Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Capp for machining process, CAPP for Machining Process This explained ...

CAPP for Machining Process This explained mainly two different approaches to Computer Aided Process Planning, i.e.  (a) Variant approach, and  (b) Generative approach.

Find the velocity of spacecraft, A space craft ‘A' has velocity 0.9 c relat...

A space craft ‘A' has velocity 0.9 c relative to the earth. Another spacecraft ‘B' overtakes A with relative velocity 0.5 c. Find the velocity of spacecraft B relative to the groun

Safety from corrosive chemicals, Q. Safety from Corrosive Chemicals? Sa...

Q. Safety from Corrosive Chemicals? Safety showers and eyewash stations shall be provided in areas where corrosive chemicals are stored and handled. They should be located so t

Screw jack and friction, Give the equivalence of screw jack and friction on...

Give the equivalence of screw jack and friction on an inclined plane

Find out ratio of upper end area to lower end area of bar, Find out ratio o...

Find out ratio of  upper end area to lower end area  of bar of uniform strength Sol : The figure given to us shows a bar subjected to external tensile load P. If bar had be

General phase of value engineering, General Phase of Value Engineering: ...

General Phase of Value Engineering: Steps- 1. Prepare a strong foundation for the value study. Extension of auger in screw conveyer in hydraulic paver machine is to be do

Angle of friction, Angle of friction:   It can be defined as t...

Angle of friction:   It can be defined as the angle made by resultant of normal reaction ( R ) and limiting force of friction ( F ) with normal reaction ( R ). Let,

Longitudinal strain produced - hollow cast iron cylinder, Longitudinal stra...

Longitudinal strain produced - hollow cast iron cylinder: A hollow cast iron cylinder 4 m long, 300 mm is the outer diameter, and thickness of metal 50 mm is subjected to cen

Calculate mean effective pressure of engine, Calculate mean effective press...

Calculate mean effective pressure of engine: A 4 stroke diesel engine is having length of 20 cm and diameter of 16 cm. The engine is generating indicated power of 25 KW when

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd