Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Forms of centralisation - library management, Forms of Centralisation   ...

Forms of Centralisation   In centralised cataloguing we observe that there are several forms of centralisation like:  Card (or Sheaf) service  MARC (Machine-Readable C

Managerial Innovation, What are the implications of management innovation i...

What are the implications of management innovation in a banking industry

Procedure of document selection - library administration , Procedure: ...

Procedure: The actual process  of document selection may be initiated in different ways. The acquisition staff take note of the desirable items and present them to the subject

Explain materials required for crocheting, Question 1) Describe any five d...

Question 1) Describe any five differences between Weaving and Knitting Question 2) State the advantages of shuttleless looms Question 3) What is felting? Explain

Performing quality control, P e rforming Quality Control Quality cont...

P e rforming Quality Control Quality control uses techniques and performs activities to compare actual quality performance with requirements and define appropriate actions if

Stack maintenance , STACK MAINTENANCE: We have explained That mainten...

STACK MAINTENANCE: We have explained That maintenance work implies the organisation of stack rooms, arrangements of books on shelve in stack rooms and conservation. In thi

Describe ways in which mass media, Problem 1 Over the last 30 years, th...

Problem 1 Over the last 30 years, there have been important developments in the evolution of mass media (Wilson and Kidd, 2010). Describe four ways in which mass media has evol

Self-managed teams, In these teams the members themselves will not only per...

In these teams the members themselves will not only perform the work but also monitor, measure, and manage their performance.

Improve public sector performance, QUESTION 1 A core concept in implem...

QUESTION 1 A core concept in implementing TQM is Deming's 14 points, a set of management practices to help companies increase their quality and productivity. List 7 points and

Selection of potential suppliers , Selection of potential suppliers  Th...

Selection of potential suppliers  This is an important function of the purchase department. If the material under reference is a standard item covered by company standards, the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd