Illustrate an example of a critical path given by activity, Project Management

Assignment Help:

Illustrate an example of demonstrating a network or critical path by given activity and duration.

Activity                      Duration (Wks)                   Preceded by

A                                 5                                   -

B                                 4                                   -

C                                 3                                   B

327_Demonstrating a network or critical path.png

a. The elapsed or expected completion time of the project is eight weeks

b. The critical path activities are as A and C for example both should be completed into their predicted durations, or else the project will be longer into duration than eight weeks. See how the EET and LET of critical activities are the same.

c. Activity B is a non-critical activity and that would have a float time of one week.

d. This is since its predicted duration is four weeks, but this can take five weeks to finish and yet leave enough time left for activity C to be finished, the elapsed time of the project will still be attained. See how the EET and LET both of non-critical activities are not same; the difference is one week for example the float time, while you deduct one by the other.

e. The broken arrow or dummy activity preserves logic into the diagram for example visually you can observe that both activities A and B should be finished, before C can begin. See also that the arrow showing activity C starts by circle 3 (not circle 2), this is since the earliest event time for C would be 5 weeks not 4 weeks like circle 2 exhibits.


Related Discussions:- Illustrate an example of a critical path given by activity

Appraisal process to help staff appreciate, KS, the Finance Manager of TZY ...

KS, the Finance Manager of TZY Company's Finance Department, is aware that it is approaching the time of year when he requirements to conduct staff appraisals. However, he is consc

Introduction to syringe management plan, Introduction The project 'Syri...

Introduction The project 'Syringe Management Plan' is created to protect the community against misplace of syringe that causes accidental needle injury. This project is introdu

Product characteristics and requirements, 1.  Main functions: The web based...

1.  Main functions: The web based site will be fully enabled for viewing via iPad and be fully accessible at the cafe seating only.  The menu will be fully automated to allow order

What is productivity, What is productivity? Productivity: Product...

What is productivity? Productivity: Productivity may be described as the ratio between input and output. Output implies the amount produced or the number of items produce

What are the main factors in organisation structure included, What are the ...

What are the main factors in organisation structure included? The structure gives an appropriate frame work for authority and responsibility relationships among different posit

What are the disadvantages of critical path analysis, What are the disadvan...

What are the disadvantages of critical path analysis? Disadvantages of critical path analysis (CPA): a. Supposes a trade off among time and money but most staff cost coul

Quantitative Methods, A2. Unfortunately, the Capital Investment Committee r...

A2. Unfortunately, the Capital Investment Committee refused to approve your recommendation (Problem 1) since you did not consider the uncertainty inherent in these types of investm

Man power planning in human resources management, What is the importance of...

What is the importance of man power planning in human resources management? Significance of Man Power Planning within Human Resources Management is as illustrated here: a. M

Limitations of quality cost analysis, T he dark side of quality cost analy...

T he dark side of quality cost analysis The Quality Cost Analysis will always look at the organisation's costs and not the customer's costs. The manufacturer and the seller ar

What are the major characteristics of a project, Question: (a) What ar...

Question: (a) What are the factors to consider while choosing an appropriate Project Management Structure? (b) What are the major characteristics of a Project? (c) Out

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd