Float or slack of an activity is positive or negetive, Civil Engineering

Assignment Help:

1. What take place when float or slack of an activity is positive

Ans: It represents a situation where extra resources are available and the completion of the project is not delayed

2. What take place when float or slack of an activity is negative

It represents that a project falls behind schedule and additional resources are required to complete the project on time

 

 


Related Discussions:- Float or slack of an activity is positive or negetive

Explain template jig, Explain Template Jig? 1) Template jig is the simp...

Explain Template Jig? 1) Template jig is the simplest type of jig, employed for accuracy than speed. 2) This jig fits over, on, or, into the work and is not generally clampe

Calculate the cost to finance the construction project, A contractor is bid...

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Define inspection of steel or cast iron substructures, Define Inspection of...

Define Inspection of Steel or Cast Iron Substructures? Corrosion is the principal cause of deterioration in steel waterfront substructures. On bare un-protected steel pilings,

Define abrasion of steel structures - inspection of bridge, Define Abrasion...

Define Abrasion of steel structures? Abrasion of steel structures can generally be recognised by a worn, smooth, polished appearance of the surface.  Abrasion is caused by cont

Calculate the annual cost of alum - coagulation, Incoming water contains 2....

Incoming water contains 2.5 mg/L as a substance of natural alkalinity (HCO 3 - ). The flow rate is 9.5 ML/day). (a) What feed rate is required if the alum dose is 7 mg/L and

Moisture-density relationship, Moisture-Density Relationship: Since va...

Moisture-Density Relationship: Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-kn

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd