Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Back charging, B ack charging: Back charging the contractor arises ...

B ack charging: Back charging the contractor arises when a certain scope of work included in the contract is either not carried out or carried out defectively. When such an

Shop floor control and what are its different functions, QUESTION 1 (a)...

QUESTION 1 (a) What is shop floor control and what are its different functions? (b) What are the advantages and disadvantages of Kanban process? (c) What do you understan

Purposes of a library catalogue , .Purposes of a Library Catalogue ...

.Purposes of a Library Catalogue Libraries generally acquire reading and reference materials in various physical forms, which will be utilised by users for study, referen

State two reasons for establishing a marcom plan, Question: (a) Th...

Question: (a) There are different types of advertising strategies adopted by Organizations in order to increase their sales force. The strongest advertising strategies

Developmental longitudinal and cross sectional survey, Developmental Longi...

Developmental Longitudinal  and Cross Sectional Survey: Suppose, you wish  to  study the  growth and development pattern  of children from birth  tofive years  of age. This  i

Issues in public relation, Question In 2000, various instances were rep...

Question In 2000, various instances were reported in which Ford owners with Firestone tyres were experiencing tyre blowouts ultimately causing around 150 deaths and over 500 s

Outline the characteristics of tourism services, QUESTION 1 (a) Describ...

QUESTION 1 (a) Describe the role of public sector in the development of tourism Industry? (b) Describe the role of private sector in the development of tourism Industry?

Choice of an inner form for a library catalogue, Choice of an inner form fo...

Choice of an inner form for a library catalogue: As can be seen from the foregoing discussions of the inner forms of a library catalogue, no particular inner form would effect

Definition of volume and periodical publications, Definition of "Volume" : ...

Definition of "Volume" : Economy in  the cost of  binding. reduction in the number of undersized volumes difficult to handle, the need for splitting  over thick and composite

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd