Flexibility in contracts, Other Management

Assignment Help:

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.


Related Discussions:- Flexibility in contracts

Determine the length of the dipole, Question: (a) A uniform linear arr...

Question: (a) A uniform linear array consists of 20 vertical dipoles, each spaced by half a wavelength in the horizontal plane. (i) If all array elements are fed in phase,

Value of information services , VALUE OF INFORMATION SERVICES: At the ...

VALUE OF INFORMATION SERVICES: At the outset, it must be emphasised that there is no consensus of opinion among information scientists and professionals regarding the "concept

Main activities during the construction of the factory, Question 1: Rea...

Question 1: Read the following and answer the questions below. You are the Health and Safety Officer of a big industrial group which is constructing a new factory in which o

Explain briefly the meaning of energy management, Question 1: (a) Disc...

Question 1: (a) Discuss the use of the following fuels in the Mauritian context. Comment specifically on their impact on the economy and on the environment. i. Coal ii.

Microforms - non-print materials, Microforms: Micropublishing is retro...

Microforms: Micropublishing is retrospective, being merely the reprinting of previously existing materials. Back files of newspapers,  periodicals and out-of-print materials a

List the distinguishing characteristics of a project, QUESTION a) In th...

QUESTION a) In the day to day operations of the organisation daily activities are carried. Project management activities are also carried out in a planned manner. List the dist

Organizational behavior, what type of errors would you be prone to make whi...

what type of errors would you be prone to make while making these judgement towards goofing employees?

Describe the characteristics of a confined space, Question 1: (a) Des...

Question 1: (a) Describe the characteristics of a confined space. (b) By reference to entry into a confined space, describe briefly the factors that should be considered

Responsibilities of a registered safety and health officer, Every employer ...

Every employer who employs more than 100 persons in his enterprise must, under section 30 of the Occupational Safety and Health Act 2005 appoint a registered Safety and Health Offi

Types and structure, Types and Structure: Types and Structure The  des...

Types and Structure: Types and Structure The  design of a useful  schedule normally  involved extensive planning, consultation with  colleagues and experts, pretesting and rev

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd