Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Subject analysis- value-added information services, Subject Analysis: ...

Subject Analysis: Subject analysis is one of the longest established forms of added value in information services. It extends to the intellectual processes of indexing, classi

Agreement - requirements of resource sharing library network, Agreements ...

Agreements The first agreement, obviously is the agreement to share currently owned materials (that is, to permit access to the holdings among partners), with protocols, limit

Terms related to procurement - supplies , Supplies  The supplier is res...

Supplies  The supplier is responsible for the delivery of goods/services that are ordered/contracted to him as per the order. However, purchaser has to ensure the goods are del

Construct a cedar eee analysis for an event, Question 1: You are to set...

Question 1: You are to set up your biggest conference room for a cocktail party for a renowned bank in Mauritius. The cocktail is scheduled to start at 19h00. However, the same

Data mining, Hi, I have a data mining solution which have be done using Rap...

Hi, I have a data mining solution which have be done using Rapid Miner 3.5 but I want some help to do a write up part and show the result that I got. So, I want you to answer quest

Value chain, For our project we have to describe a value chain for an airpo...

For our project we have to describe a value chain for an airport. Could you help me with what I need to describe at all the primary procesess.

Explain legal issues related to e-procurement, Question 1: As a procure...

Question 1: As a procurement manager of the public sector, discuss the factors that you will consider in the implementation of an e-Procurement system. Question 2: (i).

Ordering procedure - periodicals procurement, Ordering Procedure: We h...

Ordering Procedure: We have discussed the procedure until the selection is finalised and the lists and the cards are forwarded to  the Procurement Section for placing orders.

Distinguish between functional value and emotional value, Question 1: (...

Question 1: (a) Define the term "value". (b) Distinguish between functional value and emotional value. Illustrate by using relevant examples. (c) How can functional an

Implementation of the project and assign a time frame, Government has decid...

Government has decided to construct a tunnel via le Pouce Mountain to provide an alternative access to Port Louis for road users coming from the east. Assuming that roads on both s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd