Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Selection of sources, Selection of Sources: A good approach to literat...

Selection of Sources: A good approach to literature search is looking up a bibliography, an encyclopaedia or a review publication. This provides background information as also

What are the objectives of fisheries management, Question 1: (a) Descr...

Question 1: (a) Describe any two fishing methods and fish species caught. (b) List ten conditions of a fishing licence issued to a foreign vessel fishing in the EE

Show crisis management from a pr perspective, Question 1: Management ne...

Question 1: Management needs help when confronted by sudden crisis. It is required that crises be managed intelligently and forthrightly with the news media, Employees and the

Define unemployment, QUESTION 1 According to Archie Caroll, explain the...

QUESTION 1 According to Archie Caroll, explain the four levels of corporate social responsibility. How far is the model relevant to the Mauritian context? Use appropriate examp

Negotiations , Negotiations  One of the most important activities perfo...

Negotiations  One of the most important activities performed by the supply managers is to negotiate agreements or contracts with the suppliers. Although supply management is de

Types of communities of practice, C ommunities of practice take many forms...

C ommunities of practice take many forms Communities of Practice differ widely in both name and style in different organisations. CoP takes many forms and knowing these variat

Library catalogue code - library management , Library catalogue code: ...

Library catalogue code: A library catalogue code, one or two of which (for, there are a score of the them), as you may have surely become familiar with to some extent, can be

Cyclostyled form - conventional forms, Cyclostyled Form: Revised vers...

Cyclostyled Form: Revised version of bound register form came into existence due to the typewriter and cyclostyling machine. The entries are typed. Multiple copies (up to four

Binding materials - library management, BINDING MATERIALS: The quality...

BINDING MATERIALS: The quality of binding depends on the type of materials. As a working librarian or a prospective librarian you would need to be conversant with the types an

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd