Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

What is the required rate of return on the project, QUESTION a. The ris...

QUESTION a. The risk free rate is 10 percent and the expected return on the market portfolio is 14 percent. A firm considers a project that is expected to have a beta of 1.3, w

Cluster sampling, Cluster Sampling In cluster sampling there  is  a su...

Cluster Sampling In cluster sampling there  is  a successive random . sampling of units. The first unit  to  be sampled is large grouping or clusters. For example,  in  drawin

Performing quality assurance, P e rforming Quality Assurance Quality ...

P e rforming Quality Assurance Quality assurance is the process of providing confidence that the project will satisfy  the  identified  quality  standards.  It  is  performed

Disciplines and subjects - classification terminology, Disciplines and Subj...

Disciplines and Subjects - Library management: In a modern library the arrangement of documents is usually by subject. Thus, subject is the characteristic of division for arra

Efficient market hypothesis, QUESTION (a) (i) Discuss the empirical evi...

QUESTION (a) (i) Discuss the empirical evidence in relation to weak form market efficiency (ii) Explain fully how you would conduct a test of semi-strong form of the Efficie

Describe and illustrate the term non ionizing radiation, Question 1: ...

Question 1: (a) Describe and illustrate the term ‘non ionizing radiation'. (b) In what ways will noise affect workers? (c) How will the effects of noise, as a hazard,

Explain the issue of performance management system, Question: (a) Expla...

Question: (a) Explain the issue of Performance Management System and its perceptions by the school organisations in Mauritius. (b) How will the Educational Administration an

Control of contracts, C ontrol of contracts The contract control proce...

C ontrol of contracts The contract control process commences right at the beginning stage of bid document preparation inviting contractors to bid, and proceeds through the con

Clustering, In the past, in the Universe of Documents, the general trend ha...

In the past, in the Universe of Documents, the general trend has been to narrow the extension of a subject embodied in -a document taken as a whole. Therefore, there has been a gen

Sponsorship, Hi, i need to motivate a sponsorship program to exco as part o...

Hi, i need to motivate a sponsorship program to exco as part of my marketing assignment. I have no idea how to do this. Can you help?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd