Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Periodicals receiving work, PERIODICALS RECEIVING WORK: The work of re...

PERIODICALS RECEIVING WORK: The work of receiving periodicals is perhaps the most difficult activity in the Periodicals Department. It requires thoughtful planning and systema

What are the main styles of negotiation, Question 1: What are the alter...

Question 1: What are the alternative ways in which a decision can be made that affects the parties involved? In what ways will negotiation be seen as a tactical contest?

Records and registers - library management, RECORDS AND REGISTERS - library...

RECORDS AND REGISTERS - library management: The Acquisition Department has to use appropriate records, registers, files, forms and other stationery at the various stages  of i

Corporate social responsibility (CSR), ETHICS AND SOCIAL RESPONSIBILITY AT ...

ETHICS AND SOCIAL RESPONSIBILITY AT … Select a company of interest to you (Fortune 500, Not-For-Profit, etc.) Examples of corporations that could be used are: • Tommy Hilfiger at

Production and materials management, Explain intermittent and continuous op...

Explain intermittent and continuous operations. Under what type of situation it would be used in automobile industry?

Output of quality planning process, O utput of quality planning process ...

O utput of quality planning process Quality management plan is one of the major outputs of quality planning. It describes how the project management team will implement  the q

Information and other related concepts, INFORMATION AND OTHER RELATED CONCE...

INFORMATION AND OTHER RELATED CONCEPTS: You may often hear or read in newspapers and other popular magazines about "exponential growth of information" or "explosion of informa

Special furniture items-library furniture-library management, Special Furni...

Special Furniture Items-library furniture-library management Besides the above mentioned library furniture, a few other items worth considering are:  Book trolley, whi

Document delivery service(dds), Document Delivery Service (DDS): Docum...

Document Delivery Service (DDS): Document Delivery Service is actually concerned with the supply of documents to the users on demand, either in original or its copy in print o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd