Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

brazing, Brazing Brazing is a group of welding processes, which produces...

Brazing Brazing is a group of welding processes, which produces, coalescence of materials by heating them to a specific temperature and by using a filler metal having a liquids a

Objectives of planning, What are the objectives of Planning, production and...

What are the objectives of Planning, production and control ? What are the decisions involved in PPC ? What are the information needed for these decisions ?

Fatigue loading on materials, what are the factors that affecting the fatig...

what are the factors that affecting the fatigue behaviour of materials?

Determine the need for insulation, Q. Determine the need for insulation? ...

Q. Determine the need for insulation? Equipment and piping shall be insulated as required for heat conservation, process heat control and personnel protection. The temperatu

Horizontal hinge, 2 x 2 m square gate opens clockwise on a horizontal hinge...

2 x 2 m square gate opens clockwise on a horizontal hinge located at point A, which is 100 mm below the centroid of the gate. The gate sits against solid rubber blocks which create

Roller conveyors, Roller conveyors are flat circular or spiral. They con...

Roller conveyors are flat circular or spiral. They consist of rollers supported in frames over which materials are allowed to move. They are driven through gravity. Genera

Heat loss in acylindrical pipe, Ask question #Minimum 1. Research the topic...

Ask question #Minimum 1. Research the topic of heat loss in a cylindrical pipe. Explain which laws of physics are used to discuss heat loss in a pipe, and briefly explain how the f

Explain butt joints, Butt joints- formed by placing the plates edge to edge...

Butt joints- formed by placing the plates edge to edge and welding them. Grooves are sometimes cut (For thick plates) on the edges before welding. According to the shape of the gro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd