Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Public management-type of reforms in developing countries, QUESTION (a)...

QUESTION (a) There appears to be an emerging consensus that the movement towards good governance must include initiatives to strengthen the institutions of government and civil

Cobol, Write a COBOL program to accept three subject marks and to display t...

Write a COBOL program to accept three subject marks and to display the total of marks and percentage of marks.

What is fibre, Question 1) What is fibre? Explain classification of natura...

Question 1) What is fibre? Explain classification of natural fibers Question 2) Narrate the characteristics of Polyester fabrics Question 3) Write short notes on c

Analyze the destination life cycle concept, QUESTION The potential rele...

QUESTION The potential relevance of the concept of a destination life cycle has been examined in a number of studies. The model has apparent potential to advance theory and pra

Explain the essential training required for all your staff, Question: Y...

Question: You have been appointed as the Estate Manager of La Gaulette Integrated Resort. The project has just started and you have been appointed during the construction phas

Different types of hospitality offering businesses, Question 1: (a) Sho...

Question 1: (a) Show what is meant by the managerial environment? Illustrate your answer with specific examples using both internal and external environmental influences within

Horizontal and vertical integration strategies, QUESTION 1 (a) Comment ...

QUESTION 1 (a) Comment on the generic competitive strategies as proposed by Porter with the use of suitable examples (b) Briefly elaborate, with relevant examples, your unde

Process standards, P rocess standards Organisations require a set of p...

P rocess standards Organisations require a set of process management standards that indicate how well their processes are managed and if they are on course for continuous impr

R charts, R Chart In this part we are going to look at control charts w...

R Chart In this part we are going to look at control charts which are directed towards monitoring the variability in case of individual characteristics like the variability in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd