Illustrate an example of a critical path given by activity, Project Management

Assignment Help:

Illustrate an example of demonstrating a network or critical path by given activity and duration.

Activity                      Duration (Wks)                   Preceded by

A                                 5                                   -

B                                 4                                   -

C                                 3                                   B

327_Demonstrating a network or critical path.png

a. The elapsed or expected completion time of the project is eight weeks

b. The critical path activities are as A and C for example both should be completed into their predicted durations, or else the project will be longer into duration than eight weeks. See how the EET and LET of critical activities are the same.

c. Activity B is a non-critical activity and that would have a float time of one week.

d. This is since its predicted duration is four weeks, but this can take five weeks to finish and yet leave enough time left for activity C to be finished, the elapsed time of the project will still be attained. See how the EET and LET both of non-critical activities are not same; the difference is one week for example the float time, while you deduct one by the other.

e. The broken arrow or dummy activity preserves logic into the diagram for example visually you can observe that both activities A and B should be finished, before C can begin. See also that the arrow showing activity C starts by circle 3 (not circle 2), this is since the earliest event time for C would be 5 weeks not 4 weeks like circle 2 exhibits.


Related Discussions:- Illustrate an example of a critical path given by activity

Factors of quality, Factors of Quality The implications here are tha...

Factors of Quality The implications here are that quality is to be viewed in its totality and not restricted only to the quality of production or products or some aspects

Changing customer demands and strong competition, In response to changing c...

In response to changing customer demands and strong competition, the new product development team of Z Company has been working on a new product range. However, the process has not

Developing a project plan, You are creating a customer database for the Win...

You are creating a customer database for the Winston-Salem Warthogs

Linear Programming Problem, Maximize Z= 3x1 + 2X2 Subject to the constraint...

Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Caselet, what action should be taken by various functioal managers to meet ...

what action should be taken by various functioal managers to meet the scheduled dates

Key stages to conduct a training needs assessment, Question 1: (a) What...

Question 1: (a) What is a TNA, and why is it conducted? (b) What are the key stages to conduct a Training Needs Assessment? (c) Having undertaken an organization-wide TNA

Determine the supporting project activities for estimate, Describe differen...

Describe different types of supporting project activities for estimating. Estimate the given supporting project activities are as follows: 1.    Project management 2.    Team lea

Real life project, Real life project make as a project manager do it critic...

Real life project make as a project manager do it critical evolution 3000 words

Responsibilities of an event manager, Question 1: a) Outline the key r...

Question 1: a) Outline the key responsibilities of an Event Manager b) Give THREE clear working examples of possible event objectives for either a country, a resort, an or

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd