How several hours of production time would you schedule, Operation Management

Assignment Help:

For the four basic configurations that follow, assume that the market is demanding product that must be processed by both Resource X and Resource Y for Cases I, II and III. For Case IV, both resources apply separate but dependent markets; that is, the number of units of output from both X and Y must be equal.

Plans are being made to produce a product that requires 40 minutes on Resource X and 30 minutes on resource Y. Assume that there is only one of each of these resources, and that market demand is 1400 units per month.

How many hours of production time would you schedule for X and Y? What would happen if both were scheduled for the same number of hours?

Case 1 Case 2

X ------> Y -------> Market Y ----> X -----> Market

Case 3

Market

^ Case4
|| Market Market
Assembly ^ ^
^ ^ | |
| | | |
| | | |
X Y X Y


Related Discussions:- How several hours of production time would you schedule

How much hours of production time would you schedule for x, Plans are being...

Plans are being made to produce a product that requires 40 minutes on Resource X and 30 minutes on resource Y. Assume that there is only one of each of these resources, and that ma

Describe why it is both a business pressure, Explain why IT is both a busin...

Explain why IT is both a business pressure and an enabler of response activities that counter business pressures?

Primary elements of each of the three kinds of risk control, What are the p...

What are the primary elements of each of the three types of risk control? Assume you are in a hazard hunt; list a few factors in your job that may contribute to a hazard and how li

Explain what is the glass ceiling, What is the glass ceiling, and why do yo...

What is the glass ceiling, and why do you think it has proven to be such a barrier to women and minorities?

Make a mixed plan for this problem by permitting backordered, X-Print Manuf...

X-Print Manufacturing makes laser printers. One plant assembles the PL-4000 model. Standards indicate that one worker can assemble five printers per day. This model costs about $35

Calculate the expected value of perfect information, A small building contr...

A small building contractor has recently experienced two successive years in which work opportunities exceeded the firm's capacity. The contractor must now make a decision on capac

States gross national product, States Gross National Product (GNP) Gr...

States Gross National Product (GNP) Gross Domestic Product (GDP) adjusted for foreign earnings.

Explain what kind of warning signals would you like, 1. What kind of warnin...

1. What kind of warning signals would you like fed back from PAC to MRP? 2. Lead times are sometimes called rubbery. What accounts for this concept of elasticity in lead times?

Aishat, A company has the following forecast demand for the next five month...

A company has the following forecast demand for the next five months: 1,600, 2,400, 3,200, 2,800, and 2,400. The following information is also available. current

Public sector - health care, Public Sector - Health Care 1. Increased...

Public Sector - Health Care 1. Increased consumer demands - increased performance measurement 2. Increased quality of service and choice demanded 3. Increasing salaries

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd