Give the procedure of the Delphi method.
1. The co-ordinator shows a specification and estimation form to each expert.
2. Co-ordinator calls a group meeting in which the experts discuss estimation issues with the coordinator and each other.
3. Experts fill out produces anonymously.
4. Co-ordinator prepares and distributes a summary of the estimates.
5. The Co-ordinator then calls a group meeting. In this meeting the experts mostly discuss the points where their estimates differ widely.
6. The experts again fill out produces anonymously.
7. Again co-ordinator edits and summarizes the forms, repeating steps 5 and 6 unless the co-ordinator is satisfied with the overall prediction synthesized from experts.
Define software scope. The first software project management activity is the determination of software scope. Scope is defined answering the following questions. Context: Wh
pls explain how to calculatethe cyclomatic complexity and independent paths Determine the cyclomatic complexity of the code ( (iii) Identify all the independent paths
What is Requirement Traceability? Explain its importance. Requirement Traceability is mapping of needs to test cases. There are two major traceability: Forward and Backward. It
State the strategies of Software testing Two testing strategies are present. i) Code Testing: Code testing strategy examines the logic of the system. In this, analyst deve
Write about drivers and stubs. Drivers and stub software require to be developed to test incompatible software. The " driver" is a program that accepts the test data and pri
QUESTION (a) Compare and contrast between Project logic evaluation (PLE), Networking and Scheduling (b) Discuss how the true cost of defects can often be higher than the ini
What is Branch coverage? Ans) Test coverage criteria which needs that for each decision point each possible branch be implemented at least once. Syn: decision coverage. Contrast
What is requirement engineering? Requirement engineering is the process of establishing the services that the customer needs from the system and the constraints under which it
Level 5 KPAs 1)Defect Prevention (DP): It discovers causes of defects and devises techniques which prevent them from recurring. 2)Technology Change Management (TCM): It
When is RTM (Requirement traceability matrix) prepared - after or before test case designing? - RTM is prepared before test case designing. - Requirements must be traceable
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd