Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Document delivery service(dds), Document Delivery Service (DDS): Docum...

Document Delivery Service (DDS): Document Delivery Service is actually concerned with the supply of documents to the users on demand, either in original or its copy in print o

Present level of production, General Components Ltd produces a component ‘...

General Components Ltd produces a component ‘X', the selling price of which is Rs 50. The unit cost structure based on the present level of production/sales of 100 000 units

Records and registers - library management, RECORDS AND REGISTERS - library...

RECORDS AND REGISTERS - library management: The Acquisition Department has to use appropriate records, registers, files, forms and other stationery at the various stages  of i

Steps literature search, STEPS LITERATURE SEARCH  There are many point...

STEPS LITERATURE SEARCH  There are many points to consider in making an effective literature search. The first and foremost step is to ascertain the purpose, scope, depth and

Factors affecting materials handling system, Factors Affecting Materials Ha...

Factors Affecting Materials Handling System  The followings four factors material handling system: Production  System: There  are two  basic  types  of production systems.

Forces model of competition in analyzing the industry, QUESTION 1 Manag...

QUESTION 1 Management's job is not to see the company as it is but as it can become. A strategy is a commitment to undertake one set of actions rather than another. Discuss thi

Alphabetical index - Classified catalogue, Alphabetical index: The alp...

Alphabetical index: The alphabetical index to a classified catalogue; consisting of author, title (wherever necessary), subject entries and other entries for collaborators, se

Cataloguing work - library management, Cataloguing Work: The objective...

Cataloguing Work: The objective of the catalogue is to provide nodes tool that give information about all documents available in a library. The catalogue  must be designed to

Discuss the significance of world heritage sites, QUESTION World herita...

QUESTION World heritage sites are identified as sites of outstanding global values that should be preserved for all humanity. Sites will be preserved for future generations and

Internal local format, Internal Local Format   Internal formats are so ...

Internal Local Format   Internal formats are so called because they are internal/local to a software system. They can be changed specifically as per the needs of the local syst

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd