Find out the joint distribution, Civil Engineering

Assignment Help:

Find out the joint distribution:

Let XI and X2 be two independent random variables each distributed uniformly in the interval [ 0, a ], where a > 0 is a constant. Find out the joint distribution of

Yl = Xl + X2 and Y2 = X1 - X2.

Instead, in vector notation, what is the distribution of Y = XA.

where

x = (X1,X2),Y= (Y1,Y2), A = 584_Find out the joint distribution.png? Find also the marginal distributions of Y1 and Y2. ?

Solution:

The joint pdf of X is

fx(x) = 1/a2, (x1,x2)? R(x)

= 0 otherwise.

Where

R(x) = {(x1,x2):0 ≤ x1 ≤ a, 0 ≤  x2 ≤ a}

The Jacobian of the transformation is

347_Find out the joint distribution1.png

Hence the pdf of Y is

fy(y) = 1/2a2, (y1,y2)? R(y)

= 0 otherwise.

where R ( y ) is the transformed region R ( x ) under the transformation Y = XA. The range of variation of Yl is clearly [ 0,2a ] and that of Y2 is [ - a, + a ]. However Yl and Y2 are not independent.

Since the inverse transformation is

X1= ½ (Y1 + Y2), X2 = ½ (Y1 - Y2) and 0≤ x1, x2 ≤ a,

the region R ( y ) is given by

R(y) = {( Y1 + Y2) : 0 ≤ Y1 + Y2 ≤ 2a, 0≤ Y1 - Y2 ≤2a},

The Relation between R ( x ) and R ( y ) is illustrated in Figure 2.

1951_Find out the joint distribution2.png

Figure: Relation between R ( x ) and R ( y ).

Note that the variables xl and x2 are independent and the region R ( x ) is such that for Xl - xl, the variation X2 does not depend on xl, but the region R ( Y ) is not of that type and the transformed variables Yl and Y2 are not independent.

The variable Yl varies in the interval [ 0, 2a]and for a fixed yl, if 0≤ y1≤ a, then y2 takes on values -y1≤y2≤ y1, while, if a< y1≤ 2a then y2 varies in the interval

-(2a-y1) <.y2 ≤ (2a - y1)

Integrating fy ( y ) with respect to y2, the marginal pdf of y2 is obtained as follows

fY1(y1) = 2283_Find out the joint distribution3.png 1/2a2 dy2 = y1/a2, for 0 ≤ y1 ≤ a

462_Find out the joint distribution4.png 1/2a2 dy2  = 2a-y1/a2, for a< y1 ≤ 2a

= 0 otherwise.

In a similar manner, we note that for a given Y2, if -a ≤ y2 ≤ 0 then

-y2 ≤ y1 ≤ 2a-y2, and if 0≤ y2 ≤ a then y2 ≤ y1 ≤ 2a - y2

Hence,

fY2(y2) = 119_Find out the joint distribution5.png1/2a2 dy1 = a+y2/a2, -a ≤ y2 ≤ 0

960_Find out the joint distribution6.png 1/2a2 dy1 = a-y2/a2 , 0< y2 ≤ a

= 0 otherwise.

Remarks:

The forms of pdf the marginal distributions In Example 5 are shown in Figure 3. Due to their triangular shape of pdf's, the distributions are called triangular distributions.

2222_Find out the joint distribution7.png

 

Figure: The forms of the marginal distributions of YI and Y2


Related Discussions:- Find out the joint distribution

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Steel structure, what do mean by outstand element of compression flange, in...

what do mean by outstand element of compression flange, internal element of compression flange and web general

Concrete, what are the appropriate methods of concreting

what are the appropriate methods of concreting

Explain the well drawdown equations - ground water, Explain the Well Drawdo...

Explain the Well Drawdown Equations Watch the units, especially if you use log 10 or ln.    h 1 = aquifer thickness minus the drawdown (ft)  r 1 = distance from well (ft

Calculate the cost to finance the construction project, A contractor is bid...

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of

Movement accommodation factor for joint sealant, Movement accommodation fac...

Movement accommodation factor is normally specified by manufacturers of joint sealants for designers to design dimension of joints. It is stated as the total movement that a joint

What is the meaning of untensioned reinforcement, Supplementary or Untensi...

Supplementary or Untensioned Reinforcement It is that reinforcement, provided in prestressed concrete member, which is not provided in a stretched condition like tendons.

Calculate the energy loss in the piping system, The head (energy) loss in t...

The head (energy) loss in the piping system between points 1 and 7 is the most nearly. Solution: 3 ft. The difference between point 1 and point 7 = 10 ƒt - 7 ƒt = 3 ƒt

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd