Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Heat exchangers - air-conditioning guidelines, Q. Heat Exchangers - air-con...

Q. Heat Exchangers - air-conditioning guidelines? Location, size and capacity clearly indicated. Control valves indicated. Space for tube removal, keep space clear of pipes, va

Evaluate elongation of bar of varying cross section, Evaluate elongation of...

Evaluate elongation of bar of varying cross section: How you evaluate elongation of bar of varying cross section:? Sol.: Take bar made up of different lengths and which

Find out the velocity of the chain, Find out the velocity of the chain: ...

Find out the velocity of the chain: Figure shows a metal chain ABC where portion BC is of length 0.4 metres and is hanging vertically, & portion AB of length 0.8 metres rests

Corrosion in boiler, Q. Corrosion in Boiler? With proper BFW treatment,...

Q. Corrosion in Boiler? With proper BFW treatment, and maintaining pH within a certain range (9.2 to 9.4) and removing oxygen from the system, a stable passive film will be for

Boiler, What is scale formation in case of a boiler

What is scale formation in case of a boiler

Calculate the final velocities of the two masses, Calculate the final veloc...

Calculate the final velocities of the two masses: A mass of 10 kg moving along with a velocity of 10 m/sec along x direction follows another mass of 4 kg moving with 5 m/sec i

Calculate the thickness of insulation, A hot gas at 300°C flows through a l...

A hot gas at 300°C flows through a long metal pipe 100mm outer diameter and 3mm thick. From the standpoint of safety and energy conservation, mineral wool insulation of thermal con

What is manifolds, Manifolds The surface of a solid must satisfy some c...

Manifolds The surface of a solid must satisfy some conditions so that the resulting solid is well-behaved. This is the so-called manifold condition. While recent research has s

Determine the frictional resistance, Determine the frictional resistance: ...

Determine the frictional resistance:  (i) A train having weight 400 kN is running up an inclined path of 1 in 100 at a steady speed of 54 km/hour. If the frictional resistance

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd