Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Steps for F-test, Steps for F-test The Steps followed in the F-Test are...

Steps for F-test The Steps followed in the F-Test are as follows: (A) State the hypothesis: Ho: Relationship between Y and all Xs is not significant. HA: Relationship bet

Machine manufacturing technologies, Write an Machining route line and opera...

Write an Machining route line and operating line of a technological procession #Minimum 100 words accepted#

Iterature review, I have literature review and the title is "the effect of...

I have literature review and the title is "the effect of fluid cooling on the performance of building integrated photovoltaic thermal systems. Using some BIPVT prototypes measure

energy method, A semi circular frame of flexural rigidity EI is built at A...

A semi circular frame of flexural rigidity EI is built at A and caries a vertical load W at B. calculate the magnitude of the vertical and horizontal deflection at B and hence the

determine the minimum cross section area of graph, To design a cantilevere...

To design a cantilevered truss to support the loads shown in the figures, two layouts are proposed as shown in Figs. A and B. All truss members are steel with allowable stress of 2

Positive material identification testing, Q. Positive Material Identificati...

Q. Positive Material Identification Testing? Any physical evaluation or a test of a material to confirm that the material which has been or will be placed into service is consi

Explain about the pedestals as construction engineering, Explain about the ...

Explain about the pedestals as construction engineering. Introduction of pedestals enables the construction engineers to make up levels to supply larger bearing areas to the fo

Show construction subcontractor responsibilities, Q. Show Construction Subc...

Q. Show Construction Subcontractor Responsibilities? The Supplier or Construction Subcontractor is responsible for: • Employing qualified PMI technicians • Performing PMI

Pulsed dc welding, Pulsed DC Welding Pulsed DC involves the repetitive ...

Pulsed DC Welding Pulsed DC involves the repetitive variation in arc current from a background (low) value to a peak value. Adjustments of the pulse current time, background cu

Piston rings-basic components of engine , Piston Rings: Piston rings (Fig...

Piston Rings: Piston rings (Figure), fitted into the grooves around the piston, provide a tight sealing effect between the piston and the cylinder wall thus preventing leakage of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd