Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Develop a integrated management project, You are not expected to submit a f...

You are not expected to submit a formal proposal. However, you will be able to access Subject Tutors via HenleyConnect and you may seek feedback from them as to the suitability and

Article delivery over network information system, Article Delivery Over Net...

Article Delivery Over Network Information System (ADONIS): ADONIS is a consortium of biomedical journal publishers that supplies full-text journals on CD-ROM for document deli

Second elaboration iteration, Perform a status assessment of the second Ela...

Perform a status assessment of the second Elaboration iteration. DO NOT GENERALISE. Assess each activity separately against the outcomes specified for the activity. Generate a deta

System layout planning activity relationship chart , System Layout Planning...

System Layout Planning Activity Relationship Chart Systematic layout planning (SLP) method is used in some production systems such as service systems, where the amount of mate

System engineering and deployment of Envirobat, i need a 5000 words report,...

i need a 5000 words report, i have already submitted a project plan from a material. i want report from already available material and some portion from yours as well.

Project management faces a lot of risks, QUESTION a) Major project mana...

QUESTION a) Major project management activities have their operational specificities. List the distinguishing characteristics of a project? b) Project management faces a lot

Arena model, The Arena model has been designed to simulate the workflow of ...

The Arena model has been designed to simulate the workflow of the emergency room as accurately as possible. It has one top-level model and two sub-models. Create Models In

Determine the progress and control status of the project, i) Explain the p...

i) Explain the project management control technique called earned value analysis and illustrate the fundamental concepts. Justify your answer. ii) Determine the progress and

Software project, Scenario: You are a member of the Project Review team for...

Scenario: You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd