Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

What are sbus and how effective are they, QUESTION 1 Discuss the strate...

QUESTION 1 Discuss the strategic decision making process. Support your answer with examples from an industry of your choice QUESTION 2 a) What are SBUs and how effectiv

What do you mean by incoterms, Question 1 Discuss the features of inter...

Question 1 Discuss the features of international business environment. Why is it necessary to closely analyse the international environment? Question 2 What is the role

Direct ordering with publishers and standing vendor method, Direct Ordering...

Direct Ordering with Publishers: Due to the inefficiency of local booksellers,  many a library has resorted to the practice of directly ordering with publishers or their local

Simplest transporting devices, The simplest transporting devices are wh...

The simplest transporting devices are wheel barrows and hand trucks. These are still in use in number of small industries all over the country. Figure (a) shows a ha

Reference and information access tools, REFERENCE AND INFORMATION  ACCESS ...

REFERENCE AND INFORMATION  ACCESS TOOLS: Libraries have always been engaged in providing services to their users. Maximum utilization of resources is the principle underlying

Reasons for mergers and acquisitons, There are numerous reasons for a compa...

There are numerous reasons for a company to peruse M and A. Some of them are listed below: The M and A are undertaken to achieve specific financial, business and strategic

Study carrel -reader activity area of library building, Study carrel -Reade...

Study carrel -Reader Activity Area of library building -library managenent Study carrels are exclusive areas, located in quieter and undisturbed part of the library, which are

Population - definition and concepts, Population is the entire aggregatio...

Population is the entire aggregation of  cases that meet the designated set of criteria. It  includes a complete set of persons or objects that possess same characteristics that

Change manager, T he change manager The change manager is accountable ...

T he change manager The change manager is accountable for the day to day activities of the change management process for the Information Management team. This person  must  es

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd