Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Explain what you understand by internal analysis, QUESTION 1 SWOT Matri...

QUESTION 1 SWOT Matrix is one of the principal tools for strategic analysis. Referring to this matrix- (a) Explain what you understand by internal analysis (b) Explain wh

Discuss, Question 1 : Language is much more than grammar and serves va...

Question 1 : Language is much more than grammar and serves various purposes in society. Justify this statement. Question 2: One of the definitions of language is a 'sy

Describe the various exchange rate systems, Problem: 1. Describe the va...

Problem: 1. Describe the various exchange rate systems. 2. Illustrate the BPO approach and its criticism in detail. 3. Describe the International Techniques of Managing Foreig

Explain why it is necessary to introduce the dummy activity, Question: ...

Question: The following diagram shows a C.P.A.-network modeling the stages in the construction project. Each arc is labeled with the letter denoting the activity it represents

Efficient library management, Efficient library management: These-func...

Efficient library management: These-functions are carried out by any reasonably efficient library. The emphasis the definition is on the provision of information as a major fu

Alphabetical catalogues , ALPHABETICAL CATALOGUES : Readers are more a...

ALPHABETICAL CATALOGUES : Readers are more at home with a catalogue arranged alphabetically, as such catalogues are arranged as in a dictionary. Alphabetical catalogues can be

Arrays and chains - classification terminology, Arrays and Chains: Iso...

Arrays and Chains: Isolates are arranged in what are called arrays and chains. ,An array is a sequence of coordinate (equally ranked) classes arranged in some definite order.

Describe the term media literacy, It is one thing to understand the basic i...

It is one thing to understand the basic importance of being a media literate individual of knowing its basic elements and necessary skills. It is quite another to live a media lit

Finding resources - library management system, Finding resources: As s...

Finding resources: As said earlier, supply is another basic factor. Supply means availability of documents for acquisition. Information regarding supply can be collected in th

Describe talent management system, Problem 1: What is the importance of...

Problem 1: What is the importance of talent management? Describe Talent management Importance of Talent management Problem 2: Describe the five stage approa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd