Identify the characteristics of the organisation, Project Management

Assignment Help:

M is a business that sells custom made computer-based information systems. Every customer order is for a unique system, which will contain experts from many functional areas within M. Every customer expects a high level of individual attention. Some systems take only four to six months to design and form and cost less than €50,000, whereas other systems cost various million Euros and can take up to three years to complete. Projects are continually being done and started. 

Identify the characteristics of the organisation that make it suitable for M to have a matrix structure.

The characteristics of M that are appropriate to it adopting a matrix organisational structure are as follows:

  • The business of M having of a series of projects which are custom made, which are difficult and require staff from a number of dissimilar functional areas;
  • The projects undertaken by M have dissimilar start and end dates, so the organisation is continually reassigning resources from project to project as single ends and another begins;
  • The projects undertaken by M are difficult so the staff benefit from also being assigned to a technical function (like as finance or procurement) where they can share knowledge and experience with colleagues in their functional teams;

 


Related Discussions:- Identify the characteristics of the organisation

Project strategy , what is the relationship between strategy and project ma...

what is the relationship between strategy and project management. what part do leadership and governance play in project. 3. What is the role of portfolio management and programme

Financial management and control in tertiay instittution, what are the limi...

what are the limitations of financial management and control in tertiary institutions

Market share in a high market growth industry, R Company produces a range o...

R Company produces a range of hair and beauty products. T, the Finance Director, and P, the Marketing Director, are reviewing the outcome of some product portfolio analysis which h

Initial project plan, o Does the project plan clearly identify a set of fun...

o Does the project plan clearly identify a set of functional increments leading to project completion? o Is the sequence of objectives consistent with both the risk priority and

Internal external factors influence organisational culture, Internal and ex...

Internal and external factors influence the organisational culture Culture facilitates internal integration and harmony as well as external adaptation according to environmental

Responsibilities of an event manager, Question 1: a) Outline the key r...

Question 1: a) Outline the key responsibilities of an Event Manager b) Give THREE clear working examples of possible event objectives for either a country, a resort, an or

Uses and benefits of risk breakdown structure, Uses and Benefits of RBS  ...

Uses and Benefits of RBS  The main uses and benefits of the RBS are outlined in this section.  Risk identification aid  Risk Breakdown Structure is used as a list that

Describe problems with functional project coordination, Question 1: "Ma...

Question 1: "Matrix structures are becoming more common and are likely to continue to do so in the future" (Field and Keller, 1998). a) Describe likely problems with functio

What are the major characteristics of a project, Question : (a) Organi...

Question : (a) Organizations and individuals have studied a number of projects that have both succeeded and failed and some common factors emerge. Can you give some reasons fo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd