Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

How can they affect the invoicing procedures, Question 1: You have just...

Question 1: You have just been appointed as Food & Beverage Controller of a major Food & Beverage operation within a medium-size hotel. Explain in detail the various areas you

Internal and physical form of the catalogue, Internal Form of the Catalogue...

Internal Form of the Catalogue: As mentioned earlier, according to the internal farm, the two major types of  library catalogues are the Dictionary Catalogue and the Classifie

Knowledge , Knowledge  The dictionary definition of knowledge is 'orga...

Knowledge  The dictionary definition of knowledge is 'organised body of information or the comprehension and understanding, consequent on having acquired an organised body of

Hrd in. indian libraries and information centres , HRD IN. INDIAN LIBRARIES...

HRD IN. INDIAN LIBRARIES AND INFORMATION CENTRES HRD as discussed in this Unit may seem to be somewhat irrelevant to the conditions prevailing in Indian libraries and informa

Rightpages and science direct, RightPages and Science Direct: Online ...

RightPages and Science Direct: Online Document Delivery Services Another two publishers, namely Springer-Verlag and Elsevier Science, have announced launching of online docum

Cost of materials handling, Cost of Materials  Handling: The last  major  ...

Cost of Materials  Handling: The last  major  factor  is cost of  various  devices which  are available  for  use. Cost  comparisons among various alternatives are often  difficul

What motivates companies to indulge in major merging, QUESTION 1 What m...

QUESTION 1 What motivates companies to indulge in major merging or taking-over endeavours as a strategy to increase output and revenue? QUESTION 2 Short-, medium-, and

Explain e-compensation tools, In most modern organizations, the employment ...

In most modern organizations, the employment relationship has shifted from being life-long with career management provided by the organization into being more short-term with emplo

Unrecognised to institutionalised communities of practice, U nrecognised t...

U nrecognised to institutionalised The Communities of Practice have many varieties of relationships to with the  organisations which range from completely the unrecognised to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd