Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Fixed position based layout, Fixed Position Based Layout As the term its...

Fixed Position Based Layout As the term itself implies, fixed layout involves the movement of men and machines to the product which remains stationary. In this type of layout th

Define and illustrtae the term maintenance strategy, Problem: (a) Def...

Problem: (a) Define and illustrtae the term Maintenance Strategy? Support your answers with relevant examples. (b) Describe the steps that will be taken to improve the

Give an example of critical path by activity and duration, Give an example ...

Give an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Preceded by

What is buffering in risk management, What is Buffering in risk management?...

What is Buffering in risk management? Buffering: Buffering or slack is the allowance of additional cost, resources or time for example ‘just in case’ specific events or r

Earned value management is a systematic approach, Question: (a) Earned...

Question: (a) Earned Value Management is a systematic approach to the integration and measurement of cost, schedule, and technical accomplishments in a project. List the benef

Management skills required for a successful manager, How are the management...

How are the management skills required for a successful manager? Management Skills: The skills needed of a successful manager, while he is working into a industry,

Caselet, what are the objective of the project alignment session program?

what are the objective of the project alignment session program?

How is inventory control worked for an optimum balance, How is Inventory co...

How is Inventory control worked for an optimum balance between competing objectives? Inventory control is related with achieving an optimum balance in between two competing obj

Continuous improvement (Individual Assignment), I and my friend would like ...

I and my friend would like to make assignment of PPMP20009 (project management methodology) of master of project management

Discuss the importance of proper design for a hospitality, Question 1: ...

Question 1: Discuss the importance of proper design for a hospitality unit of your choice. Support your answer with relevant examples from the appropriate industry. Q

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd