Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Applications of high temperature materials, Q. Applications of high tempera...

Q. Applications of high temperature materials? A brief description of materials of construction used for common high temperature components in furnaces, boilers, superheaters,

Tensile and compressive force - mechanics, Tensile and Compressive Force: ...

Tensile and Compressive Force: T ensil e Forces A force, that pulls the body, is called as tensile force. Here member AB is tension member carrying tensile force P. As

Burner management - discrete controls for steam generators, Q. Burner Manag...

Q. Burner Management - Discrete Controls for steam generators? The burner management system shall control the generator operation during pre-purge, light off, normal operation,

Calculate the net positive suction head, A pump station has been designed t...

A pump station has been designed to lift water out of a 6 metre deep pit (vented to atmosphere) via a centrifigual pump mounted at ground level.                    Liquid condit

Washing and drying a motorcycle, Washing and Drying a Motorcycle :  It is ...

Washing and Drying a Motorcycle :  It is important to wash and dry the motorcycle before servicing. It would ensure cleanliness during the service and would not allow any dust ent

Compound springs how do they work?, Ask Compound springs how do they workqu...

Ask Compound springs how do they workquestion #Minimum 100 words accepted#

magnitude of the maximum bending moment , Solve the following three questi...

Solve the following three questions of the beam ABCD. Note that A is a fixed end; B is apin connection; C is a roller support; and D is a free end.    1)  Sketch the quantita

Generation of continuation, Generation of Continuation It is assumed th...

Generation of Continuation It is assumed that a partial schedule (which may be empty schedule) is given. For this partial schedule, a number of possible continuations is genera

Planimeter, procedure for measuring area of square by planimeter

procedure for measuring area of square by planimeter

Torque transmission-various factors in clutch design , Torque Transmission ...

Torque Transmission : The clutch should be able to transmit the maximum torque of the engine under all conditions. It is usually designed to transmit 125 to 150 percent of the max

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd