Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Product development cycle, Product development cycle   All products unde...

Product development cycle   All products under development typically follow the cycle of market place-to-market place. The development starts with identification of a product in

Closed loop, . Write a note on tracing a closed loop. What are the ch...

. Write a note on tracing a closed loop. What are the characteristic features of a closed loop?..

Integral part of effective management, Problem: 1 "Inventory control i...

Problem: 1 "Inventory control is an integral part of effective management." Discuss. 2 A large firm uses an average of 50 packages of copier paper a day. The firm operate

Set up a cost control system, Question 1: Set up a cost control system ...

Question 1: Set up a cost control system for a newly established hotel. i) Explain how you would proceed. ii) What set of documentation you will require and wh

Managerial Innovation, What are the implications of management innovation i...

What are the implications of management innovation in a banking industry

Primary sources of information, Primary Sources These are materials, w...

Primary Sources These are materials, which are the most authentic and original. They usually take the form of a a monograph, journal article, dissertation, report or a paten

Referral centres, Referral Centres: A referral centre is some sort of ...

Referral Centres: A referral centre is some sort of "information desk" for the scientific and technical community which does not provide enquirers directly with the informatio

Public procurement management, A Public Body has conducted a bidding exe...

A Public Body has conducted a bidding exercise through the Restricted Bidding Method for the procurement of five PCs, five laser printers, two UPS and one scanner. Bidders were

Importance of the different stages in the process, QUESTION 1 (a) Descr...

QUESTION 1 (a) Describe the various stages of a strategic management process .and explain the importance of the different stages in the process (b) Can unexplained strategie

Use vogel''s approximation method to obtain an solution, Question (a) A...

Question (a) A plastics manufacturer has 1200 boxes of transparent wrap in stock at one factory and another 1000 boxes at its second factory. The manufacturer has orders for th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd