Function of prime coat in bituminous pavement, Civil Engineering

Assignment Help:

Q. Function of prime coat in bituminous pavement?

The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the presence of moisture affects the strength of subgrade, prevention of water entry at the time of construction is essential to avoid the failure of the pavement. In cold countries, by getting rid of moisture from subgrade, danger of frost heave can be minimized.

Prime coat is an asphalt that, when applied evenly to the surface of subgrade orsub-base, serves to seal the surface to hinder the penetration of moisture into subgrade. Vehicular traffic must be avoided on the surface sprayed with prime coat since the traction and tearing action of vehicles would damage this asphalt layer.

477_Function of prime coat in bituminous pavement.png

Fig: Position of application of prime coat


Related Discussions:- Function of prime coat in bituminous pavement

Rectangular tie, using an optical square how would you perform a rectangula...

using an optical square how would you perform a rectangular tie?

Block contouring, how to calculate contour surveyed area

how to calculate contour surveyed area

Determine the variation of safe bearing capacity of soi, State the algebrai...

State the algebraic equations showing the variation of safe bearing capacity of soil (for clay and sand to be given separately) in shallow foundation with: (i) depth of foundati

Calculate the elastic stretch of the steel wire rope, A 70-ft long, ¾" diam...

A 70-ft long, ¾" diameter, 6 x 7 FC wire rope is resisting a tension force of 12-kips.  The elastic stretch of the steel wire rope given the following properties is most nearly: E

Engineering Graphics, Draw a parabola , height 40mm and bass 120mm using of...

Draw a parabola , height 40mm and bass 120mm using offset method

#tile.., Material for formwork and their specifications

Material for formwork and their specifications

Moment distribution method hinges, Analyse the continuous beam using moment...

Analyse the continuous beam using moment distribution. A continuous beam ABCDE fixed at A carry a load of 2KN one metre from A at AB 3m. BC 3m, carry a UDL of 3KN/m and hinge at

State the natural frequency of a machine foundation, State the natural freq...

State the natural frequency of a machine foundation of base area 2m × 2m and weight 150 kN, suppose that the soil mass participating in the vibration is 20% of the weight of founda

Scales and sludges, Discussscales and sludges. Writea note on internal trea...

Discussscales and sludges. Writea note on internal treatment of water

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd