Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Explain what the term preventive legal management address, Question 1: ...

Question 1: (a) Explain what the term "preventive legal management" addresses. (b) Describe any 5 stakeholders that have a legal relationship within the hospitality indust

Differentiate between overt and covert resistance to change, Question: ...

Question: "Resistance to change is not only a predictable part of change, it is perhaps the most difficult phase to deal with. People resist change for good reasons, even thoug

Explanation of public relations, Problem Explain the key tools availabl...

Problem Explain the key tools available to carry out the public relations function. Explanation of Public relations Developing Media Relations Launching Media Tours

Finishing - binding processes, Finishing: Finishing is the final proce...

Finishing: Finishing is the final process of making the binding more artistic and attractive. This includes: preparation of the leather covering  imaginative design f

Card form - library catalogues, Card Form: Library catalogue in the ca...

Card Form: Library catalogue in the card form is by far the most popular physical form. It is widely prevalent in libraries throughout the world including India. In this form

Size of sample, SIZE OF SAMPLE: Large  samples are more  representativ...

SIZE OF SAMPLE: Large  samples are more  representative  of the population of interest than the sinall  samples. There  are no specific  rdes for determining the desired sampl

Steps in developing a questionnaire, Steps in Developing a Questionnaire or...

Steps in Developing a Questionnaire or  Interview  Schedule: a)  Preliminary Decisions:  Decide  on  the form that the schedule will take  e.g. structured, unstructure

Need and purpose of library classification, NEED AND PURPOSE OF LIBRARY CLA...

NEED AND PURPOSE OF LIBRARY CLASSIFICATION: Library classification invariably requires written has of damps and their subdivisions arranged in a systematic way along with corr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd