Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Illustrate an example of demonstrating a network or critical path by given activity and duration.
Activity Duration (Wks) Preceded by
A 5 -
B 4 -
C 3 B
a. The elapsed or expected completion time of the project is eight weeks
b. The critical path activities are as A and C for example both should be completed into their predicted durations, or else the project will be longer into duration than eight weeks. See how the EET and LET of critical activities are the same.
c. Activity B is a non-critical activity and that would have a float time of one week.
d. This is since its predicted duration is four weeks, but this can take five weeks to finish and yet leave enough time left for activity C to be finished, the elapsed time of the project will still be attained. See how the EET and LET both of non-critical activities are not same; the difference is one week for example the float time, while you deduct one by the other.
e. The broken arrow or dummy activity preserves logic into the diagram for example visually you can observe that both activities A and B should be finished, before C can begin. See also that the arrow showing activity C starts by circle 3 (not circle 2), this is since the earliest event time for C would be 5 weeks not 4 weeks like circle 2 exhibits.
Define the term risk in risk management. Risk: It is the probability or chance of something which may or may not arise; this is something that can be quantified by using s
Compare and Contrast the KN346 investment and the "plain vanilla" alternative.
What are the uses of Cost Benefit Analysis? Generally, this technique (complex cost benefit analysis) is advocated for use within decisions on public projects, wherein social c
Question 1 Differentiate between Commercial and Open Source ERPs software packages Question 2 For a successful MRP system three types of information are very essential. Descr
Identify the critical path by activities and duration. Activity Duration (Wks) Preceded by A 5 -
Explain TWO strategies that a project manager might implement to address a project risk. Risk avoidance - this strategy would be 'exiting the method that is giving rise to
Describe the range of internal possibilities that exist for an organisation wishing to fill a job vacancy. A number of internal possibilities exist for recruitment, short listi
Are the principal advantages and disadvantages of the sequential approach to system development offered through the waterfall and ‘V’ lifecycle models? The waterfall approach a
What do you mean by variable costs? Variable costs conversely, tend to vary directly along with the volume of output. Illustrations of variable cost are as given below: direct
Personnel Management Personnel Management refers to the process of procurement and management of the human resource that is needed to accomplish organization objectives. It is
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd