Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Short-term decision-making problem, A company manufactures and sells a sing...

A company manufactures and sells a single product. The variable cost of the product is Rs 2.50 per unit and all production each month is sold at a price of Rs 3.70 per unit. A pote

Policies implemented to counteract the informal economy, QUESTION 1 Gov...

QUESTION 1 Governance had gained ground as a result of the failure of the State and how far do you agree? QUESTION 2 It is evident that a high level of informal economi

The computer misuses and cybercrimes that are punishable, QUESTION 1 Wh...

QUESTION 1 What are the principles that one should take into consideration when dealing with data protection? QUESTION 2 What are the institutions set up for the protec

Efficient market hypothesis, QUESTION (a) (i) Discuss the empirical evi...

QUESTION (a) (i) Discuss the empirical evidence in relation to weak form market efficiency (ii) Explain fully how you would conduct a test of semi-strong form of the Efficie

Health and research management, 1.  You will critically review 6 or more sc...

1.  You will critically review 6 or more scholarly articles that inform the reader about your topic. You should have: At least: Two articles that describe the overall issue or

Maturity model in cobit 5, Maturity model in CobiT 5: CobiT 5 maturity ...

Maturity model in CobiT 5: CobiT 5 maturity model is based on the ISO/IEC 15504. This new model presents some differences (CobiT 5 2012). However, an important similarity betwe

Tools and techniques used for quality planning, T ools and techniques used...

T ools and techniques used for quality planning Let us now see some of the tools and techniques used for quality planning. They are: C ost /benefit analysis: This is an

Examine the nature of people-organisation relationship, QUESTION 1 Crit...

QUESTION 1 Critically examine the nature of people-organisation relationship. Why is it important to distinguish between the ‘intent' and the ‘implementation' of management dec

Major ecosystems in the tropical marine environment, Problem: (i). De...

Problem: (i). Define the term ‘ecosystem' (ii). What are the three major ecosystems in the tropical marine environment. (iii). State and explain four main ecological

North american free trade agreement (nafta), North American Free T r...

North American Free T rade Agreement (NAFTA) It is a multilateral accord among the United States, Canada, and Mexico.  It is also preferred to as the (NAFTZ) North

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd