Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Agency method - , Agency Method: The jobs included in the case of the ...

Agency Method: The jobs included in the case of the agency method can be listed as follows: Sending list of periodicals asking for pro-forma invoice from the agent Scrutinisin

Laws of library science, The study of the structure and development of the ...

The study of the structure and development of the UoS by the information professional can be shown to be a necessary implication of the five laws of library science. Law 1 And I

Individual ministerial responsibility, QUESTION 1 Explain clearly the m...

QUESTION 1 Explain clearly the meaning of the following- (a) Collective Responsibility of Ministers (b) Individual Ministerial Responsibility QUESTION 2 "Some pol

Stack guides - library management, Stack Guides: Guides are to be put...

Stack Guides: Guides are to be put up at different places in the library in order to enable a user to find his/ her way into different parts of the library with minimum of ass

Advantages of an enterprise project management system, A d v antages of ...

A d v antages of an EPM System Let us now see some of the advantages of EPM are: One of the key rewards of converting to an EPM system is that projects have superior

Definition of library classification, Definition of Library Classification:...

Definition of Library Classification: Having understood the meaning of classification in library science, let us now go through a few well-known definitions of library classif

Elaborate the different types of benchmarking, QUESTION (a) Explain, us...

QUESTION (a) Explain, using examples, the Prevention, Appraisal and Failure (PAF) model for measuring quality costs and briefly assess its potential for use in a service organi

Define the term crystallized intelligence, QUESTION 1 a. Describe the 4...

QUESTION 1 a. Describe the 4 identity statuses put forward by James Marcia b. Adolescence is often described as a period of storm and stress [Hall. 1904]. Evaluate this clai

Critically analyse what political and business leaders, "Sustainable" is a ...

"Sustainable" is a word/concept that is more frequently being used in Mauritius, both by government bodies and private companies. Some are working towards environmental protection

Briefly discuss the motivations behind this trend, QUESTION 1 (i) Discu...

QUESTION 1 (i) Discuss the key activities of the strategic management process'. Explain why it is important for managers to recognise the interdependent nature of these activit

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd