Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Vertical and horizontal integration strategies, QUESTION (a) Comment o...

QUESTION (a) Comment on the generic competitive strategies as proposed by Porter with the use of suitable examples (b) Briefly elaborate, with relevant examples, your unders

Connecting professional development and corporate strategy, C onnecting pr...

C onnecting professional development and corporate strategy The CoP builds value by connecting the personal development and also the professional identities of the practitione

Organisational framework for project management, Organisational Framework f...

Organisational Framework for Project Management A project based organisation is a composition that facilitates the coordination and implementation of project behaviours. Projec

Managerial economics, why is it important for managers to understand macro ...

why is it important for managers to understand macro economics

Four levels of corporate social responsibility, QUESTION (a) Describe f...

QUESTION (a) Describe five driving forces that have contributed to the growing popularity of Corporate Social Responsibility during the last few years. (b) According to Arch

Explain scope and goals of iso/ts 16949, Question 1 Explain the various pr...

Question 1 Explain the various principles of Quality Management Systems Question 2 Explain scope and goals of ISO/TS 16949 Question 3 Explain the procedures and benefits

Periodicals and serials - selection tools, Periodicals and Serials: Pr...

Periodicals and Serials: Primary periodicals constitute one  of the most indispensable categories of publications  in academic  research and special libraries. A substantial p

Proposal or renewal sub system, Proposal or Renewal Sub System: Type  ...

Proposal or Renewal Sub System: Type                                         Web-based Application Role                                          Software Engineer Team s

Possible challenges and dark-side of an e-pms, "The use of technology in pe...

"The use of technology in performance management has the potential to increase productivity and enhance competitiveness. We believe that appraisal satisfaction is a key concept tha

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd