a) Critical Path: A, B, E and F. Project completed in 11 weeks.

1433_Forward planning and Critical Path.png

Subtract one mark for each error made. Maximum marks can only be awarded if the candidate explicitly indicates the critical path (either on the diagram or written out).

b) Any two reasons explained in the context of SJC warrants maximum marks. These might include:

• It encourages forward planning at SJC, i.e. managers need to consider the different aspects of the construction project in order to complete it in minimal time

• Since CPA provides a visual stimulus, it is easier for people to interpret the logistics of the plan in order for the construction project to run more smoothly.

• It identifies the shortest time in which the construction project can be completed so that the buyer will have the house completed on time.

• CPA can help SJC to control costs more effectively by identifying when certain activities can start and how long certain tasks should last.


Related Discussions:- Forward planning and critical path

London stock exchange, London Stock Exchange (LSE) The origin of the Lo...

London Stock Exchange (LSE) The origin of the London Stock Exchange goes back to the coffee houses of 17th century. London, where people willing to invest or raise money, bough

Indexed bonds, In indexed bonds, the principal and coupon payme...

In indexed bonds, the principal and coupon payments are linked to the market index like inflation and price index. Index bonds are attractive to investors

Bank credit, Definition of 'Bank Credit': The amount of credit availab...

Definition of 'Bank Credit': The amount of credit available to a business or individual from the banking system. It is the aggregate of the amount of funds financial instituti

Explain the various key determinants of initial project cost, Question 1 Th...

Question 1 There are several elements which you can take into consideration, while budgeting a project. Describe these elements Question 2 Explain the different methods/source

Pre-requisites for effective budgetary control system, ORGANISATION FOR BUD...

ORGANISATION FOR BUDGETARY CONTROL (or) PRE-REQUISITES FOR THE INTRODUCTION OF AN EFFECTIVE BUDGETARY CONTROL SYSTEM 1.   BUDGET CENTRE:  It is a section of the organization

Currency, You have the following limited information upon which to base you...

You have the following limited information upon which to base your decision as to which is the better of two alternative funding arrangements: ? Alternative 1 is to arrange funding

TOOLS TO ACCESS ECONOMIC RECESSION, WHAT ARE THE TOOLS OR MECHANISMS THAT C...

WHAT ARE THE TOOLS OR MECHANISMS THAT CAN BE USED TO ACCESS ECONOMIC RECESSION?

6 KEY STAGES OF INVESTMENT DECISION WITH APPROPRIATE DIAGRAM, 6 KEY STAGES ...

6 KEY STAGES OF INVESTMENT DECISION WITH APPROPRIATE DIAGRAM

What is public finance, What is Public Finance Central, state as well...

What is Public Finance Central, state as well as local governments handle large sums ofmoney, which are received from several sources and should be utilized in accordancewith

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd