Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Negotiation skills , Negotiation Skills  Negotiation is an interactive ...

Negotiation Skills  Negotiation is an interactive process between two or more parties seeking to find common ground on an issue or issues of mutual interest. Negotiation is als

Define learning, QUESTION (A) Define learning (B) Playing on a backy...

QUESTION (A) Define learning (B) Playing on a backyard one day, three-year-old Albert is on a swing when a rabbit suddenly appears out of the bushes and startles him. He sli

Subject analysis- value-added information services, Subject Analysis: ...

Subject Analysis: Subject analysis is one of the longest established forms of added value in information services. It extends to the intellectual processes of indexing, classi

Define business ethics, Question 1 i) Discuss managing quality transform...

Question 1 i) Discuss managing quality transformation in organisation ii) Explain the concept of quality in manufacturing & services Question 2 Explain the different step

Observation sampling technique, Observation Sampling Technique: Since ...

Observation Sampling Technique: Since it  is usually impossible  to  observe behaviour for extended period of time because of fatigue and boredom  one must plan how and when t

Document selection - library management system, DOCUMENT SELECTION: Yo...

DOCUMENT SELECTION: You have seen that acquisition work includes three distinct phases of activities. Document selection is the first phase. There are two aspects in document

Construct a cedar eee analysis for an event, Question 1: You are to set...

Question 1: You are to set up your biggest conference room for a cocktail party for a renowned bank in Mauritius. The cocktail is scheduled to start at 19h00. However, the same

Centralised purchasing, What are the characteristics of centralised purchas...

What are the characteristics of centralised purchasing?

Develop negotiating strategy and tactics , Develop negotiating strategy and...

Develop negotiating strategy and tactics  These are two dimensions of the negotiating process. They are:  Strategy:  It has a long term focus. It is a predetermined app

Implement a successful conservation programme, Implement a successful conse...

Implement a successful conservation programme:  To implement a successful conservation programme, the staff must know:  The nature  of base materials and  manufacturing

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd