Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Illustrate an example of demonstrating a network or critical path by given activity and duration.
Activity Duration (Wks) Preceded by
A 5 -
B 4 -
C 3 B
a. The elapsed or expected completion time of the project is eight weeks
b. The critical path activities are as A and C for example both should be completed into their predicted durations, or else the project will be longer into duration than eight weeks. See how the EET and LET of critical activities are the same.
c. Activity B is a non-critical activity and that would have a float time of one week.
d. This is since its predicted duration is four weeks, but this can take five weeks to finish and yet leave enough time left for activity C to be finished, the elapsed time of the project will still be attained. See how the EET and LET both of non-critical activities are not same; the difference is one week for example the float time, while you deduct one by the other.
e. The broken arrow or dummy activity preserves logic into the diagram for example visually you can observe that both activities A and B should be finished, before C can begin. See also that the arrow showing activity C starts by circle 3 (not circle 2), this is since the earliest event time for C would be 5 weeks not 4 weeks like circle 2 exhibits.
A brilliant UTM student at the end of his graduation is in presence of two opportunities and has to choosen between them.
However proving a design defect can be difficult. Some of the factors used by the jury to asses s whether a product design is defective and unreasonably dangerous are: 1.The utili
Ask question #MinimumIn its first year, “ABC Co” had the following experience Sales = 50,000 units Selling price = br. 50 TVC = br. 1,000,000 TFC = br. 250,000 Required: A. Devel
Factors affecting Process Design - Nature of Product The operations management has to design the production systems to produce products/ service of the kind that customers wan
prepare income statement
Risk management enhancement There is scope for risk management scenario and the following are some of the methods suggested: Bringing increased awareness of risks: Imp
Defects found after product delivery per function point Defects found after product delivery per LOC Pre-delivery defects: yearly post-delivery defects Defects per functio
what is the nine key competencies that project manager must develop? explain in detail of each and individual for the key competencies
what risks can you identify? why are they risk to global green books publishing?
Question: (a) Past projects have shown that cost escalation is a common phenomenon with respect to the amount by which actual costs increases overrun the initial estimated cos
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd