Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Illustrate an example of demonstrating a network or critical path by given activity and duration.
Activity Duration (Wks) Preceded by
A 5 -
B 4 -
C 3 B
a. The elapsed or expected completion time of the project is eight weeks
b. The critical path activities are as A and C for example both should be completed into their predicted durations, or else the project will be longer into duration than eight weeks. See how the EET and LET of critical activities are the same.
c. Activity B is a non-critical activity and that would have a float time of one week.
d. This is since its predicted duration is four weeks, but this can take five weeks to finish and yet leave enough time left for activity C to be finished, the elapsed time of the project will still be attained. See how the EET and LET both of non-critical activities are not same; the difference is one week for example the float time, while you deduct one by the other.
e. The broken arrow or dummy activity preserves logic into the diagram for example visually you can observe that both activities A and B should be finished, before C can begin. See also that the arrow showing activity C starts by circle 3 (not circle 2), this is since the earliest event time for C would be 5 weeks not 4 weeks like circle 2 exhibits.
What are the questions of the initiation phase? Questions to be answered in the initiation phase include the given as: • Why only project management? • Is this feasible?
What du you understand by line balancing
Prepare a 1-page Cost Estimate in MS Excel for the project similar to the example provided below. Use the WBS items provided below, and be sure to document assumptions you make in
Are the principal advantages and disadvantages of the sequential approach to system development offered through the waterfall and ‘V’ lifecycle models? The waterfall approach a
Question: You have been appointed as consultant to advise a small company of your choice about its product portfolio. Write a report which: a) explains the product life cycl
Determine elapsed time of critical path when The critical path is given by points BCFG and the elapsed time 17 weeks. There D can over running by up to 3 weeks without
Critical Path about wedding planning
Degree of Customer Contact The extent to which customers get involved in the production system has important implications for the design of production processes. In custom bui
compare cobit 4.1 with cobit 5
Process Planning Process planning is the systematic determination of method or process by which the product is to be manufactured economically and competitively within the limits
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd