Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

What are the two ways of pile foundation, What are the two ways of pile fou...

What are the two ways of pile foundation Pile foundations can be installed in two ways. Timber, steel and precast concrete piles, are driven from the ground using hammers till

Axial flow turbine, The mass flow rate is 28kg/s in an axial flow gas turbi...

The mass flow rate is 28kg/s in an axial flow gas turbine that develops 3.5MW. The stagnation conditions are 780KPa and 730 deg.C. at the entry. At the exit of the nozzle, the stat

Find the maximum torque - i-section, Find the maximum torque - I-section: ...

Find the maximum torque - I-section: An I-section 150 × 80 mm has flanges 6 mm thick and web 4 mm thick. Discover the maximum torque that may be safely applied if the shear st

Compute the diameter of a solid shaft, Compute the diameter of a solid shaf...

Compute the diameter of a solid shaft: Compute the diameter of a solid shaft transmitting 150 kW at 25 rpm, if the maximum shear stress in the shaft is not to exceed 70 MPa. C

Evaluation of force exerted by jet on the plate, (a) What are the assumptio...

(a) What are the assumptions made during evaluation of force exerted by jet on the plate ? (b) A jet of water which has diameter of 8 cm. issues with a velocity of 40 m/sec. and

Shielding gas-argon-advantages of argon, Argon Argon is approximatel...

Argon Argon is approximately one and one third times as heavy as air and ten times heavier than helium. Argon, after leaving the torch nozzle, forms a blanket over the weld

Purpose of internal review, Q. Purpose of Internal review? The Project ...

Q. Purpose of Internal review? The Project Engineer in consultation with affected disciplines decides the timing of an internal review of IFR issue drawings. Each involved dis

DESIGN, HOW DO I DESIGN A COMPONENT FOR IMPACT STRENGTH FOR IMPACT LOAD AT ...

HOW DO I DESIGN A COMPONENT FOR IMPACT STRENGTH FOR IMPACT LOAD AT LOWER TEMPERATURE

Systematic layout planning, What are the primary benefits of using computer...

What are the primary benefits of using computerized layout procedures vs. Systematic Layout Planning (SLP) procedures done by hand?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd