Functions of water stops in joints of box culverts, Civil Engineering

Assignment Help:

Question
What will functions of water stops in joints of box culverts and drainage channels?

Answer
Principal function of water stops is to stop liquids, water-borne materials and solids to go through concrete joints. In essence, it plans at provided that water tightness to drainage channel.

Moreover, water stops in drainage channels or box culverts are able to also serve two reasons-
(i) To evade water contacting joints dowel bars and causing corrosion.
(ii) To evade water seeping in from underside of drainage channels or box culverts, thus washing in dirt particles and causing void under these structures and at last leading to their failure. To serve second purpose, clearly only one water stop is necessary at depth location.

To serve up first purpose, water stop has to be installed on pinnacle of dowel bars to stop water from drainage channels from leaking from side to side. On other hand, water stop has to be offered under dowel bars to keep away from secretive water from surging upwards.

In fact, other way out to serve first purpose is by using corrosion anti bars.

 


Related Discussions:- Functions of water stops in joints of box culverts

Air infiltration, Using Matlab/ Simulink software, verify the heating requi...

Using Matlab/ Simulink software, verify the heating requirement (kW) for the building because of  air infiltration and natural ventilation. Note that this needs you to estimate air

Surveying, closed traverse ABCDE form a regular polygon with fore bearing o...

closed traverse ABCDE form a regular polygon with fore bearing of line is 35 find the bearing of other lines

Open channel, design of irrigation channel permissible velocity table

design of irrigation channel permissible velocity table

Define installation of pot bearings, Define Installation of Pot Bearings? ...

Define Installation of Pot Bearings? In a sliding POT bearing, positive fixing to the main structure may not be required if the bearing is always subjected to adequate vertical

Role of rebate in typical construction joint, Question What is role of reba...

Question What is role of rebate in typical construction joint ? Answer Construction joints are formed on sites to facilitate construction procedure. Though, if improperly constr

Determine the normal and shear stress elements, Determine the normal and sh...

Determine the normal and shear stress elements: The state of stress at a point is given through the stress components σ x = 70 MPa, σ y = 10 MPa, and τ xy = - 40 MPa. Using

CUBE STRENGTH, IN CASE CUBE IS FAIL WHAT CAN IDO

IN CASE CUBE IS FAIL WHAT CAN IDO

Full bore flow in drainage design, Q. Full bore flow in drainage design? ...

Q. Full bore flow in drainage design? In the design of gravity drainage pipes, full bore flow capacity is usually adopted to check against design runoff. Though one should note

Determine the cubic yard in the ground, An earthwork contractor encountered...

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd