Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Beam, Beam: What do you mean by Beam, and Shear force and bending mom...

Beam: What do you mean by Beam, and Shear force and bending moment diagrams? Sol.: A beam is structural member whose longitudinal dimensions (that is width) is large co

Slipping of belt, the effect of slip of belt on the pulleys on the velocity...

the effect of slip of belt on the pulleys on the velocity ratio of belt drive?

Friction welding, FRICTION WELDING In this, friction is employed to genera...

FRICTION WELDING In this, friction is employed to generate heat b/w two sliding or rotating metal surfaces. This process is usually carried out by placing the pieces to be welded

Illustrate wood and silica flour, Q. Illustrate Wood and Silica Flour? ...

Q. Illustrate Wood and Silica Flour? Wood Flour : It is ground wood particles or other cellulose materials such as grain hulls. They serve the same purpose as cereals except t

Determine the stresses in the shell, Determine the stresses in the shell: ...

Determine the stresses in the shell: A cylindrical boiler is 2.5 m in diameter and 20 mm in thickness and it carries steam at a pressure of 1.0 N/mm2. Determine the stresses i

the entropy change of the universe, Two insulated and identical tanks are ...

Two insulated and identical tanks are filled with nitrogen.  One tank is at 1 bar, 250 o C and the other is at 5 bar, 25 o C.  If the two tanks are connected with a pipe and the v

Banking of a cyclist, what is the formula for measuring the safe speed to d...

what is the formula for measuring the safe speed to drive for a cyclist

Estimate the cutting time, Estimate the Cutting Time A surface 115 mm ...

Estimate the Cutting Time A surface 115 mm wide and 250 mm long is to be rough milled with a depth of cut of 6 mm by a 16-tooth cemented carbide face mill 150 mm in diameter.

Difference between intrinsic and extrinsic semiconductors, Question: (a...

Question: (a) (i) Describe the difference between intrinsic and extrinsic semiconductors. (ii)Is it possible for compound semiconductors to exhibit intrinsic behaviour? Desc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd