Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Explain any five features of sfa, Question 1 Explain the CRM technology co...

Question 1 Explain the CRM technology components Question 2 Explain any five features of SFA Question 3 Explain the major components of Enterprise Marketing Automa

Retrospective survey, Retrospective Survey: In a retrospective survey,...

Retrospective Survey: In a retrospective survey, the researchers may  also like to investigate possible cause and effect relationships by  observing some existing consequences

Short-turm financing, What are the three approach to the short-term financi...

What are the three approach to the short-term financing problem and provide relevant examples for each ?

Organizational behavior, what type of errors would you be prone to make whi...

what type of errors would you be prone to make while making these judgement towards goofing employees?

Domain, D omain A community will be just a group of friends without th...

D omain A community will be just a group of friends without the commitment to the domain. A domain is not just the group of people with connections but it is an identity which

Type of building, Type of Building: The  number  of floors has direct effe...

Type of Building: The  number  of floors has direct effect on the  which  should be used.  Single  story building  the most  common  type  being  built today  lends  themselves to

Checking with the catalogue - library classification, Checking with the cat...

Checking with the catalogue: The individual classifier  who is allotted a  set of documents for processing will first  check  each item in the set with the library catalogue.

Inadequacies of the traditional public administration, Question 1: The ...

Question 1: The Public Sector is undergoing a major transformation. What according to you, are the imperatives that are driving the change process ? Question 2: What

Implement a successful conservation programme, Implement a successful conse...

Implement a successful conservation programme:  To implement a successful conservation programme, the staff must know:  The nature  of base materials and  manufacturing

Hrd in. indian libraries and information centres , HRD IN. INDIAN LIBRARIES...

HRD IN. INDIAN LIBRARIES AND INFORMATION CENTRES HRD as discussed in this Unit may seem to be somewhat irrelevant to the conditions prevailing in Indian libraries and informa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd