Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Explain tee joints, Tee joints -The square tee joint requires a fillet weld...

Tee joints -The square tee joint requires a fillet weld that can be made on one or both sides. It can be used for light or fairly thick materials. For maximum strength, considerabl

Wilson hartnell governor, how to design and fabricate wilson hartnell gover...

how to design and fabricate wilson hartnell governor?

Otto cycle - thermodynamics, Ott o Cycle (1876): This cycle consists...

Ott o Cycle (1876): This cycle consists of the two reversible adiabatic processes and the two constant volume processes as shown in the figure given below on P - V and T -

#strength of materials, Distribution of shearing stresses on l--sections an...

Distribution of shearing stresses on l--sections and miscellaneous sections

Find out power transmitted by belt, Find out power transmitted by belt: ...

Find out power transmitted by belt: A belt is running over pulley of 1.5m diameters at 250RPM. The angle of contact is 120º and coefficient of friction is 0.30. If maximum te

Intermodular piping connections, Q. Intermodular Piping Connections Ali...

Q. Intermodular Piping Connections Alignment of pies shall be achieved as detailed in the construction drawings. Special attention shall be paid to the alignment and installati

Define economics order quantity, a) Define Economics Order Quantity. Derive...

a) Define Economics Order Quantity. Derive, using neat diagram, the mathematical formula for economic order quantity. b) The purchase manager of an industrial unit is placing on

the centripetal force acting on the ball, A child is twirling a 0.0106 kg ...

A child is twirling a 0.0106 kg ball on a string in a horizontal circle whose radius is 0.096 m. The ball travels once around the circle in 0.540 s. (a) Determine the centripeta

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd