Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Determine the value of registers, The ARM microprocessor has 32 bit instruc...

The ARM microprocessor has 32 bit instructions and 32 bit registers. Explain why this means that immediate addressing cannot be used to load a register with a 32 bit constant. T

Capp for casting and welding, CAPP for Casting and Welding In this , w...

CAPP for Casting and Welding In this , we have studied the CAPP systems for Casting and Welding processes. Compared to the traditional (manual) process planning methods, CAPP

Wrought aluminium alloys, Wrought Aluminium Alloys Extrusion ingots an...

Wrought Aluminium Alloys Extrusion ingots and sheets are cast through semi-continuous direct chill method. The sheet ingots are scalped in which about 12 millimeter of ingot s

Determine the moment of resistance of the flitched beam, Determine the mome...

Determine the moment of resistance of the flitched beam: A flitched beam consists of a wooden beam of width 120 mm & depth 250 mm & mild steel plates of thickness 10 mm & widt

What is epoxy powder, Q. What is Epoxy Powder? The coating manufacturer...

Q. What is Epoxy Powder? The coating manufacturer shall be consulted as to the product best suited to the Applicator's speed of coating, pipe diameter and wall thickness, and t

Reduce system to a single force and couple, Reduce system to a single force...

Reduce system to a single force and couple: Q: A system of parallel forces is acting on rigid bar as shown in the figure given below. Reduce this system to  a single force

Multiview Projections, I''m having trouble with some drawing questions, whe...

I''m having trouble with some drawing questions, where I am given two orthogonal projections (front and side view) of an unknown 3D object, I have to draw the top view using a mite

Pmi testing of alloy materials, Q. Show PMI testing of alloy materials? ...

Q. Show PMI testing of alloy materials? Suppliers and Construction Subcontractors are required to verify or conduct PMI testing of alloy materials that they procure and use and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd