Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

How to measures defect ratios for the product, Defects found after product ...

Defects found after product delivery per function point Defects found after product delivery per LOC Pre-delivery defects: yearly post-delivery defects Defects per functio

Whole healing system and modality, 1)  Compare your chosen Whole Healing Sy...

1)  Compare your chosen Whole Healing System and Modality by considering: a)  When and by who were they 'invented'? b)  How have the therapies changed over time? c)  What

Balancing efficiency, Balancing Efficiency An efficient line balancing...

Balancing Efficiency An efficient line balancing will minimize the amount of idle time.  The balance efficiency can be calculated as Eff B = output of task time / in

Tools for collecting data, T ools for collecting data Improper or inco...

T ools for collecting data Improper or incomplete collection of data is a fundamental error which has an effect on all the subsequent actions. Data may be collected at the tim

Production control system, Question 1: What is understand by a producti...

Question 1: What is understand by a production control system and how are the elements of control systems categorized? Description of production control system Catego

Skills helpful in project and programm support office, What skills are help...

What skills are helpful when working in Project and Programme support office? The skills which are most helpful probably include in Project and Programme support office: a.

Line balancing methods, Line Balancing Methods  The various line balan...

Line Balancing Methods  The various line balancing methods or techniques used are: Heuristic Methods Linear Programming Kilbride and waste Methods

Address the issue of time, J Company is a retailer of fashion goods operati...

J Company is a retailer of fashion goods operating in a highly competitive market place. The Board of the company has given the go-ahead to redesign the company's website to make i

Draw a control chart for the number of defects, Explain the concepts involv...

Explain the concepts involved in Product Layout and its advantages and disadvantages vis-a-vis process layout. 18 carpets were observed closely and the number of defects in thei

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd