Functions of water stops in joints of box culverts, Civil Engineering

Assignment Help:

Question
What will functions of water stops in joints of box culverts and drainage channels?

Answer
Principal function of water stops is to stop liquids, water-borne materials and solids to go through concrete joints. In essence, it plans at provided that water tightness to drainage channel.

Moreover, water stops in drainage channels or box culverts are able to also serve two reasons-
(i) To evade water contacting joints dowel bars and causing corrosion.
(ii) To evade water seeping in from underside of drainage channels or box culverts, thus washing in dirt particles and causing void under these structures and at last leading to their failure. To serve second purpose, clearly only one water stop is necessary at depth location.

To serve up first purpose, water stop has to be installed on pinnacle of dowel bars to stop water from drainage channels from leaking from side to side. On other hand, water stop has to be offered under dowel bars to keep away from secretive water from surging upwards.

In fact, other way out to serve first purpose is by using corrosion anti bars.

 


Related Discussions:- Functions of water stops in joints of box culverts

Pavement layers, What role does modulus of elasticity play in the pavement ...

What role does modulus of elasticity play in the pavement layer arrangement

Dressing of stones.., what is dressing of stones and its various types

what is dressing of stones and its various types

#titlemichelson interferometer.., Describ the construction and working of M...

Describ the construction and working of Michelson interferometer and discuss tha method to determine wavelength of monochromatic

Shear stress, shear stress numerical of T section & I section to find maxim...

shear stress numerical of T section & I section to find maximum shear stress

Determine the thickness of flexible pavement layer, Determine the thickness...

Determine the thickness of flexible pavement layer 2 given the following:  FACTS: Total Structural Number required = 7.0 Total number of layers = 2 Layer 1 consists of

Door, types of door with sketches

types of door with sketches

How to design banks, Q. How to design banks? When approach banks are of...

Q. How to design banks? When approach banks are of medium height upto 3 m, the material may be homogeneous. For bigger heights zoned section with impervious core and pervious o

Write short note on surplus store, Q. Write short note on Surplus Store? ...

Q. Write short note on Surplus Store? Comprise stores which are surplus to requirements and include materials released from renewals and replacements as well as from dismantled

Diaphragms necessary in concrete box girder bridges, Are diaphragms necessa...

Are diaphragms necessary in designing of concrete box girder bridges ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd