Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Write break down or corrective or remedial maintenance, Question 1 Write b...

Question 1 Write break down or corrective or remedial maintenance. Question 2 Explain the planning principles in maintenance management, Question 3 The principles used i

What are the four basic change management strategies, Question : (a) Wh...

Question : (a) What are the skills required from change agents in order to manage the different kinds of change effectively? (b) What are the four basic change management st

Beta of a share, Beta of a share Financial analysts often talk of the ...

Beta of a share Financial analysts often talk of the beta (b) of a share. We will describe what the beta signifies and the method commonly used to estimate it in this section.

Production process , Production Process  Let us begin our discussion wi...

Production Process  Let us begin our discussion with the production process.  The production process for any project begins soon after the research and development department f

Links in information, Links in InformationTransmission Chain: i)  Sour...

Links in InformationTransmission Chain: i)  Sources of Generation: As discussed in Unit 1, the researchers and their employing oreganisations are responsible for generating in

Outline four major benefits of erp implementation, QUESTION a) Outline ...

QUESTION a) Outline four major benefits of ERP implementation. b) 'An ERP integrates the organization as one functional unit'. Briefly explain the meaning of this statement.

Choice of bindery- factors to be considered , Choice of Bindery: Factors to...

Choice of Bindery: Factors to be Considered  Outside binders are normally selected through competitive bidding or through free selection. Whatever the case, the librarians sho

Definition of resource sharing, Definition   Allen Kent provides a desc...

Definition   Allen Kent provides a description of some of the concepts associated with the resource sharing activity in the following terms:   Resource sharing in libraries is

Finding resources - library management system, Finding resources: As s...

Finding resources: As said earlier, supply is another basic factor. Supply means availability of documents for acquisition. Information regarding supply can be collected in th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd