Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Interval measurement - levels of measurement, Interval Measurement: It  i...

Interval Measurement: It  is a  scale based on equal units of measurement indicating how much of  a given attribute is present  in the subject. It exhibits equal differences  ia

Organization of petroleum exporting countries (opec), Organization of Petro...

Organization of Petroleum Exporting Countries  (OPEC) This is the most important international commodity group (ICG) in the world. It is the model of a successful internationa

Pest framework to analyse the business environment, QUESTION 1 Apply Po...

QUESTION 1 Apply Porter's Five Forces Model to UTM explaining how it can be used by the University to assess the attractiveness of the Tertiary Education Sector QUESTION 2

Information may replace inventory., Explain what you understand by this sta...

Explain what you understand by this statement in the context of strategic inventory management.

Public procurement management, A Public Body has conducted a bidding exe...

A Public Body has conducted a bidding exercise through the Restricted Bidding Method for the procurement of five PCs, five laser printers, two UPS and one scanner. Bidders were

Differentiate between overt and covert resistance to change, Question: ...

Question: "Resistance to change is not only a predictable part of change, it is perhaps the most difficult phase to deal with. People resist change for good reasons, even thoug

Forcast demand, A firm uses simple exponential smoothing with à=0.1 to forc...

A firm uses simple exponential smoothing with à=0.1 to forcast demand.the forecast for first week of february was 500units whereas actual demand turned out to be 450units....1.for

Discuss the different policies and factors for rural tourism, QUESTION ...

QUESTION Rural tourism represents a merging of perhaps two of the most influential yet contradictory features of modern life. Not only are the forces of economic, social, cultu

Describe the communication difficulties that may exist, Question 1 You ...

Question 1 You have been requested by your Superior to deliver a speech to a hundred parents on the importance of a balanced diet for their children. Describe the communication

Project approaches for capability development, P roject Approaches for Cap...

P roject Approaches for Capability Development The project team must understand the difference between quality assurance and control. Both are the essential elements of qualit

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd