Measure the free length of the bolts ultrasonically. This must be done prior to applying any load to the bolt.

Install bolts on the bottom half of the flange. The bolts must extend one to one and a half bolt diameters from the face of the nut on the side to be tensioned.

Install the gasket on the flange surface to be sealed. The gasket shall be located centrally in the flange assembly. The gasket shall not be forced into position.

Bring the opposing flange into contact with the gasket.

Assemble Hydraulic Bolt Tensioners on the first set of bolts in the pattern (50% of the bolts).

Pressurize the tensioners to the first pass pump setting. Turn the nuts down against the flange face.

Release the pressure after the required pressure is reached and the nuts have been turned down against the joint face.

Transfer the Hydraulic Bolt Tensioners to the second set of bolts in the pattern.

Measure the residual stress in the bolts ultrasonically.

Following hydrotest, complete a check of the bolt stress levels in 5% of the bolts on any flanges sized NPS 24 and above, or with pressure ratings Class 900 and above.

Once the tensioning procedure is complete, apply a liberal coating of lubricant to the stud ends protruding from the nuts.


Related Discussions:- Flange assembly with bolt tensioning

Determine the position and magnitude, The intensity of loading on a simply ...

The intensity of loading on a simply supported beam of 5m span increases uniformly from 8KN/m at one end to 16KN/m at the other end. Determine the position and magnitude of the max

Duty cycle, Duty cycle The concept of duty cycle is to be clearly under...

Duty cycle The concept of duty cycle is to be clearly understood before operating any machine. Unlike the arc welding power sources, the resistance welding power sources are de

Selection of electrodes and filler metals, Q. Selection of Electrodes and F...

Q. Selection of Electrodes and Filler Metals? Only low hydrogen electrodes shall be used for SMAW of all carbon and low alloy steels, except for root pass welding of single wel

#power plant, Components of power plant &it''s functions

Components of power plant &it''s functions

Foundry, properties of moulding sand

properties of moulding sand

Gear complaints of engine starting, Gear Complaints Nature of Complaints (...

Gear Complaints Nature of Complaints (a) Gear shifting hard (b) Gear slipping (c) Gear noise

Spring, direct shear and torsional shear of the coil

direct shear and torsional shear of the coil

Mounting systems for the welding head-fixed type:, Fixed type In this se...

Fixed type In this set up, the welding head is kept fixed and the movement required during welding is provided through in the jobs to be welded. A typical application of this arr

Example of manufacturing lead time (mlt), Example of Manufacturing Lead Tim...

Example of Manufacturing Lead Time (MLT) A certain part is generated in a batch size of 100 units. The batch should be routed through five operations to complete the processin

Condition for a heat transfer process to occur, What the necessary conditio...

What the necessary condition for a heat transfer process to occur?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd