Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Domain, D omain A community will be just a group of friends without th...

D omain A community will be just a group of friends without the commitment to the domain. A domain is not just the group of people with connections but it is an identity which

Stereotype, Stereotype The tendency to judge someone is based on the pe...

Stereotype The tendency to judge someone is based on the perception of the group to which that person belongs. For example I might stereotype him as a "jock" if I know a person

Library catalogue and the five laws of library science , LIBRARY CATALOGUE ...

LIBRARY CATALOGUE AND THE FIVE LAWS OF LIBRARY SCIENCE The Five Laws. of Library Science are a set of basic guiding principles for designing and operating a library or a libr

Discuss the characteristics of an effective leader, QUESTION 1 (a) Comp...

QUESTION 1 (a) Compare and contrast the quality culture in a traditional and a TQM organization (b) What do you understand by the PDCA cycle? QUESTION 2 (a) Discuss

Steps for force account , Steps for force account  Now that we are awar...

Steps for force account  Now that we are aware of the requirements for force account contracting, let us understand the steps involved in force account contracting:  1.  Est

Connecting professional development and corporate strategy, C onnecting pr...

C onnecting professional development and corporate strategy The CoP builds value by connecting the personal development and also the professional identities of the practitione

Compare and contrast the fundamental and technical analysis, Question 1 ...

Question 1 Explain the characteristics of investment. Differentiate between investment and speculation. Question 2 What do you understand risk and measurement of ris

Change manager, T he change manager The change manager is accountable ...

T he change manager The change manager is accountable for the day to day activities of the change management process for the Information Management team. This person  must  es

Practical application in conducting the interview, Practical Application  ...

Practical Application  in Conducting the Interview:  Interviews can be conducted by  face  to  face meeting, telephonically or video recording.  If possible interview should b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd