Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Explain the new performance management system, Question 1: (a) How does...

Question 1: (a) How does Training differ from Development? (b) Elaborate on the different training methods, highlighting their relative advantages and disadvantages. Ques

Business negotiation, Tony Taxpayer''s return case study. Question is to ap...

Tony Taxpayer''s return case study. Question is to apply general attribution theory to analyze and explain each parties attitude and conclusions.

Describe the concept of ethics at the workplace, Question 1: (a) There ...

Question 1: (a) There are clear messages given to managers as far as how should rewards be. Elaborate on these messages. (b) Illustrating your answer with relevant examples,

Woody, woody Develop a list of "Key Success Indicators" that could and shou...

woody Develop a list of "Key Success Indicators" that could and should have been measured on completion. Rank them in order of priority for this project.

Risk management plan , Creating a Risk Management Plan  The main aim of...

Creating a Risk Management Plan  The main aim of risk management is to develop a well-structured approach to deal with any kind of uncertainty, which create threats in the proj

Disadvantages of product layout - high overhead charges, Disadvantages of P...

Disadvantages of Product Layout - High Overhead charges Due to heavy investment, the overhead fixed charges also tend to be high. A decline in demand for the product will rend

What types of problems solved by break even analysis helps, What types of p...

What types of problems solved by Break even Analysis Helps? Break even Analysis helps to solving the given types of problems as given below: 1. What volume of sales will be

Framework for organisational culture, According to Schein (2004),culture is...

According to Schein (2004),culture is essentially an established pattern of behavior built on shared basic assumptions generated by tackling crucial external adaptions and internal

Design changes during production, Even when the design has been released...

Even when the design has been released for production it cannot be considered to be absolutely final requiring no further changes. Certain problems may be faced during produ

What are its core features of mpmm, MPMM is a body of project management co...

MPMM is a body of project management content, wrapped in an easy, simple to use software tool. This tool contains such core features as a Navigation Panel, Display Panel, Page Summ

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd