Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Explain the relationship between treasury and alm, Question 1 Suppose you ...

Question 1 Suppose you are the CEO of MS Bank Corporation. Your bank is facing interest rate risk which has affected its operation significantly. Explain the factors that influenc

Constraints - library catalogue code, Constraints: This unit calls for...

Constraints: This unit calls for a comprehensive and thorough treatment to cover the various aspects of history and development of library catalogue codes. However, such a tho

Subject catalogue - types of catalogue, Subject Catalogue : In an alph...

Subject Catalogue : In an alphabetical subject catalogue, entries are made under the name of the specific subjects of documents. Irrespective of their affiliations, specific s

Short-turm financing, What are the three approach to the short-term financi...

What are the three approach to the short-term financing problem and provide relevant examples for each ?

Audience analysis, Audience Analysis To enhance communication with you...

Audience Analysis To enhance communication with your audience, you must have to analyze it carefully to formulate a message in a way they will understand and search meaningful

Benefits of project quality management, Benefits of Project Quality Managem...

Benefits of Project Quality Management Let us now discuss the benefits of quality in project performance. C ustomer satisfaction: It is the result of a quality project

Cumulative index work and loose issue shelving work, Cumulative Index Work:...

Cumulative Index Work: As the name suggests, it pertains to noting by entering down the announcement of cumulative index followed by entering  the receipt of cumulative index

Discuss importance of using personal protective equipment, Question 1: ...

Question 1: Heat and noise are important factors for productive work inside the work premises. Describe, in details, how you would control these factors at the workplace to inc

Meaning and Purpose of Education, What is the meaning and Purpose of Educat...

What is the meaning and Purpose of Education in this age of technological advancement?

Porter''s five forces model, QUESTION 1 Implementation of selected stra...

QUESTION 1 Implementation of selected strategies is a phase in the strategic management process. Discuss the key issues that need to be considered in this phase. QUESTION 2

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd