Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Allocating funds - library management system, Allocating Funds: Financ...

Allocating Funds: Finance is the most important factor in document selection. Proper planning of finance is basic to good  acquisition  work. Every library works according to

Describe importance of information to top management, Question 1: (a). ...

Question 1: (a). Outline the major elements which make up the i) Macro (External) environment. ii) Micro (Internal) environment. (b). Discuss five methods that can be use

Observation technique - methods of data collection, Observation Technique: ...

Observation Technique: What  does  observation  technique  mean:  Observation  Is one of the basic and  oldest  research methods  to  gather data. Observation stops being  a n

Reference service - information behaviour, Reference Service:  Notwith...

Reference Service:  Notwithstanding library catalogues and various other aids available for exploiting the library resources, users would frequently need some personal assista

What are the major characteristics of adult learners, QUESTION 1 Motiva...

QUESTION 1 Motivation is a vital condition of learning. Discuss the statement and suggest ways and means by which school learning can be effectively motivated QUESTION 2

Internal and physical of the catalogue, Internal and Physical of the Catalo...

Internal and Physical of the Catalogue: Internal Form of the Catalogue  As mentioned earlier, according to the internal farm, the two major types of  library catalogues a

Intercultural communication differences, Intercultural communication differ...

Intercultural communication differences: reconciliating disparities through recognition You represent a Mauritian hardware company which is negotiating to buy hardware from

HRM in HEALTH CARE MANAGEMENT, EXPLAIN THE IMPORTANCE OF HRM IN HEALTH CARE...

EXPLAIN THE IMPORTANCE OF HRM IN HEALTH CARE MANGEMNT

Managerial economics, what is prisoner''s dilemma'',of non cooperative game...

what is prisoner''s dilemma'',of non cooperative game?

Connecting professional development and corporate strategy, C onnecting pr...

C onnecting professional development and corporate strategy The CoP builds value by connecting the personal development and also the professional identities of the practitione

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd