Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Determine the best practices apply to project implementation, The objective...

The objectives of assignment are to determine what best practices apply to project implementation and close out, and to apply your individual knowledge of the quantitative topics t

Article delivery over network information system, Article Delivery Over Net...

Article Delivery Over Network Information System (ADONIS): ADONIS is a consortium of biomedical journal publishers that supplies full-text journals on CD-ROM for document deli

Risk process , Risk Process  An organisation faces many risk related is...

Risk Process  An organisation faces many risk related issues. To mitigate those risks we have risk management techniques. These steps assist an organisation to mitigate risk an

What is a trade-off in the context of a project?, Question: a) ‘Changes...

Question: a) ‘Changes in the competitive environment in which majority of organisations operate has necessitated a major rethink of the ways in which projects are managed'(Harv

Scope of materials management, Scope  of Materials  Management Material...

Scope  of Materials  Management Materials  management  embraces all  functions  concerning  planning  purchasing  production  control  stores  traffic and physical distribution

Design of an accounting system, Discuss the considerations that management ...

Discuss the considerations that management should take into account in determining the design of an accounting system which will satisfy both (i) its own information requirement

What is the use of gantt charts as a tool, What is the use of Gantt Charts ...

What is the use of Gantt Charts as a tool? The use of Gantt Charts as a tool: This tool can be used to plan time scale for a project This tool can be used to approxima

Areas of business excellence, A reas of Business Excellence Typically,...

A reas of Business Excellence Typically, we think about business excellence in the terms of superiority, but in practice, it is frequently translated into features of the busi

Illustrate the product life cycle, Q. Illustrate the Product life cycle? ...

Q. Illustrate the Product life cycle? Every food product passes through different phases throughout its life and therefore, the need for development of a new product arises. Ea

What are the techniques used for a post completion review, What are the tec...

What are the techniques used for a post completion review? Techniques used for a PC (post completion) review: a. End user satisfaction surveys regarding to the quality of th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd