Feedback - advantages of statistical process control, Operation Management

Assignment Help:

Feedback - Advantages of Statistical Process Control 

SPC is a clear example of negative-feedback system control, providing management with timely information on the state of the process, allowing corrective action to be taken if required. Equally, SPC indicates when a process should be left to run, thereby saving on unnecessary adjustments to the process and, perhaps, avoiding non- conformance which could result from such adjustments. The following simple example may help to make the latter point clear. Consider a process with a target output value of 10.0 which, when running in a stable manner, has an inherent variability (see common cause variability, later) such that 50 per cent of the output is at the mean output value, 25 per cent measures 0.1 below, and the balance of 25 per cent measures 0.1 above the mean output value. Assume that the initial process setting is such that the mean output value matches the target value of 10.0. Twelve consecutive measurements might produce the following results (see table). Note that none of the measured values are outwith the expected range: with SPC, no adjustment of the process would be recommended.

53_Feedback - Advantages of Statistical Process Control.png

Now consider the same situation in the absence of SPC. The operator can adjust the process setting but cannot directly determine its mean value: he can only measure individual instances of the output, which, as we have seen, may differ from the mean as a result of the inherent variability of the process. Suppose, now, that the operator measures each output, calculates the deviation from the target value and adjusts the output by that amount. In the next table, the first output value (10.1) is above the target value (10.0) by 0.1. He adjusts the process setting to reduce the output value by this amount but, unknown to him, the process setting is now 9.9. As a result, the second output value is 9.8, not 9.9 (as it was in the previous table). The deviation is now 0.2 below target. The operator adjusts the process to increase the output by 0.2, taking the mean setting from 9.9 to 10.1, and so on.

1528_Feedback - Advantages of Statistical Process Control 1.png

Notice the effect: under SPC, as shown in the first table, six of the values would be at the target value and the others would range between 0.1 above to 0.1 below target. In the absence of SPC, as shown in the second table, only two of the values are on target and the others range from 0.1 above to 0.2 below target. The process adjustments have increased the variability of the output.


Related Discussions:- Feedback - advantages of statistical process control

Explain what is the evpi, State of nature decision ...

State of nature decision S1 S2 S3 D1 250 750 500 D2 300 -250

Explain what type of transmission path, What type of transmission path does...

What type of transmission path does a fixed wireless signal require? a. line-of-sight b. non-line-of-sight c. omni-directional d. code divided

What the cafeteria should use, A cafeteria wants to introduce a new burger,...

A cafeteria wants to introduce a new burger, with bread and beef together weighing at least 1 ounce. The cafeteria manage also wants the new burger to meet a new nutrition standard

Explain a linear trend line for expected freight car, Freight car loadings ...

Freight car loadings over a 12-year period at a busy port are as follows: Week Number Week Number Week Number 1 220 7 350 13 488 2 245 8 360 14 475 3 274 9 440 15 499 4 275 10 380

Explain the employer-sponsored sales process, Describe the employer-sponsor...

Describe the employer-sponsored sales process? What is the goal of this process once it is completed? Why is accreditation important?

Explain what are the minimum and maximum cycle times, An assembly line with...

An assembly line with 17 tasks is to be balanced. The longest task is 2.1 minutes, and the total time for all tasks is 23 minutes. The line will operate for 480 minutes per day. a.

Assume the length of critical path in a project, Suppose the length of crit...

Suppose the length of critical path in a project is 40 days and the standard deviation is 2 days. What due date should be set for the project so that the probability of completing

Describe traffic accidents requiring medical assistance, It has been observ...

It has been observed that the average number of traffic accidents requiring medical assistance in Santa Clara between 7 and 8 AM on Wednesday mornings is 1. What, then, is the chan

Answer the this question as I found on the google search, Ask questioAn ups...

Ask questioAn upscale home fixture supplier has four locations. Each location manages its ordering independently. The specialized lighting fixture sells for $300 and sales are on a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd