Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Project management process, Project management Process According to PMB...

Project management Process According to PMBoK, project management is the application of knowledge, skills, tools and techniques to project activities in order to meet or exceed

Determine what are the delphi technique, The Delphi technique intends to at...

The Delphi technique intends to attain a consensus evaluates by the efforts of a number of estimators. How is this attained and what is the advantage of the Delphi technique over,

Why flf should undertake competitor analysis, FLF is a courier company base...

FLF is a courier company based in Z Country which presents direct document and parcel express delivery services for commercial customers. It prides itself not only on its reliabili

Phases of a project life cycle, Question: (a) A project manager must ta...

Question: (a) A project manager must take ownership of the project at its early stage through the following tasks namely: stakeholder identification and analysis, prepare a bus

Industrial management technique, Thus by the term quality control we mea...

Thus by the term quality control we mean the process of control where the management tries to conform the quality of the product in accordance with the pre determined stand

Continuous improvement - total quality management, Do it Right First Tim...

Do it Right First Time : TQM adopt the policy of zero defect. There is no scope for rework and rejection. The right first time or zero defect is the result of an empha

Project organisational structures, Organisational Structures The projec...

Organisational Structures The project organisational structure facilitates coordination and implementation of project activities. It should be designed to include the essential

Management, Ask question #MinimumIn its first year, “ABC Co” had the follow...

Ask question #MinimumIn its first year, “ABC Co” had the following experience Sales = 50,000 units Selling price = br. 50 TVC = br. 1,000,000 TFC = br. 250,000 Required: A. Devel

Example for the need to globalize it management, Question: a) With the...

Question: a) With the help of a diagram classify the different global project methodologies (ITIL, CoBIT, Prince 2, BS 17799, COSO,....) that you are aware of in terms of deve

Determine the analogy method of estimating, The analogy method of estimatin...

The analogy method of estimating is frequently used to produce broad-brush evaluates at the start of a project. Why this method is mainly suited to such application? Determinin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd