Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Production and development process, Production and Development Process  ...

Production and Development Process  The traditional approach to product  development stresses on a rigid sequence of steps. Usually R&D engineers exclude the manufacture proces

Statistical process control, Problem QC is often performed by a team of...

Problem QC is often performed by a team of professionals who use specific techniques. These techniques do vary depending on the intended measurement. Without QC techniques, a c

Describe the concept of corporate social responsibility, Problem 1 (a) ...

Problem 1 (a) Describe the concept of Corporate Social Responsibility (CSR) and explain the forms and purpose of CSR as practiced by most organizations. (b) Illustrate with

Explain the reinforcement theory of motivation, QUESTION (a) Define the...

QUESTION (a) Define the term 'Motivation' and explain its importance for organizational success (b) Reply ANY TWO of the following items- (i) Explain with the support of

Construct validity - major types of validity , Construct  Validity: I...

Construct  Validity: In  cqnstruct validity, the investigator  is  concerned with the questions  the  concept under investigation being adequately measured? Is  there  a valid

Entrepreneurship, #question. I want detailed information about entrepreneur...

#question. I want detailed information about entrepreneurship.

Controlling risks, Controlling Risks Risk management is not just provid...

Controlling Risks Risk management is not just providing for uncertainties - it is management of risks considering the combination of the probability (extent to which the risk e

Choice of the tps by the consultant firm, Question: A textile manufactu...

Question: A textile manufacturing company would like to implement a system for managing its production. The company does not have any in-house IT staff and has outsourced the c

Reasons for quality improvement, R easons for quality improvement The ...

R easons for quality improvement The Quality Improvement helps the organisation to continuously improve the quality of the product or the service. The quality improvement can

Advanced Linear programming questions, where can i get Advanced Linear Prog...

where can i get Advanced Linear Programming questions from ??

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd