:- Immersed tube method for underwater crossings

Material which can endures vibrations and saline conditions, material which...

material which can endures vibrations and saline conditions

Assignment, on timber, varieties , preservation, and seasoning of timber

on timber, varieties , preservation, and seasoning of timber

Prestressed concrete poles, Prestressed concrete poles In the past deca...

Prestressed concrete poles In the past decades, prestressed  concrete poles have become popular and have replaced the traditional poles made of timber, steel or reinforced  con

Surveying, what are tie lines? explain in detail

what are tie lines? explain in detail

Concrete surface finish - limitations of ultrasonic system, Define Concrete...

Define Concrete Surface Finish - Limitations of Ultrasonic System? The smoothness of the surface under test is important to ensure proper acoustical contact between the transdu

Errors in leveling, what is the errors faced in leveling servey

what is the errors faced in leveling servey

IRC class 70R, What will be the structural weight per meter for IRC class 7...

What will be the structural weight per meter for IRC class 70r bridge

Example for beam flexure design, Example for Beam Flexure Design Select...

Example for Beam Flexure Design Select the lightest W section for the simply supported beam shown below.  The beam length is 12ft.  The nominal loading is: w d = 4.0 kip/ft (i

Retardation of fresh concrete, Retardation of fresh concrete has numerous b...

Retardation of fresh concrete has numerous benefits as below: (i)  A rapid hydration process leads to loss in concrete strength since concrete will have a poorer structure with

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd