Free- fall concrete placement in bored piles, Civil Engineering

Assignment Help:

Q. Free- fall concrete placement in bored piles?

Based on the research by STS Consultants Ltd it was found that concrete placed by free falling below 120 feet will not suffer from the problem of segregation and strength of concrete won't be detrimentally impaired provided that piles' bore and base are dry and free of debris. Furthermore it's assumed in the past that during free falling of fresh concrete into the pile bores the hitting of falling concrete in the reinforcement cage causes segregation. Though in accordance with experimental results of STS Consultants Ltd, striking of reinforcement cage by fresh concrete doesn't have significant effect on the strength of concrete.

Additionally for long bored piles, it's impractical to conduct vibration to concrete. For concrete placed by free falling method, impact action arising from free falling is presumed to induce adequate vibration. Alternatively concrete placed by tremie method appears to be lack of vibration and this can affect the integrity and strength of concrete. The research results showed that strength of vibrated concrete was slightly higher than unvibrated concrete. Vibration proved to have added benefit to concrete strength however not essential to achieve the design pile strength.


Related Discussions:- Free- fall concrete placement in bored piles

Define the term - permanent load, Define the term - permanent load Wher...

Define the term - permanent load Where the permanent load is less than or equal to 25% of the design imposed load, deflections may be calculated using any elastic method. When

What is bore hole, What is Bore Hole In exploration of  area of  limit...

What is Bore Hole In exploration of  area of  limited extent  the borings should preferably be located near the comers of  the area. A minimum of three holes should be made un

Estimate the probable final settlement, A bed of sand 12 m thick is underla...

A bed of sand 12 m thick is underlain by a compressible stratum of normally loaded clay, 6 m thick. The water table is at a depth of 5 m below the ground level. The bulk densities

Steel Design Assignment, I have a steel design assignment for my class that...

I have a steel design assignment for my class that will be given to us on Friday at 6 pm and will be due at 10 pm. I was wondering if you guys would be able to help me with that?.

Major bridge and important bridge, Major bridge - Major bridge is one of wh...

Major bridge - Major bridge is one of which has a total linear waterway of 18 m or more for multiple span and total linear water way of 12 m or more for single span. Important b

Define non-carbonate hardness (nch) - water softening, Non-carbonate hardne...

Non-carbonate hardness (NCH) - Water Softening 1. Permanent Hardness, not removed by heating water 2. Ca +2 , Mg +2 combining with ions outside of alkalinity such as Cl -1

Bricks, BRICKS Brick is obtained by moulding good clay into a block, wh...

BRICKS Brick is obtained by moulding good clay into a block, which is dried and then burnt. It is the oldest building block to replace stone. Manufacture of brick started havin

Postensioning in raft foundation, how can we post tension a raft foundation...

how can we post tension a raft foundation? what design procedure should we follow to post tension raft foundation in order to decrease the concrete and steel volume and increase th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd