Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Cost of processing the payroll, The processing of payroll for the 10,000 wo...

The processing of payroll for the 10,000 workers in a large rm can either be done using 1 hour of computer time (signed by K) and no clerks or with 10 hours of clerical time (sign

Evaluate boiler efficiency, The following data were obtained in a boiler tr...

The following data were obtained in a boiler trail: Mass and temperature of feed water: 680 kg/hr and 20 0 C, Steam temperature and its pressure : 15bar and 300 0 C, Coal used

Metals, what effects do external factors have on engineering metals

what effects do external factors have on engineering metals

Processing sequence for manufacturing coupling nut, Processing Sequence for...

Processing Sequence for Manufacturing Coupling Nut Referring to the Figure 12 below, we now illustrate the processing sequence for manufacturing coupling nut.

Simply supported beam, Simply Supported Beam: Simply Supported Beam: ...

Simply Supported Beam: Simply Supported Beam: The beam on which both ends are supported, either by point load or hinged or roller support.

Show mass energy relation, Q. Show Mass energy Relation? Until the time...

Q. Show Mass energy Relation? Until the time of Einstein, mass and energy were considered as two different physical quantities. But in 1905, with the help of postulates of the

Manufacturing technology, Details of rolling process,Different rolling meth...

Details of rolling process,Different rolling methods,

Determine the spring force, A double shoe brake as shown in the figure is c...

A double shoe brake as shown in the figure is capable of absorbing a torque of 1400 N-m. The diameter of the brake drum is 350mm and the angle of contact of each shoe is 100°. If t

Explain principle of design of jig and fixture, Explain Principle of Design...

Explain Principle of Design of Jig and Fixture While designing jigs and fixtures following considerations should kept in mind: Reduction of idle time. Rigidity

Order quantity and reorder point, Example: Order Quantity and Reorder Point...

Example: Order Quantity and Reorder Point: Daily demand for a particular product manufactured by ABC company is distributed normally with a mean of 30 and standard deviation o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd