Large catchments in estimating peak runoff, Civil Engineering

Assignment Help:

Question

Is it true that rational process has to not be used for large catchments in estimating peak runoff?


Answer

Rational process is appropriate for small catchments only as time of absorption of small catchments is small. In Rational system peak runoff is calculated based on assumption that time of concentration is equal to rainfall duration. For small catchments, this assumption might hold true in mainly circumstances. One of assumptions of rational process is that rainfall intensity over entire catchment remains constant all through storm period. Though, in case of a large catchment it stands a high possibility that rainfall intensity varies in a variety of part of large catchment. In adding, for long period of rainfall, it is rare that rainfall intensity remains constant over total rainstorm and a shorter period but an additional intense rainfall might create a higher peak runoff. Furthermore, a decrease of peak runoff is also brought about by temporary storage of storm water similar to channels within catchment.

In genuine condition, runoff rate within catchment differs from place to place since of different soil properties and past conditions. Sometimes peak free occurs before all of drainage area is contributing. For example, when a significant portion of drainage area within catchment has very little time of concentration so that a higher rainfall strength be able to be used for this portion, runoff coming solely from this portion is higher than that of whole catchment in which a lower rainfall strength is adopted since remaining part of catchment has comparatively large occasion of concentration. Therefore, this results in wrong estimation of peak runoff of large catchments if rational process is adopted.

 

 


Related Discussions:- Large catchments in estimating peak runoff

Explain the inventory inspections - inspection of bridge, Explain the Inven...

Explain the Inventory inspections - Inspection of Bridge? These inspections are normally performed following new construction, modifications, or repair to establish as-built or

Explain the shrink factor of soil, Explain the Shrink Factor of Soil In...

Explain the Shrink Factor of Soil In addition to the swell factor and its associated load factor, soil also has a shrink factor. While the first two relate the volume of an equ

Comparing speed, Question Comparing speed of "Formwork exceeding 300mm wide...

Question Comparing speed of "Formwork exceeding 300mm wide, horizontal and at any inclination up to and including 5o to horizontal" with speed of "Formwork exceeding 300mm wide, at

Steps to determine brake (bhp) and motor horsepower (mhp), Steps to determi...

Steps to determine the brake (bhp) and motor horsepower (mhp):  1) Determine water horsepower (whp). h A (Qgpm) (SG) / 3956 OR h A (Qcfs) (SG) / 8.814 2) Apply the pump

Steel and timber structures, design a tension member subjected to a pull of...

design a tension member subjected to a pull of 300KN using a channel section. the length of a joint available is only 400mm.check the condition of using lug angle for end connecti

Premix road, plz tell me the ratio of sand,aggregate,and asphalt.pl tell me...

plz tell me the ratio of sand,aggregate,and asphalt.pl tell me the mm of aggregate

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd