Q. Function of prime coat in bituminous pavement?

The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the presence of moisture affects the strength of subgrade, prevention of water entry at the time of construction is essential to avoid the failure of the pavement. In cold countries, by getting rid of moisture from subgrade, danger of frost heave can be minimized.

Prime coat is an asphalt that, when applied evenly to the surface of subgrade orsub-base, serves to seal the surface to hinder the penetration of moisture into subgrade. Vehicular traffic must be avoided on the surface sprayed with prime coat since the traction and tearing action of vehicles would damage this asphalt layer.

477_Function of prime coat in bituminous pavement.png

Fig: Position of application of prime coat


Related Discussions:- Function of prime coat in bituminous pavement

Fore bearing and back bearing, write a c program to calculate the included ...

write a c program to calculate the included angles for given fore bearing and back bearing.

Purpose of setting minimum amount of longitudinal steel area, Q. Purpose o...

Q. Purpose of setting minimum amount of longitudinal steel areas for columns? In some design codes it specifies that area of longitudinal steel reinforcement must be not less

Sewer manhole, minimun difference in level of inlet and oulet pipe level in...

minimun difference in level of inlet and oulet pipe level invert in manhole

Determine the governing effective length of a steel column, Determine the g...

Determine the governing effective length of a steel column? Determine the governing effective length of a W12 x 106 steel column that is 12' high, pinned at each end, and

Survey, chaining on level surface

chaining on level surface

Explain types of tiles, Q. Explain Types Of Tiles? Different types of t...

Q. Explain Types Of Tiles? Different types of tiles available in the market for floor and walls & dado are as under - 1. Glazed tiles , 2. Ceramic tiles , 3. Granit

Amount of water that added to achieve the optimum moisture, Geotechnical pr...

Geotechnical project specifications require that the soil's optimum moisture content of 24% be maintained during the roadbed's construction.   The field moisture test finds that fi

Reinforcement detailing, i want to know about the detailing at beam -column...

i want to know about the detailing at beam -column joint & beam- wall joint

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd