Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

What are the advantage of bottom-up decentralised approaches, What are the ...

What are the advantages of bottom-up decentralised approaches? Project budgets can be imposed by using bottom-up that is decentralised approaches for example project manager or

Different stages in the negotiation process, In the face of rising costs, t...

In the face of rising costs, the senior management in PT Company has decided that significant cuts will be needed in the budgets of some of its departments. The promotional budget

Areas of key risk in project management, Areas of key risk in Project Manag...

Areas of key risk in Project Management Companies believe that the most critical risk they face is market or competitive risk. There are various other risks faced by organisati

Rules-planning function, Rules Rules are prescriptions for how members ...

Rules Rules are prescriptions for how members of a group ought to or not to behave. They are specific and allow no discretion. In any group situation, and more so in the formal

What are the advantages of top-down centralised approaches, What are the ad...

What are the advantages of top-down centralised approaches? The advantages top-down centralised approaches Project budgets can be imposed by using top-down that is centralis

How to measures customer satisfaction for the product, Quality ultimately i...

Quality ultimately is calculated in terms of customer satisfaction.) Surveyed before product delivery and after product delivery (and on-going on a periodic basis, using standar

Explain the sources of power of a project manager, Question 1: (a) Powe...

Question 1: (a) Power is one of the most important human variables in the project management process as it sets the framework for directing and influencing human resources. Exp

Cobit, compare cobit 4.1 with cobit 5

compare cobit 4.1 with cobit 5

Uses and benefits of risk breakdown structure, Uses and Benefits of RBS  ...

Uses and Benefits of RBS  The main uses and benefits of the RBS are outlined in this section.  Risk identification aid  Risk Breakdown Structure is used as a list that

Degree of vertical integration, Degree of Vertical Integration Vertical ...

Degree of Vertical Integration Vertical integration is the amount of production and distribution chain, from suppliers of raw materials and components to the delivery of finishe

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd