Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Determine the actual average pressure, A multiple disc clutch, steel on bro...

A multiple disc clutch, steel on bronze, is to transmit 4.5 kW at 750 r.p.m. The inner radius of contact is 40mm and outer radius of the contact is 70 mm. The clutch operates in oi

Compute the coefficient of friction at block, Compute the coefficient of fr...

Compute the coefficient of friction at block: The frame shown in Figure rotates about a vertical axis. The coefficient of friction under block A is 0.4. Compute the coefficien

Determine contact reactions and force, Determine contact reactions and forc...

Determine contact reactions and force: Figure given below shows a sphere resting in smooth V shaped groove and subjected to a spring force. The spring is compressed to

Calculate tensions in chain and chord - mechanics, Calculate tensions in ch...

Calculate tensions in chain and chord - Mechanics: A lamp of mass 1Kg is hung from the ceiling by a chain and is pulled aside by horizontal chord until the chain makes an ang

Thermodynamics, Show that the entropy maximum principle encountered in the ...

Show that the entropy maximum principle encountered in the study of isolated system is equivalent to the statement that the nonflow exergy of an isolated system is destined to decr

What are the approaches to the design of retaining walls, What are the appr...

What are the approaches to the design of retaining walls? The approach to the design of retaining walls can be started as follows: a. Chosse a trial dimension of the wall

Types of electron beam welding gun, TYPES OF ELECTRON BEAM WELDING GUN ...

TYPES OF ELECTRON BEAM WELDING GUN   Diode (Cathode - anode) Gun : In this gun, the beam shaping electrode and the emitter are both at the same electrical potentials. These

Process planning, we have to design crane we did already with calculation r...

we have to design crane we did already with calculation remaining is process planning

Steps for solving problem for finding maximum power, Step s for Solving Pr...

Step s for Solving Problem for Finding Maximum Power: 1. Use formula stress (σ) = force (Maximum Tension)/Area Where;  Area = b.t that is, T max = σ.b.t 2. Unit mass (

Vibration, On the Moodle site just below the assignment you will find data ...

On the Moodle site just below the assignment you will find data from a slow sine sweep test conducted on a car on a "four-post" road simulator for the frequency range 0 to 20 Hz in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd