Function of longitudinal joints in concrete road pavements, Civil Engineering

Assignment Help:

Question

What is function of longitudinal joints in concrete road pavements?


Answer

A longitudinal joint consists of a tie bar located at mid-depth of a concrete pavement and it is not intended for joint lateral movement. Then one might doubt the reasons of placing longitudinal joints in concrete pavements. In fact, longitudinal joints are usually designed at a regular spacing as in 4.5meter to accommodate effect of differential settlement of pavement foundation. At what time uneven settlement occurs, tie bars in longitudinal joints perform as hinges that allow for settlement of concrete carriageway. Furthermore, it also serves to cater for effect of warping of concrete due to moisture and temperature gradients by permission of a small quantity of angular movement to occur consequently that stresses induced by restrained warping can be avoided.

Dowel the bars are provided in longitudinal joints for following causes-

(i) In case of occurrence of uneven settlement between adjacent panels, it assists to preserve a level surface by transfer of loads through dowel bars.

(ii) Keep longitudinal joints close.

 


Related Discussions:- Function of longitudinal joints in concrete road pavements

Resting on several raking piles, Question Should dolphins be designed i...

Question Should dolphins be designed in a rigid manner such as resting on several raking piles? Answer While designing dolphins, they are normally supported on a syste

Show the specification of bricks, Q. Show the Specification of Bricks? ...

Q. Show the Specification of Bricks? Specification of Ist class Bricks- 1. Table moulded and wire cut. 2. It should have edges and parallel faces. 3. If struck with ha

CANTILEVER RETAINING WALL, NEED TO DESIGN A CANTILEVER RETAINING WALL 8M HI...

NEED TO DESIGN A CANTILEVER RETAINING WALL 8M HIGH, SATURATED UNIT WEIGHT IS 16KN/M3, SURCHARGE IS 7KN/M2, LOAD ABOVE WALL SUPPORTED ON WALL STEM IS 10KN/M RUN, ANGLE IN INTERNAL F

Calculate the flood discharg, Q. A bridge is to be constructed over a strea...

Q. A bridge is to be constructed over a stream having a catchment area = 20 miles 2 partly in plains and partly in hills. Portion in hills has a length of 1.7 miles and fall of 88

Shallow foundations, The drainage system of a cantilever wall shown in Figu...

The drainage system of a cantilever wall shown in Figure As 1 became blocked after a heavy rainstorm and the groundwater level, which was originally below the base, rose to1.5 (m)

NERNST EQUATION, HOW CAN I MAKE ASSIGNMENT ON THIS TOPIC

HOW CAN I MAKE ASSIGNMENT ON THIS TOPIC

Chemistry, scale and sludge formation in boilears

scale and sludge formation in boilears

Fore bearing, find out the interior angleS with diagrame LINE AB, BC, CD, D...

find out the interior angleS with diagrame LINE AB, BC, CD, DE, EA Fore bearing 60''30" , 122'' , 46'' , 205''30" , 300''

Millennium mills redevelopment project assignment, Millennium mills redevel...

Millennium mills redevelopment project assignment in group Presentation

Casing has to be left in for mini-piles, Question What are thought in d...

Question What are thought in determining whether casings have to be left in for mini-piles ? Answer Contrary to most of pile design, design of min-piles is controlled

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd