Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Functions of library classification , Functions of library classification :...

Functions of library classification : Functions of library classification can be summarised as follows: i) Library classification helps to arrange documents in a systemati

Human resource management, is it a good process if the human resource manag...

is it a good process if the human resource management adapt the long selection process to recruit the employer

Reference sources and books, THE REFERENCE SOURCES/ BOOKS: A basic qu...

THE REFERENCE SOURCES/ BOOKS: A basic question arises then when we start discussing reference books, that is what books and other materials a reference library should stock an

Sampling error and sampling bias, SAMPLING ERROR AND SAMPLING BIAS: Sa...

SAMPLING ERROR AND SAMPLING BIAS: Sampling error may  be  deiined  as the difference between  data obtained  from random sample and data  obtained  from  entire population.  E

Gilding and hollow backs - binding processes, Gilding:   Gilding or co...

Gilding:   Gilding or colouring edges may be done either at the time of trimming the edges or after cutting the boards. The purpose of gilding or colouring is primarily or prot

Areas of risk and causes of risk, A reas of risk and causes of risk Be...

A reas of risk and causes of risk Below are mentioned few areas and causes of risk. The term „operator? used in this listing means the owner (you) who awards the contract to t

Define a marine protected area, Question: (i) Define a Marine Protecte...

Question: (i) Define a Marine Protected Area; what are the types of Marine Protected Areas that exist in the Republic of Mauritius, naming one example of each (ii). What i

Physical mobilisation, The areas to be considered while monitoring and cont...

The areas to be considered while monitoring and controlling a contract are wide spread. They are: P h y sical mobilisation: In this stage, the contractor gathers people, m

Functional organisation - information centres, Functional Organisation: ...

Functional Organisation: The library is expected to take care of selection, acquisition and storage of documents. The documentation/information centre, in collaboration with t

Constraints - library catalogue code, Constraints: This unit calls for...

Constraints: This unit calls for a comprehensive and thorough treatment to cover the various aspects of history and development of library catalogue codes. However, such a tho

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd