Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Calculate efficiency of turbine, (a) Explain briefly the functions of the s...

(a) Explain briefly the functions of the spiral casing guide vanes, and draft tube of a reaction water. (b) A Kaplan turbine developing 3250 KW under a head of 6m has a draft tu

Steam power plant , Steam power plant: Steam power plant converts heat...

Steam power plant: Steam power plant converts heat energy Q from combustion of fuel into mechanical work W of shaft rotation which is used to generate electricity. This ty

Efficiency test on sand blasting, Efficiency Test on Sand Blasting:   ...

Efficiency Test on Sand Blasting:             After the study on sand blasting, the result was acceptable and the next step is planning to make order for new machine and searc

Find out moment of inertia, Find out Moment of Inertia: Find out Momen...

Find out Moment of Inertia: Find out Moment of Inertia of an I shaped area around its centroidal axis as illustrated in Figure.  Solution  (i)        The area of

Duty cycle, Duty cycle The concept of duty cycle is to be clearly under...

Duty cycle The concept of duty cycle is to be clearly understood before operating any machine. Unlike the arc welding power sources, the resistance welding power sources are de

Isothermal transformation, Isothermal Transformation: Austenite is no...

Isothermal Transformation: Austenite is not normally converted in martensite instantly but the procedure continues for some time. Various steels take various time for full tr

Path function, how to prove that work done is a path function

how to prove that work done is a path function

Process of alloy materials sampling, Q. Process of Alloy Materials Sampling...

Q. Process of Alloy Materials Sampling? The following alloy-materials require a minimum of 10% per lot representative PMI sampling. If any incorrect material is found in repres

How many types of foundations are there, How many types of Foundations are ...

How many types of Foundations are there Foundations are broadly classified into two types, viz., shallow and deep foundations with respect to  the width (B) and depth (D) below

Calculate the spindle speed in milling operation, Calculate the Spindle Spe...

Calculate the Spindle Speed in Milling Operation Calculate the spindle speed (N) if a copper job is to be milled by  (a) stellite cutter  (b) cemented carbide cutter.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd