Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Reinforced concrete design, You are tasked with the analysis and design of ...

You are tasked with the analysis and design of the gravity and wind framing system for a 6-story office building. A part plan of the building is attached.  The plan dimensions o

Explain moulding sand for non-ferrous casting, Q. Explain Moulding Sand for...

Q. Explain Moulding Sand for Non-ferrous Casting? The melting point of non- ferrous metal is much lower than that of ferrous metals. Therefore, the moulding sands for non-ferr

Loosening a part with multiple fasteners services tips, Loosening a Part wi...

Loosening a Part with Multiple Fasteners: Loosening a part with multiple fasteners should be done from the outside to inside in a criss-cross pattern, loosening the small fastener

Find the magnitude of force, Find the magnitude of force: Q: The two ...

Find the magnitude of force: Q: The two parallel forces are acting at point A and B respectively is equivalent to force of  100 N acting downwards at point C and coupl

Stitch welding, Stitch Welding This is a variation of spot welding, in ...

Stitch Welding This is a variation of spot welding, in which a series of overlapping spot welds are made in the same manner as stitching cloth. Stitch welding may be performed

Effects of air resistance. , Traveling at a speed of 16.0 m/s, the driver o...

Traveling at a speed of 16.0 m/s, the driver of an automobile suddenly locks the wheels by slamming on the brakes. The coefficient of kinetic friction between the tires and the roa

Explain end relief angle, Explain End Relief Angle It is the angle betw...

Explain End Relief Angle It is the angle between the plane perpendicular to base and end flank. The angle prevent\s the cutting tool from rubbing against the job where as if th

Design varies with scale of operation, Design varies with scale of operatio...

Design varies with scale of operation The design of a fermenter varies with scale of operation from lab (1-20L), to pilot (up to 5000L) to production (to >200,000L) scales. Th

Explain the side relief angle, Explain the Side Relief Angle It is angl...

Explain the Side Relief Angle It is angle made by flank of a tool and plane perpendicular to base just under the side cutting edge. if the side relief angle is very large the c

Obtain the closed loop transfer function, Question: The block diagram o...

Question: The block diagram of a dc servo motor feed drive is shown   Obtain the closed loop transfer function relating the output to the disturbance T L while V

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd