Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Elements of binding - library management, ELEMENTS OF BINDING: The wea...

ELEMENTS OF BINDING: The wear and tear of books and other documents are normal features of most modem libraries. Binding and repair of damaged books and preserving them for lo

Perfect binding - library bindings, Perfect binding: The need to find ...

Perfect binding: The need to find a less expensive process for binding paperbacks led to the development of the 'perfect binding' - Considered as the most imperfect. This subs

Purchase order/contract, Purchase Order/Contract  A purchase order/cont...

Purchase Order/Contract  A purchase order/contract is issued to the supplier/contractor. The offer once accepted by the supplier/contractor becomes a legal contract by which th

Requirements of sustainability, Question 1: What are the important ste...

Question 1: What are the important steps a hotel could take in order to meet the environmental concerns of the country and the requirements of sustainability? Question 2:

Conservation - library management, Conservation: The second aspect of...

Conservation: The second aspect of maintenance work is book conservation. Only books in good physical condition should be allowed to stay  on shelves. Constant shelf checking

Explain the arbitrage pricing theory, QUESTION (a) Explain the Arbitrag...

QUESTION (a) Explain the Arbitrage Pricing Theory. In what ways the Arbitrage Pricing Theory is considered to be a superior model. What are its main limitations? (b) Disting

Discuss the relevance of evaluation, Problem: Dressel (1986) defines ev...

Problem: Dressel (1986) defines evaluation as "the collection and interpretation, through systematic and formal means, of relevant information which serves the basis for ration

Library cooperation, LIBRARY COOPERATION   Libraries have many things i...

LIBRARY COOPERATION   Libraries have many things in common. The processes and practices in several libraries are similar. Even the problems of management and services are commo

State and explain fully the capital asset pricing model, QUESTION (i) S...

QUESTION (i) State and explain fully the Capital Asset Pricing Model (CAPM) (ii) An asset X has an expected return of 20%. The risk free rate is 6%. Find the expected return

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd