Q. Fixed vs pinned connection between piles and pile caps?

The type of connection amid piles and pile caps affects the load carrying capacity of pile groups. Fixity of pile head into pile cap, in place of pinning into pile cap, improves higher lateral stiffness of the pile groups. For example, for same deflections, a cap with fixed connected piles can withstand far more loads than that of pinned connected piles. To satisfy criteria of fixed connection, minimum embedded length of piles into pile caps must be at least two times the diameter of piles. 

Furthermore the fixed connection of piles at pile caps allows significant bending moment to be transmitted through the connections when compared with pinned connections.


Related Discussions:- Fixed and pinned connection between piles and pile caps

Assigning central pier and abutment as fixed piers, What are beneficial poi...

What are beneficial points of assigning central pier and abutment as fixed piers ?

Boundaries of rational method in calculating runoff, Question What are main...

Question What are main boundaries of Rational Method in calculating runoff? Answer Calculation of runoff is compound matter that depends on a lot of factors similar to ground

Cumulative error, diffrence between cumilative compensative error

diffrence between cumilative compensative error

Evaluate different gas turbine engine, Investigate and evaluate different G...

Investigate and evaluate different Gas Turbine Engine configurations in use for commercial or military Gas Turbine Engine aircraft. 1) Through research, investigate the differen

Determine the reliable moment capacity, Figure 2 details a typical T-beam u...

Figure 2 details a typical T-beam unit in a beam and slab floor with a span of L = 10 m. Determine the reliable moment capacity M ′ for the T-section shown. Take f c ′ = 32

Determine the interdependent phases of investigation, Determine the interde...

Determine the interdependent phases of investigation The following are the interdependent phases of investigation: i)  Stratigraphical survey, ii) Physical survey, and

Fluid mechanics, How a water bound macadam road is maintained

How a water bound macadam road is maintained

Retaining wall, I retained the soil in my yard by brick with 3 levels to a...

I retained the soil in my yard by brick with 3 levels to avoid sliding the soil to the street. the appeared part of the bricks from each level is 3 feet and less.The hidden part o

Normal stress, how does wrong calculations in normal stress cause partial o...

how does wrong calculations in normal stress cause partial or total collapse of a building?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd