Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Lp modles, how do you write a lp model in standard form? ex) max z=9x+6x ...

how do you write a lp model in standard form? ex) max z=9x+6x subject to 12x+5x x

Discuss how culture affects management, Question: The ‘external environ...

Question: The ‘external environment' of a firm represents basically the forces and institutions outside the organization that may affect organizational performance. (a) Def

What are the steps to the fade qi model, Question 1 Write short notes on t...

Question 1 Write short notes on the Quality planning an element of Quality management Question 2 What are the steps to the Fade QI model? Question 3 Quality costs are th

Increase in demand, Increase in Demand: Exponential growth in the volu...

Increase in Demand: Exponential growth in the volume of published information, increase in the number of users and availability of large number of online and C D - R OM  bibli

Use of fca dispirit communities, Q. Will the use of fca dispirit communitie...

Q. Will the use of fca dispirit communities from allowing the environment while they consider solid waste management options? No. While FCA only obtain into account the tangibl

Explain the process involved in hr audit, Question 1 Explain the opportuni...

Question 1 Explain the opportunities and challenges in healthcare HRM Question 2 Discuss employee grievance systems in healthcare Question 3 Transactional analysis

Define learning organization, Question 1 What is change management? Explai...

Question 1 What is change management? Explain the importance of change management Question 2 Define Organisational Life Cycle. List and explain the stages in organizational L

Periodicals selection - library management, PERIODICALS SELECTION: In ...

PERIODICALS SELECTION: In Section 8.2, you have seen that acquisition work includes three distinct phases of activities. Periodicals selection is the fist phase. The selection

Functions of documentation and information centres, FUNCTIONS OF DOCUMENTA...

FUNCTIONS OF DOCUMENTATION AND  INFORMATION CENTRES: In general, a documentation or an, information centre brings to the attention of specialist users the current as well as r

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd