Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Individual ministerial responsibility, QUESTION 1 Explain clearly the m...

QUESTION 1 Explain clearly the meaning of the following- (a) Collective Responsibility of Ministers (b) Individual Ministerial Responsibility QUESTION 2 "Some pol

Define and explain the term management, Question 1: (a) Define and expl...

Question 1: (a) Define and explain the term management. (b) What are the roles of managers in an organisation? (c) Rather than managers, organisations require leaders. D

Comparison of cobit 4.1 and cobit 5, Comparison of CobiT 4.1 and CobiT 5 ...

Comparison of CobiT 4.1 and CobiT 5 This review of CobiT 4.1and CobiT 5 does not include all possible elements of these two complex frameworks. Still, this review is exhaustive

Environmental assessment and management, Environmental Assessment and Manag...

Environmental Assessment and Management: 1. Using a case study area of your choice, explain and demonstrate different understandings of nature, environment and / or landscape

Explanation of public relations, Problem Explain the key tools availabl...

Problem Explain the key tools available to carry out the public relations function. Explanation of Public relations Developing Media Relations Launching Media Tours

Forcast demand, A firm uses simple exponential smoothing with à=0.1 to forc...

A firm uses simple exponential smoothing with à=0.1 to forcast demand.the forecast for first week of february was 500units whereas actual demand turned out to be 450units....1.for

Discuss the relationship between treasury and alm, Question 1 ALM deals wi...

Question 1 ALM deals with strategic balance sheet management, which involves various risks, caused because of the changes in exchange rates and the position of liquidity, intere

Has fca be efficient in addressing privatization questions, Q. Has FCA be e...

Q. Has FCA be efficient in addressing privatization questions? Ans. Yes. Greensboro, North Carolina, faced this issue, and FCA was instrumental in trade with it. When the

Change management process, QUESTION 1 Failed organizational change init...

QUESTION 1 Failed organizational change initiatives leave in their wake cynical and burned out employees making the next change objective even more difficult to accomplish. Dis

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd