Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Evaluation of force exerted by jet on the plate, (a) What are the assumptio...

(a) What are the assumptions made during evaluation of force exerted by jet on the plate ? (b) A jet of water which has diameter of 8 cm. issues with a velocity of 40 m/sec. and

#title.cutting tool life, what is relation between tool life and cutting sp...

what is relation between tool life and cutting speed?

Calculate the maximum bending moment, A shaft is supported on bearings A an...

A shaft is supported on bearings A and B, 800 mm between centres. A 20° straight tooth spur gear having 600 mm pitch diameter, is located 200 mm to the right of the left hand beari

Preliminary stress analysis, Preliminary stress analysis work will start ea...

Preliminary stress analysis work will start early in the detail engineering phase after completion of equipment layout and piping study drawings. The piping required to be analyzed

Scope of corrosion assessment design, Q. Scope of corrosion assessment desi...

Q. Scope of corrosion assessment design? The purpose of this guideline is to describe the common corrosion damaging modes and mitigation methods and provides recommended materi

Evaluate the velocity ratio, (a) A geometrically similar model of spillway ...

(a) A geometrically similar model of spillway is to be laid to a scale of 1 in 50. Evaluate the velocity ratio, discharge ratio and acceleration ratio. (b) If model prototype ra

Corrosion control in oil-treating equipment, Q. Corrosion Control in Oil-Tr...

Q. Corrosion Control in Oil-Treating Equipment? Bitumen provides adequate internal protection for Inlet Slug Catcher, FWKO and Treater. Due to high operating temperature, inter

Determine power required and the cop of the system, A Boot Strap Cooling sy...

A Boot Strap Cooling system of 10 TR capacity is used in an aeroplane. The ambient air pressure and temperature are 0.85 and 20 0 C bar respectively. The pressure of air increases

Economic order quantity, Economic Order Quantity: Assume an economic o...

Economic Order Quantity: Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stockin

Determine the rate of heat removal - mechanics, Determine the rate of heat ...

Determine the rate of heat removal: Carbon dioxide passing through heat exchanger at rate of 100kg/hr is cooled down from  800 0 C to 50 0 C . Write down the steady flo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd