Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Illustrate an example of demonstrating a network or critical path by given activity and duration.
Activity Duration (Wks) Preceded by
A 5 -
B 4 -
C 3 B
a. The elapsed or expected completion time of the project is eight weeks
b. The critical path activities are as A and C for example both should be completed into their predicted durations, or else the project will be longer into duration than eight weeks. See how the EET and LET of critical activities are the same.
c. Activity B is a non-critical activity and that would have a float time of one week.
d. This is since its predicted duration is four weeks, but this can take five weeks to finish and yet leave enough time left for activity C to be finished, the elapsed time of the project will still be attained. See how the EET and LET both of non-critical activities are not same; the difference is one week for example the float time, while you deduct one by the other.
e. The broken arrow or dummy activity preserves logic into the diagram for example visually you can observe that both activities A and B should be finished, before C can begin. See also that the arrow showing activity C starts by circle 3 (not circle 2), this is since the earliest event time for C would be 5 weeks not 4 weeks like circle 2 exhibits.
What is the meaning of exception reports? Progress (or exception reports) can be utilized to monitor and to control the project. It permits the project board or project manager
Problem 1: a) What is the role of strategy in project management? b Explain the importance of aligning H.R projects with the organizational strategy. c) What are the impa
what action should be taken by various functioal managers to meet the scheduled dates
At this stage of design the designer will invariably by under tremendous pressure to quickly finish the design and pass it on for production. This is so because even w
P hases of value engineering process I nvestigation phase: This phase investigates the background information, the technical input reports, the field data, the functiona
Question : The process of delivering a presentation is a systematic one that involves thorough planning as well as preparation and one of the main phases is preparing the prese
Managerial function of organizing Organizing is the process of grouping activities and resources in a logical and appropriate manner. Because of the changes that take place wit
You should design a ‘hearts and minds’ programme associated with the implementation of a modern system for the recording and management of stock within a book-publishing company an
GBF Group is a leading food and beverage manufacturer with an international presence in over 50 countries worldwide. The group has seven strategic business units (SBUs) and each ha
o Is the domain model a complete representation of the relevant objects in the problem domain? o Are associations between problem domain objects captured? o Are specializatio
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd