Float or slack of an activity is positive or negetive, Civil Engineering

Assignment Help:

1. What take place when float or slack of an activity is positive

Ans: It represents a situation where extra resources are available and the completion of the project is not delayed

2. What take place when float or slack of an activity is negative

It represents that a project falls behind schedule and additional resources are required to complete the project on time

 

 


Related Discussions:- Float or slack of an activity is positive or negetive

Lintel, what is the classification of lintel

what is the classification of lintel

Shear strength of concrete., why do we use effective depth ''d'' in calcula...

why do we use effective depth ''d'' in calculating the shear capacity of uncracked Concrete beam. If it is uncracked, why cant we use the full depth ''D''.

Soil Mechanics, Good evening. I have two homework projects from the Soil Me...

Good evening. I have two homework projects from the Soil Mechanics. I am interesting if anybody can solve them.

Breakwaters - harbour layout, Breakwaters: A breakwater is an artific...

Breakwaters: A breakwater is an artificial structure constructed in the sea to protect ships from the effect of waves and storms. Three types of breakwaters are common :

I.s. codes on earthquake resistant building design, I.S. CODES ON EARTHQUAK...

I.S. CODES ON EARTHQUAKE RESISTANT BUILDING DESIGN Bureau of Indian Standard has divided the country into five zones depending upon the severity of earthquake after observing

Strength of materials, Didtribution of shear stree over a triangular sectio...

Didtribution of shear stree over a triangular section

Explain ductile iron pipes and mild steel pipes, Ductile iron pipes vs. mil...

Ductile iron pipes vs. mild steel pipes as pressurized pipelines For water main pipe size less than 600mm, ductile iron is generally used since internal welding for steel pipe

Define the limitations of shock transmission unit, Define the Limitations o...

Define the Limitations of shock transmission unit? STUs are not intended for energy/shock absorption. They simply transmit load from one part of the structure to another thus s

Determine the project duration and critical path, Critical Path - Activity ...

Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd