Float or slack of an activity is positive or negetive, Civil Engineering

Assignment Help:

1. What take place when float or slack of an activity is positive

Ans: It represents a situation where extra resources are available and the completion of the project is not delayed

2. What take place when float or slack of an activity is negative

It represents that a project falls behind schedule and additional resources are required to complete the project on time

 

 


Related Discussions:- Float or slack of an activity is positive or negetive

Show the probable type of clay mineral, The liquid limit and plastic limit ...

The liquid limit and plastic limit of clay are 100% and 25%, respectively. From a hydrometer analysis it has been found that the clay soil having of 50% of particles smaller than 0

Geofabric strengthening of perth soils, I need technical assistance. The pr...

I need technical assistance. The project is incomplete. I need someone to proofread it. Do you have someone who know Plaxis, Slope/W and Flac?. Can you arrange a case study for Geo

Explain the difference in elevation between bm and tp2, Based on the inform...

Based on the information provided in Figure, the difference in elevation between BM and TP 2 is most nearly: Solution: Set up a Table as shown below and insert the kno

How to evaluate quality of bricks, Q. How to evaluate quality of Bricks? ...

Q. How to evaluate quality of Bricks? 1. Clour -Deep red, Carry red, Copper red, colour is indication of uniform burning and also suggests quality of clay used. Over brunt bric

Prismatic compass, what is the role of agate cape in prismatic compass?

what is the role of agate cape in prismatic compass?

What do you mean by shallow gradient of pipes, Q. Colebrook White formula s...

Q. Colebrook White formula suitable for shallow gradient of pipes? Manning's Equation is commonly used for rough turbulent flow while Colebrook-White Equation is adopted for t

Method of section, III. Calculate the magnitude and sense of the member for...

III. Calculate the magnitude and sense of the member forces BC, BG and HG using the method of sections

Distance between concrete columns in 5 story building, distance between con...

distance between concrete columns in 5 story building and if there is distance 15 feet than what should be the column size and how many bars and diameter of each bar ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd