Give an example of critical path by activity and duration, Project Management

Assignment Help:

Give an example of demonstrating a network or critical path by given activity and duration.

Activity                      Duration (Wks)                   Preceded by

A                                 5                                              -

B                                 4                                              -

C                                 3                                              B

Every activity is denoted through a letter and the expected duration specified. A and B could begin instantly, thus can start on the similar circle. C should be preceded from B for example C cannot start till B has been finished.
Network (critical path) diagram:

1891_Example of critical path.png

a. The elapsed or expected completion time of the project is seven weeks

b. The critical path activities are of B and C for example both must be finished within their predicted durations, or else the project will be longer into duration than seven weeks.

c. Activity A is a non-critical activity and it would have a float time of two weeks, which is since it only takes 5 weeks to finish, has nothing preceding or succeeding this, hence specified the elapsed time of the project is 7 weeks; this could finish as late as this.


Related Discussions:- Give an example of critical path by activity and duration

Competitive priorities, Explain the basic competitive priorities considered...

Explain the basic competitive priorities considered while formulating operations strategy by a firm?

Create a 2-level wbs and apply project-management skills, A project to remo...

A project to remodel an office area has the following activities. (Hint: You will need to build an AIB diagram, perform a forward pass, and perform a backward pass to answer this q

Misconceptions and pitfalls, The followings is a list of some of the comm...

The followings is a list of some of the common misconceptions that should be understood by those claiming to have used quality by design: 1. Quality by design is not simult

Explain how effective teamwork is beneficial, Question: (a) Explain how...

Question: (a) Explain how effective teamwork is beneficial to both the individual and the organisation. (b) Team leaders have to be on the lookout for symptoms of ineffecti

The series of training sessions to help members, PR has recently joined FPC...

PR has recently joined FPC Company as the new Finance Director. He is needed to work towards getting the finance staff to play a fuller role in the company, becoming more integrate

How is inventory control worked for an optimum balance, How is Inventory co...

How is Inventory control worked for an optimum balance between competing objectives? Inventory control is related with achieving an optimum balance in between two competing obj

Need for safety, Need for safety 1. Cost Saving: Two type  of costs ...

Need for safety 1. Cost Saving: Two type  of costs  are incurred by the management  when an accident  occurs. There are the  direct  costs in the  form  of compensation paya

Product development cycle, The product development cycle starts with th...

The product development cycle starts with the assessment of the customers needs and ends when the design is finally released for bulk production. The main steps in th

Precedence Diagrams, I know how to construct a precedence diagram but i am ...

I know how to construct a precedence diagram but i am asked the question :use the largest candidate rule to assign work elements to stations using a service time of 1.5 min how do

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd