Functions of cap block drive cap and pile cushion, Civil Engineering

Assignment Help:

Question

What are main functions of cap block drive cap and pile cushion in driven piles?


Answer

Cap block is fit amid hammer end and drive cap to manage hammer blow in order to protect together hammer and pile from damage. When hammer hits cap block, it squeeze elastically and reduces peak forces, thereby lengthening time of hammer blow. Furthermore, it has to be capable of transmitting hammer energy effectively to piles.

Drive cap is put in at hammer tip to improve uniform distribution of hammer energy to pile. Pile cushion is positioned amid drive cap and pile top. It means to protect pile from driving stress induced during hammer blows. Furthermore, it also serves to give a uniform driving load on top of pile.

 


Related Discussions:- Functions of cap block drive cap and pile cushion

What is function of mortar in brick walls, Q. What is Function of mortar in...

Q. What is Function of mortar in brick walls? A distinctive brick wall structure generally comprises the subsequent components:  (i)  Coping on top of the brick wall to prot

Road survay, how many programmes in road survey by level matichine and ts?

how many programmes in road survey by level matichine and ts?

Doors and windows, what are the actuall windows and door dimensions e.g AN ...

what are the actuall windows and door dimensions e.g AN ND4

Functions and desirable characteristics of pavements, Functions and Desirab...

Functions and Desirable Characteristics of Pavements Function of Pavement A pavement is that part of a road on which vehicles travel. The pavement has the following f

Curved surface profiles, Question Why is concrete profile barriers plan...

Question Why is concrete profile barriers planned with curved surface profiles ? Answer Safety fencings are designed to include vehicles in carriageway in that they a

Pure bending, What are the assumptions made in the theory of pure bending

What are the assumptions made in the theory of pure bending

Plants aeration period, Plants aeration period: Problem: What i...

Plants aeration period: Problem: What is the plant's aeration period? Solution The plant's aeration period is the number of hours that the wastewater is aerated

Explain in brief about the term - anchorage, Explain brief about the term -...

Explain brief about the term - Anchorage A device used to anchor tendons at the end of a concrete member is called as an anchorage in the case of post-tensioned concrete. In th

Category of bars reinforcement are more corrosion resistant, Question Which...

Question Which category of bars reinforcement are more corrosion resistant , epoxy-coated bars, stainless steel bars, galvanized bars? Answer Supported on experiment conducte

Main problems related with prestressed concrete piles, Question What ar...

Question What are main problems related with prestressed concrete piles ? Answer Origin of Daido piles comes from Japan where these prestressed actual piles are used

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd