Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

In project management there are three primary variables, QUESTION In pr...

QUESTION In project management, there are three primary variables: the amount of work to be done; the amount of time available (calendar time, not person-years); and the amount

Planning and organisation, PLANNING AND ORGANISATION: The major items ...

PLANNING AND ORGANISATION: The major items of work are classification and cataloguing. They are of a highly  technical nature and accuracy is the very essence of all technical

Shifting and reshifting books - library management, Shifting and Reshifting...

Shifting and Reshifting Books: In order to take away the monotony of appearance of shelf arrangement and to introduced an element of novelty,  books have to be reshuffled to

High standard of ethical behaviour, Problem: ‘Government officials resp...

Problem: ‘Government officials respond to incentives and disincentives. They are unlikely to undertake policies that are generally unpopular or that will lose them powerful sup

Space allocation utilization and management-library building, Space Allocat...

Space Allocation Utilization and Management of library building in library managenent Library planning constitutes correct estimation  of space required for various activities

Discuss the role of nabard in rural housing development, Question 1 Develo...

Question 1 Development Banks or Development Financial Institutions (DFIs) in India were established mainly to provide long term capital for industry and trade. Write a detailed no

Purchase order/contract, Purchase Order/Contract  A purchase order/cont...

Purchase Order/Contract  A purchase order/contract is issued to the supplier/contractor. The offer once accepted by the supplier/contractor becomes a legal contract by which th

Operations strategy, describe the impact of operations strategy at differen...

describe the impact of operations strategy at different levels within the organization.

Describe the guidelines of change management, Question 1 Define strategic ...

Question 1 Define strategic quality management. Describe the elements of strategic quality management Question 2 Explain the types, advantages and drawbacks of qualitative re

Write short notes on any two kinds of leaders, Question 1 Define communica...

Question 1 Define communication. Explain function and purpose of communication Question 2 Write down the advantages and disadvantages of oral communication Question 3 Wh

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd