Identify the characteristics of the organisation, Project Management

Assignment Help:

M is a business that sells custom made computer-based information systems. Every customer order is for a unique system, which will contain experts from many functional areas within M. Every customer expects a high level of individual attention. Some systems take only four to six months to design and form and cost less than €50,000, whereas other systems cost various million Euros and can take up to three years to complete. Projects are continually being done and started. 

Identify the characteristics of the organisation that make it suitable for M to have a matrix structure.

The characteristics of M that are appropriate to it adopting a matrix organisational structure are as follows:

  • The business of M having of a series of projects which are custom made, which are difficult and require staff from a number of dissimilar functional areas;
  • The projects undertaken by M have dissimilar start and end dates, so the organisation is continually reassigning resources from project to project as single ends and another begins;
  • The projects undertaken by M are difficult so the staff benefit from also being assigned to a technical function (like as finance or procurement) where they can share knowledge and experience with colleagues in their functional teams;

 


Related Discussions:- Identify the characteristics of the organisation

Process of diagnosing the system, Question 1: What are the steps involv...

Question 1: What are the steps involved in the process of diagnosing the system? Steps involved in the process of diagnosing the system. Question 2: What are the maj

Quantitative Methods, A2. Unfortunately, the Capital Investment Committee r...

A2. Unfortunately, the Capital Investment Committee refused to approve your recommendation (Problem 1) since you did not consider the uncertainty inherent in these types of investm

Cost benefit analysis, How to determine which project have larger net benef...

How to determine which project have larger net benefit between two projects

Organisational competences and core competences, Explain the relationship b...

Explain the relationship between organisational competences and decisions relating to the contracting out of activities. Organisational competences A competence is an mehod

Network, charateristics of a good network

charateristics of a good network

Discuss importance of value management in project life cycle, Question: ...

Question: (a) Past projects have shown that cost escalation is a common phenomenon with respect to the amount by which actual costs increases overrun the initial estimated cos

Macro environment, The influence an organisation will normally have over it...

The influence an organisation will normally have over its macro environment will be Limited or non existent

Demonstration of work plan of national weather service, The National Weathe...

The National Weather Service The Scenario:The National Weather Service has recently faced downsizing due to a significantpersonnel shift in the Obama budget.  The White House budg

Preliminary design, Having given the guidelines in the form of design s...

Having given the guidelines in the form of design specifications the designer should be given a free hand in developing the preliminary design of the product. However i

Develop a new product from the given product ingredient, To develop a new p...

To develop a new product from the given product ingredient. • explore new ideas for product development, • understand the concept of development of a process, • gain kno

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd