Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

What are the challenges that managers face, Question 1: What are the ch...

Question 1: What are the challenges that managers face in implementing successful change? - challenges that managers face in implementing successful change Question 2:

Help me, What are some study techniques that I can use to study for the ACT...

What are some study techniques that I can use to study for the ACT??

Key principles of total quality management, QUESTION (a) Medicines are ...

QUESTION (a) Medicines are much specialised form of consumer product. They must be safe, effective and suitable for their intended purpose. Quality Assurance (QA) in pharmaceut

Classification scheme - technical processing, Classification Scheme: A...

Classification Scheme: A scheme of classification is but a tool in the hands of the library to organise subjects and to serve them out in an efficient way. Therefore, it is ne

Write break down or corrective or remedial maintenance, Question 1 Write b...

Question 1 Write break down or corrective or remedial maintenance. Question 2 Explain the planning principles in maintenance management, Question 3 The principles used i

Describe the characteristics of a confined space, Question 1: (a) Des...

Question 1: (a) Describe the characteristics of a confined space. (b) By reference to entry into a confined space, describe briefly the factors that should be considered

Acquisition through donations - library administrations, Acquisition Throu...

Acquisition Through Gifts/Donations: Gifts and donations constitute an important source acquisition of reading materials in a library. Many a library has benefited enormously

Classified catalogue code -british museum cataloguing rules , Classified Ca...

Classified Catalogue Code: Ranganathan (Shiyali Ramamrita) (1892-1972). Classified Catalogue Code with Additional Rules for Dictionary Catalogue Code. Ed 5. Assisted by A Neel

Trade discounts - library administration, Trade Discounts: Trade disco...

Trade Discounts: Trade discounts area common feature in book purchases. The discounts may vary according to categories of publications. Normally a 10% discount is admissible o

Organizational culture, Organizational Culture A common perception held...

Organizational Culture A common perception held by the industries members is a system of shared meaning. For most people, organizational culture is something they cannot descri

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd