Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Develop negotiating strategy and tactics , Develop negotiating strategy and...

Develop negotiating strategy and tactics  These are two dimensions of the negotiating process. They are:  Strategy:  It has a long term focus. It is a predetermined app

Explain project reviews and risk reassessment briefly, Question 1 Explain ...

Question 1 Explain the various inputs , tools and techniques of qualitative risk analysis process Question 2 The risk mitigation methodology describes the approach to contro

Liquidated damages, The General Condition of Contract provides clauses to e...

The General Condition of Contract provides clauses to establish the rights and liabilities of the Purchaser and the Supplier in connection with the execution of a procurement contr

Importance of branding, Question: The branding strategy adopted by any ...

Question: The branding strategy adopted by any organization today is very important to be able to maintain or gain competitive edge over its competitors. (a) Define brandin

Charging desk -circulation area in library building, Charging Desk -Circula...

Charging Desk -Circulation Area in library building This is the key functional area of the library and a great deal of  thought should be given to its location, size and shape

Special furniture items-library furniture-library management, Special Furni...

Special Furniture Items-library furniture-library management Besides the above mentioned library furniture, a few other items worth considering are:  Book trolley, whi

Possible challenges and dark-side of an e-pms, "The use of technology in pe...

"The use of technology in performance management has the potential to increase productivity and enhance competitiveness. We believe that appraisal satisfaction is a key concept tha

Cobol, Write a COBOL program to accept three subject marks and to display t...

Write a COBOL program to accept three subject marks and to display the total of marks and percentage of marks.

Derivatives section of a bank treasury, Question 1 Discuss the various act...

Question 1 Discuss the various activities carried out by commercial banks these days that are common to clients of both commercial banks and development banks Question 2 What

Different types of information services, DIFFERENT TYPES OF INFORMATION SER...

DIFFERENT TYPES OF INFORMATION SERVICES: Modem libraries and information centres provide a variety of documentation and information services to support research and developmen

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd