Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

example of alteration of position and reference line method, Example of Al...

Example of Alteration of Position and Reference Line Method: Sketch the projections of a pentagonal prism edge of the base 50 millimeter long and height 90 millimeter, the axi

Som, Simple problem on direct stress and Bending stres

Simple problem on direct stress and Bending stress

Queuing model, ppt of applying queuing model in railway reservasion

ppt of applying queuing model in railway reservasion

Metal transfer, METAL TRANSFER The continuously fed electrode wire is mel...

METAL TRANSFER The continuously fed electrode wire is melted in the arc heat and the droplets thus formed at the wire tip are transferred to the weld pool. The way in which mater

Two stroke and four stroke engines, T w o Stroke and Four Stroke Engines:...

T w o Stroke and Four Stroke Engines: In  the two stroke engines thermodynamic cycle is completed in One revolution of crank shaft whereas in 4 stroke engines the cycle is c

Corrosion - erosion allowance, Q. Corrosion - Erosion Allowance? The re...

Q. Corrosion - Erosion Allowance? The required design life shall be based on written agreement between the user and the Engineering Contractor. Allowance specified shall be ba

Physics, State and explain parallelogram law of vectors

State and explain parallelogram law of vectors

Define application of electro discharge machining, Normal 0 fal...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Calculate the axial deflection and angle of rotation, Calculate the axial d...

Calculate the axial deflection and angle of rotation: Any open coiled helical spring along with 10 complete turns is built of 16 mm diameter steel rod, the mean radius of the

Find out diameter of steel wire, Find out diameter of steel wire: Q: ...

Find out diameter of steel wire: Q: A load of 5 KN is to be raised with help of steel wire. Find out diameter of steel wire, if maximum stress does not to exceed 100 MNm 2

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd