Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Write short notes on pert, Question 1 The PMBOK Guide addresses four eleme...

Question 1 The PMBOK Guide addresses four elements related to scope. List and explain them Question 2 Write short notes on PERT Question 3 Explain the various planning p

Architecture of library building -library management, Architecture of libra...

Architecture of library building in library management Library activity is a specialised activity and it should be designed so as to carry out this activity  efficiently in a

Documentation and information centres and databases , DOCUMENTATION AND INF...

DOCUMENTATION AND INFORMATION CENTRES AND DATABASES:   Traditionally, libraries have been collecting various kinds of publications and holding them in readiness for use by scho

Describe talent management system, Problem 1: What is the importance of...

Problem 1: What is the importance of talent management? Describe Talent management Importance of Talent management Problem 2: Describe the five stage approa

Case study, Rajender Kumar was a production worker at competent Motors Limi...

Rajender Kumar was a production worker at competent Motors Limited (CML) which made components and accessories for the automotive industry. He had worked at CML for almost seven ye

Acquisition, A c quisition An acquisition is slightly different from ...

A c quisition An acquisition is slightly different from a merger. Unlike all mergers, all acquisitions  involve  one  company  purchasing  another  -  there  is  no exchange

Describe carefully the forms of organizational culture, QUESTION 1 (a) ...

QUESTION 1 (a) What is an organization? (b) What is management? (c) Describe carefully the functions of managers in organizations QUESTION 2 Organisations are com

Prepare an asset for the company, Branding started because companies wanted...

Branding started because companies wanted their services and products to be distinguishable from the generic dross of others and prepare an asset for the company. This is still the

Main activities during the construction of the factory, Question 1: Rea...

Question 1: Read the following and answer the questions below. You are the Health and Safety Officer of a big industrial group which is constructing a new factory in which o

Test for the apt model on the stock exchange, QUESTION (i) Compare and ...

QUESTION (i) Compare and contrast the Capital Asset Pricing Model (CAPM) with that of the Arbitrage Pricing Theory (APT) (ii) Asset A has an expected return of 25% and the r

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd