Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Different types of cultures prevalent in organisations, Question 1: (a)...

Question 1: (a) Describe, with the use of examples, Lewin's model of organisational change. (b) Explain either the "action research model" developed by Cummings & Huse or th

Public catalogue -circulation area in library building, Public Catalogue  ...

Public Catalogue  -Circulation Area in library building in library management Public catalogue is the key to the document collection in a library and frequently used by the re

Top level management & stakeholder involvement in six sigma, T op level ma...

T op level management commitment and stakeholder involvement -  Six   sigma   involves   top   level   management commitment as well as stakeholder involvement. Let us go into det

Library catalogue : objectives purposes and functions , OBJECTIVES Li...

OBJECTIVES Library catalogue is an important tool in a library and cataloguing is one of the most important activities of a library. In this Unit, you are introduced to a few

Ascertaining demand - library management, Ascertaining Demand: The met...

Ascertaining Demand: The methodology to be followed in ascertaining users' needs have been discussed in detail, in Unit 5 under Sec 5.2 Users' Studies of this Block 2. In addi

Explain these decision areas in detail, Question 1 Explain the four basic ...

Question 1 Explain the four basic varieties of layouts for manufacturing facilities Question 2 The major decision areas in supply chain management have both strategic and ope

What is tax planning, Question 1 How are taxable entities divided for the ...

Question 1 How are taxable entities divided for the purpose of determining their residential status? Question 2 What do you understand by expenditure on scientific research?

Components of hrd-mechanisms, Mechanisms The first step towards HRD is...

Mechanisms The first step towards HRD is to set up a unit in the organisation to deal exclusively with personnel development programmes. The mechanisms to implement these prog

Major issues to consideration during strategy implementation, QUESTION 1 ...

QUESTION 1 Using appropriate examples from the hospitality industry illustrate how a company may benefit from integrative types of strategies QUESTION 2 Before executiv

What are the main elements of tqm, QUESTION 1 (a) What do you understan...

QUESTION 1 (a) What do you understand by the term 'Enterprise Resource Planning (ERP)? Discuss the evolution of ERP (b) How business process re-engineering can be integrated

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd