Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Determine the mean radius of an open coiled spring, Determine the mean radi...

Determine the mean radius of an open coiled spring: Determine the mean radius of an open coiled spring of helix angle of 38 o , to give a vertical displacement of 20 mm and an

Slab hanging - mechanics, Slab hanging: Three similar uniform slabs ...

Slab hanging: Three similar uniform slabs each having length '2 a ' are resting on edge of table as shown in the figure given below. If each slab is overhung by the maximum

Copper-beryllium alloys, Copper-Beryllium Alloys Copper-beryllium allo...

Copper-Beryllium Alloys Copper-beryllium alloys comprise between 0.6 to 2% Be and 0.2 to 2.5% Cobalt. Such alloys can be precipitation hardened and cold worked to improve a te

Computer integrated manufacturing, the component of computer integrated man...

the component of computer integrated manufacturing with the diagram

Describe about austenitic stainless steels, Q. Describe about Austenitic st...

Q. Describe about Austenitic stainless steels? Austenitic stainless steels (300 series) generally exhibit very good corrosion resistance in sulphuric acid service for low conce

Slider crank mechanism, What is the mathematical displacement equation and ...

What is the mathematical displacement equation and its derivatives?

System of parallel forces - mechanics, System of parallel forces: A r...

System of parallel forces: A rigid body is subjected to system of parallel forces as shown in the figure. Reduce this system to, ( i ) A single force system ( i

Calculate the cycle and production rate , Calculate the Cycle and Productio...

Calculate the Cycle and Production Rate for Single-Machine Robotic Cell Determine the cycle and production rate for a single-machine robotic cell for an 8-hr shift if the syst

marginal rate of technical substitution?, Assume the production function f...

Assume the production function for a rm is given by the equation Q = L √K. Graph the isoquants corresponding to Q = 10, Q = 20, and Q = 50. Do these isoquants exhibit diminishing

Gantry crane, A gantry crane shown in figure above acts an auxiliary to...

A gantry crane shown in figure above acts an auxiliary to bridge cranes. It is provided with wheels and can be moved from open place to another as per requirements.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd