Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Show the geometric similarity, Q. Show the Geometric Similarity? When m...

Q. Show the Geometric Similarity? When model is required to provide an aid merely for visualisation, scaler reproduction of form is sufficient which is termed Geometric Similar

Find out power transmitted by belt, Find out power transmitted by belt: ...

Find out power transmitted by belt: A belt is running over pulley of 1.5m diameters at 250RPM. The angle of contact is 120º and coefficient of friction is 0.30. If maximum te

Calculate stress in the bolts, A new high temperature alloy has been dev...

A new high temperature alloy has been developed with creep properties as follows: stress exponent, m = 4.5, activation energy, Q = 110,000 J/mol and pre-exponential constant,

COMPRESSOR PROBLEM FROM CUSTOMER, OUR CUSTOMER HAD APROBLEM WITH OUR CUSTO...

OUR CUSTOMER HAD APROBLEM WITH OUR CUSTOMER ,AND ME AS AMECHANICLAL ENGINEER FOUND THE PROBLEM

Determine the crippling load and safe load, A hollow mild steel tube 6 m lo...

A hollow mild steel tube 6 m long 4 cm internal diameter and 6 mm thick is used as a strut with both ends hinged. Determine the crippling load and safe load taking factor of safety

Determine the required feed rate of seawater, Seawater is boiled in a 5 lit...

Seawater is boiled in a 5 liter kettle to produce drinking water.  In class we solved the steady-state version of this problem.  Here you are asked to consider the transient period

Define heat treatment and surface treatment processes, Heat Treatment and S...

Heat Treatment and Surface Treatment Processes Heat treatment processes are employed to improve of a work piece. The category includes the processes. Annealing, Normalizing,

Drainage of the railway track - construction of railway line, Drainage of t...

Drainage of the Railway Track: It is necessary to keep the embankment free from water. This is done by providing side ditches, all along the edge of the embankment, and leadi

Determine the processing time of iges, Determine the Processing Time of IGE...

Determine the Processing Time of IGES File Size/Processing Time: IGES was heavily criticized for requiring large files that took hours or even days to parse, given the averag

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd