Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Porter''s five forces model, QUESTION 1 Implementation of selected stra...

QUESTION 1 Implementation of selected strategies is a phase in the strategic management process. Discuss the key issues that need to be considered in this phase. QUESTION 2

Syringe management plan, The purpose of this Syringe management plan is to ...

The purpose of this Syringe management plan is to protect the social community against injuries caused by syringes and help people manage the use of syringes in a safe and healthy

Write a mission statement for burger king, QUESTION 1 The survival of a...

QUESTION 1 The survival of any business enterprise is dependent on its competitive spirit in the business world. Using the Porter's Five Forces model, identify the competitive

Information services, INFORMATION SERVICES: In the earlier Unit of thi...

INFORMATION SERVICES: In the earlier Unit of this Block (Block 1, Unit 1), you have learnt about the concept and need for information. In this context, it has been emphasised

Periodicals selection - library management, PERIODICALS SELECTION: In ...

PERIODICALS SELECTION: In Section 8.2, you have seen that acquisition work includes three distinct phases of activities. Periodicals selection is the fist phase. The selection

Spontaneous or intentional communities of practice, S pontaneous or intent...

S pontaneous or intentional Most of the Communities of practice begins without any intervention or the development effort from the organisation. The members spontaneously join

Explain what is meant by e-commerce, Question 1: (a) Operations managem...

Question 1: (a) Operations management is an integral part of an organisation. Show how operations management can contribute to the success of an organisation. (b) Differen

Responsibility for loss of books, Responsibility for Loss of Books: In...

Responsibility for Loss of Books: In a majority of libraries of the western countries, librarians are not held responsible for books losses, but many organisations in India co

Document accessioning - library management, DOCUMENT ACCESSIONING: All...

DOCUMENT ACCESSIONING: All the books and documents received in the  library are taken into its stock  by a process called Accessioning which involves the assignment of a seria

Force account , Force Account  You have learnt that direct contracting ...

Force Account  You have learnt that direct contracting is used under a limited number or exceptional circumstances without inviting any open bids.  Force account is to make

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd