Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Show the support locations for truckable skid, Q. Show the support location...

Q. Show the support locations for truckable skid? Unless instructed otherwise by Engineer, support locations for truckable skid shall be determined by skid Vendor. Support loca

Stress strain curves, Stress Strai n Curves (Tension): When a bar or ...

Stress Strai n Curves (Tension): When a bar or specimen is subjected to a gradually increasing axial tensile load, the strains and stresses can be found out for number of loa

Example of manufacturing lead time (mlt), Example of Manufacturing Lead Tim...

Example of Manufacturing Lead Time (MLT) A certain part is generated in a batch size of 100 units. The batch should be routed through five operations to complete the processin

Calculate the probable wall thickness of the tank, The background for the o...

The background for the oil storage tank failure is as follows: the tank involved was a four million gallon circular tank that was built in 1940 for Ashland Oil Company in Cleveland

Steps of engine oil replacement and top-up, Engine Oil Replacement and top ...

Engine Oil Replacement and top up steps • The engine oil should be changed only when motorcycle has run through the prescribed kilometers. • Change the engine oil every 4000 k

Assignment, AskTask 2 (3 questions) Material engineers should be conversant...

AskTask 2 (3 questions) Material engineers should be conversant of various materials, their properties, manufacturing process involved, environmental issues, monetary issues and mo

Design and sketch a knuckle joint to transmit a tensile load, Give a genera...

Give a generalized definition of factor of safety. Illustrate the factors responsible for Un-certainities in design necessitating a suitable factor of safety. How is ‘factor of saf

Thermodynamics, we can use in proove of energy is a propertyof system we ca...

we can use in proove of energy is a propertyof system we can use (E) instead of (dQ-dW)

Gas metal arc welding (gmaw), GAS METAL ARC WELDING (GMAW) GMAW is abbr...

GAS METAL ARC WELDING (GMAW) GMAW is abbreviation for Gas shielded Metal Arc Welding. Here fusion is achieved by an electric arc formed between work piece and process is called

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd