Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Explain an alternative model of change, Question: "According to Lewin, ...

Question: "According to Lewin, change underlies the modification of those forces that keep a system's behaviour stable" (a) Why do people in organisations at times prefer t

Investment anlysis mangement, define,fuctions, principals, and introduction...

define,fuctions, principals, and introduction,how to speculation

Discuss and analyze the set of inter-related factors, QUESTION 1 The mu...

QUESTION 1 The museums of today serve increasingly complex institutional missions and diverse audiences through their programs. Critically discuss and analyze the role of museu

Gestalt alphabetisation, Gestalt Alphabetisation   Ranganathan was foll...

Gestalt Alphabetisation   Ranganathan was following the Gestalt Aplhabetisation to a severe degree in the earlier editions of CCC up to the 3rd edition published in 1951. In th

Explain security risk management process, Question: a) Describe why the...

Question: a) Describe why the following security measures are important for e-banking and how are they implemented? (i) Data Confidentiality (ii) Data Integrity (iii) Aud

Prepare an asset for the company, Branding started because companies wanted...

Branding started because companies wanted their services and products to be distinguishable from the generic dross of others and prepare an asset for the company. This is still the

Explain the term public relations, (a) Explain the term Public Relations (P...

(a) Explain the term Public Relations (PR) as per the British Institute of PR and illustrate the relevance and interdependence of i. PR and marketing and ii. PR and adverti

Advantages and disadvantages of stock verification, Advantages and Disadvan...

Advantages and Disadvantages of Stock Verification Some of the advantages  and disadvantages of stock verification are listed in this section.  Advantages  •  By revea

Define creativity, Question 1 What are special events? Give example. Wh...

Question 1 What are special events? Give example. What is meant by vision statement? What are the components of a good vision statement? Question 2 Every bidding doc

What do you understand by contract management, QUESTION When a company ...

QUESTION When a company is forming long-term outsourcing relationship with another company, the foundation of the success of the venture is a good contract management (a) Wh

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd