Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Angle of twist is zero on the shaft, Angle of twist is zero on the shaft: ...

Angle of twist is zero on the shaft: A shaft 10 m long and 100 mm diameter during its length is fixed at the ends and is subjected to two opposite torques of 8 kN-m and 10 kN-

Introduction and over view of various manufacturing process, Introduction A...

Introduction And Over View Of Various Manufacturing Process The main aim behind advances in engineering and technology has been to raise the standard of living of man and to ma

Product life-cycle management, Product life-cycle management: There ha...

Product life-cycle management: There have also been changes in the use of some pre-existing data formats. Open associations have been formed to encourage some formats to becom

Explain external pressure design, Q. Explain External Pressure Design? ...

Q. Explain External Pressure Design? Determine requirements for external pressure based on the expected operation of the vessel, and add a suitable operating margin to establis

Relation for fin insulated tip and the heat dissipation, Derive the relatio...

Derive the relation for a fin insulated at the tip and the heat dissipation?

Calculate the diameter of the single pipe, a) Three pipes of lengths 800m, ...

a) Three pipes of lengths 800m, 400m, 500m and of diameter 500mm, 400mm and 300mm respectively are connected in series. Pipes are to be removed by a single pipe of length 1700m. Ca

Describe the term critical insulation thickness, Q. Describe the term ‘Crit...

Q. Describe the term ‘Critical Insulation thickness'. What is its significance? Derive an expression for the critical insulation radius of a spherical system. A bar of square cr

Sequecing problm, What is the sequence of this problem Job- 1 2 3 4 5 6 7 ...

What is the sequence of this problem Job- 1 2 3 4 5 6 7 M/c M1 4 13 16 7 11 12 10 M2 9 11 11 7 13 2 4

Evaluate the speed of shaft, Two shafts A and B are co-axial. A gear C (50 ...

Two shafts A and B are co-axial. A gear C (50 teeth) is rigidly mounted on shaft A. A compound gear D-E gears with C and an internal gear G. D has 20 teeth and gears with C and E h

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd