Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Document delivery service - world scenario, DOCUMENT DELIVERY SERVICE .WORL...

DOCUMENT DELIVERY SERVICE .WORLD SCENARIO: Earlier libraries and information centres had no capability to deliver the documents other than to buy them from the publishers, dis

Operations strategy, describe the impact of operations strategy at differen...

describe the impact of operations strategy at different levels within the organization.

What are corals and coral reefs, Question 1: (i) What are corals and c...

Question 1: (i) What are corals and coral reefs? (ii) Illustrate with the help of a diagram the schematic representation of a coral polyp. (iii) Marine tourism is growi

Compensation management, In 2001, a Chennai- based two- wheeler major intro...

In 2001, a Chennai- based two- wheeler major introduced a bonus scheme for its employees. Employees covered under this bonus scheme are evaluated through a three-tier process- (1)

Inputs to quality planning process, I nputs to quality planning process ...

I nputs to quality planning process For  creating  an appropriate quality plan,  it  is very  important  to  provide proper inputs to the quality planning process. The various

Collation - binding processes, Collation: Collation is the first task ...

Collation: Collation is the first task in the binding processes. All the parts and the pages of a volume have to be correctly sequenced. In the case of periodicals, collation

Participative management, Participative Management Umbrella term encomp...

Participative Management Umbrella term encompassing management methods where employees share a significant degree of decision-making power with managers. These include MBO, con

Tools and techniques used for quality assurance, T ools and techniques use...

T ools and techniques used for quality assurance All the tools used for quality planning and quality control are used for quality assurance as well. In addition to these tools

Referral centres, Referral Centres: A referral centre is some sort of ...

Referral Centres: A referral centre is some sort of "information desk" for the scientific and technical community which does not provide enquirers directly with the informatio

Brand mangement, process of re branding of product or services?

process of re branding of product or services?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd