Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

What are sbus and how effective are they, QUESTION 1 Discuss the strate...

QUESTION 1 Discuss the strategic decision making process. Support your answer with examples from an industry of your choice QUESTION 2 a) What are SBUs and how effectiv

What is meant by organisational change, Question 1 Explain the importance ...

Question 1 Explain the importance of Organisational development to managers. Describe the characteristics of Organisational Development Question 2 What is meant by Organisati

International marketing, List out the secondary sources of information whil...

List out the secondary sources of information while pursuing market research

Importance of an environmental impact assessment, Question 1: (a) Ident...

Question 1: (a) Identify and clearly explain the benefits of implementing ISO 14001? (b) Describe the importance of an Environmental Impact Assessment (EIA). Explain the are

Basic materials handling principles, Basic  Materials Handling Principles ...

Basic  Materials Handling Principles 1.  Lest Handling  is Best Handling: it is  best to keep  the handling  cost of the  minimum  because  handling  does not add value  to

What are the basic components of inventory, Question: (a) What are the ...

Question: (a) What are the basic components of inventory? (b) Name the steps for finding the optimum inventory. (c) What are the assumptions for the Economic Order Quanti

State two reasons for establishing a marcom plan, Question: (a) Th...

Question: (a) There are different types of advertising strategies adopted by Organizations in order to increase their sales force. The strongest advertising strategies

Human resource development-need and purpose, Need and Purpose The per...

Need and Purpose The personnel of an organisation play the most vital role by converting all the other  resources into tangible products and services.. Therefore attention to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd