Gis based mapping of electrical network, Electrical Engineering

Assignment Help:

GIS Based Mapping of Electrical Network:

You have learnt in which the Geographic Information System is a system of mapping of the complete electrical network. The question we address now is: How is the mapping done? What are the systemic requirements? For this we first required to understand what type of data is required to map in a GIS.

All GIS data are made of two elements:

  • Geometric data and
  • Attributes data.

Geometric data refers to the geometry of geographical features like as building features, locality boundary, plot boundary, street boundary, and etc. Geometric data could be one or both of the subsequent:

1          Geo-referenced satellite imagery,

2          Maps generated by surveys.

The geometric data is commonly acquired using a variety of technologies along with one of the following two accuracies:

 

Positional Accuracy

Geometric Tolerance

 

 

 

Coarse Mapping

10 m (using hand held

DGPS or IKONOS)

1-2 m (using

Rodometer and Tape)

Fine Mapping

2m (using Geodesic GPS

and ETS)

Sub-decimeter (using

ETS)

Because of an inherent nature of the technologies deployed,

a.)  "Fine Mapping" is much more capital intensive than "Coarse Mapping".

b.)  "Fine Mapping" is more labour intensive than "Coarse Mapping".

c.)  "Fine Mapping" is commonly two to three times as expensive as "Coarse Mapping".


Related Discussions:- Gis based mapping of electrical network

Determine the voltage drop, A 15 volts source is applied to a series 150 mH...

A 15 volts source is applied to a series 150 mH inductor and 169 pF capacitor. The resistance of the inductor plus the connecting wires is 1,6 W. Determine the voltage drop and

Digital electronic, What are the advantages of wired-AND connection of digi...

What are the advantages of wired-AND connection of digital IC

Draw and explain the block diagram of dma controller, Draw and explain the ...

Draw and explain the block diagram of DMA controller. The fundamental idea of DMA is to transfer blocks of data directly between peripherals and memory. The data don't suffer t

Binary number system - number systems , Binary  Number Systems As men...

Binary  Number Systems As mentioned  earlier this  number is used by  digital  systems like  microprocessor  and other  digital  circuits. This  number  systems  use only two

Series connected motor, In this case, the armature is connected in series w...

In this case, the armature is connected in series with the field coils. Thus I a   = I f = I         NB. At starting, the back emf is zero (because the m

Compute the efficiency of the motor, Q. A 10-hp, 230-V dc shunt motor takes...

Q. A 10-hp, 230-V dc shunt motor takes a full- load line current of 40 A. The armature and field resistances are 0.25 and 230 , respectively. The total brush-contact drop is 2 V,

Applications platform - gis applications, Applications Platform: GIS a...

Applications Platform: GIS applications should be capable to act as a base system over which the other business process application can be integrated which is the objective of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd