Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Questions and answers while going for a negotiation, Let us review some que...

Let us review some questions that as a negotiator you can face while conducting a negotiation and the considerations to find answers to these questions:  Framing the opening

Cluster sampling, Cluster Sampling In cluster sampling there  is  a su...

Cluster Sampling In cluster sampling there  is  a successive random . sampling of units. The first unit  to  be sampled is large grouping or clusters. For example,  in  drawin

Cd-rom networks, CD-ROM Networks CD-ROM has become an important medium...

CD-ROM Networks CD-ROM has become an important medium for the storage and dissemination of information. Many information products are now available on CD-ROM. CD-ROMs represen

Major ecosystems in the tropical marine environment, Problem: (i). De...

Problem: (i). Define the term ‘ecosystem' (ii). What are the three major ecosystems in the tropical marine environment. (iii). State and explain four main ecological

Caselet, critically analyze mr. vincent’s reasoningtion?

critically analyze mr. vincent’s reasoningtion?

Nature of documents - library classification, Nature of Documents: The...

Nature of Documents: The problem of collection, storage and retrieval of documents has been complicated by the following factors: The steady growth in the output of various

Card services - library management, Card Services   Eminent librarians ...

Card Services   Eminent librarians like Charles Jewett, Albert Blor, Henry Stevens, F. Max Mueller, W.C.Lane, Melvil Dewey and several others advocated centralised cataloguing

Library building-library management, LIBRARY BUILDING Libraries come i...

LIBRARY BUILDING Libraries come in various types and  sizes  to fulfill certain specific needs of the community it is established to serve. Thus we  can have a single room vil

Style of a research review, STYLE OF A RESEARCH REVIEW: The  review mu...

STYLE OF A RESEARCH REVIEW: The  review must be brief but complete in itself. Systematic review should be considered. The review should use statements of opinions, sparingly,

Outline the organisational and behavioural factors, Question 1: Describ...

Question 1: Describe what is meant by ‘skilled-based', ‘rule-based' and knowledge-based behaviour. Explain in each case how these operating levels can give rise to human error

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd