Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Need for defining the problem - research topic, NEED FOR DEFINING THE PROBL...

NEED FOR DEFINING THE PROBLEM Problem clearly stated is a problem half solved. A proper definition of research problem will enable you as the researcher to be on the track whe

Jewetts rules - british museum cataloguing rules, Jewetts Rules - British m...

Jewetts Rules - British museum cataloguing rules: Jewett, Charles Coffin. Smithsonian report on the construction of catalogues of libraries and their publication by means of s

Direct contracting, Direct contracting is another procurement method that ...

Direct contracting is another procurement method that is used under a limited number of exceptional circumstances. In Direct contracting method, contract for works or supply is ma

Rajender Kumar was a production worker at competent , #questioWhom do you t...

#questioWhom do you think Rajender will eat with? Why? 2. If you were one of the other foremen, what could you do to make Rajinder’s transition easier? END OFn..

Case studies in Public sector Management, Writing a case report analysis on...

Writing a case report analysis on public sector management

Sample and sampling, Sample and Sampling  The  sample represents  the popu...

Sample and Sampling  The  sample represents  the population of  those critical characteristics you  plan to  study. In other words,  if the  sample  is representative of  th'e pop

User approaches - need for catalogue entries, User Approaches   We have...

User Approaches   We have seen the purpose and functions of a catalogue. By using a library catalogue we can find out the various documents available in the library, without ph

Purpose and objectives of binding - library management, Purpose and Objecti...

Purpose and Objectives of Binding : Unlike private collection, books in libraries are to be used by successive groups-be it a public library or an academic library-and hence n

Explain what the term preventive legal management address, Question 1: ...

Question 1: (a) Explain what the term "preventive legal management" addresses. (b) Describe any 5 stakeholders that have a legal relationship within the hospitality indust

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd