Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Define the winged-edge representation, The Winged-Edge Representation P...

The Winged-Edge Representation Perhaps the oldest data structure for a b-rep is Baumgart's winged-edge data structure. It is quite different from that of a wire-frame model, be

LPP, (Hint Minimization problem -min X1 + X2, s.t. 2X1 + X2 = 12, X1 + 6X2 ...

(Hint Minimization problem -min X1 + X2, s.t. 2X1 + X2 = 12, X1 + 6X2 = 24, 5X1 + 8X2 = 24; X1, X2 = 0).

Calculate the diameter of the single pipe, a) Three pipes of lengths 800m, ...

a) Three pipes of lengths 800m, 400m, 500m and of diameter 500mm, 400mm and 300mm respectively are connected in series. Pipes are to be removed by a single pipe of length 1700m. Ca

Heat loss in acylindrical pipe, Ask question #Minimum 1. Research the topic...

Ask question #Minimum 1. Research the topic of heat loss in a cylindrical pipe. Explain which laws of physics are used to discuss heat loss in a pipe, and briefly explain how the f

Resultant of coplanar concurrent force system, Resultant of coplanar concur...

Resultant of coplanar concurrent force system: The resultant force, of given system of forces can be found out by the resolution method, which is discussed below: Assume th

Transmission system , Transmission System: In a two-wheeler, the transmiss...

Transmission System: In a two-wheeler, the transmission system means the whole arrangement that transmits the power from the engine crankshaft to the rear wheel.

Production, what is tooling economics, machine economics and optimization

what is tooling economics, machine economics and optimization

Determine the excavation of soil, Determine the Excavation of soil Exc...

Determine the Excavation of soil Excavation of soil in open well foundations is done  by dredging with grab buckets or similar equipment. The volume of excavated soil always e

Desgin of furnce - combustion chamber, Desgin of furnce - combustion chambe...

Desgin of furnce - combustion chamber: • Deside on type of furnace :need review of furnace types (grete,fluidized bed,puluerised coal or other. • Sectch of furnace design with

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd