Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Give an example of critical path by activity and duration, Give an example ...

Give an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Preceded by

Explain the event and the ideal target group, Question 1: a) As an eve...

Question 1: a) As an event organiser you need to target the right audience/visitor group. Taking a festival [local, regional or national] - explain the event and the ideal t

Use of both innovative approach in development process, Q. Use of both inno...

Q. Use of both innovative approach in development process? There are many major aspects that will sway the future trends in the development of new products. In the new millenn

Evaluating the design models, o Is the design understandable? o Is the desi...

o Is the design understandable? o Is the design of appropriate complexity for the task undertaken and the skill of the developer? o Is the design consistent? o Is the design mainta

Define product mix, Problem Define Product mix. Explain the factors det...

Problem Define Product mix. Explain the factors determine the decisions of the Product mix. Factors: Expansion of Product mix Contraction of Product mix Alteration

Production development flow diagram, The followings is a list of some of ...

The followings is a list of some of the common pitfalls to avoid if an organization is considering implementing quality by design: 1. Team members should be assigned to

Quality and cycle time in projects, Quality and Cycle Time in Projects ...

Quality and Cycle Time in Projects The cycle time is a very important outcome variable because the projects are usually carried out under the strict delivery schedules. The cyc

Procedure for registration of iso, ISO is located in Geneva, Switzerland....

ISO is located in Geneva, Switzerland. Each nation has its own national Standard Organization ( NSO) which is affiliated to the ISO. The system and procedures are laid down

Assessing Infrastructure Project-Related Risks, The Three Gorges Dam is pot...

The Three Gorges Dam is potentially one of the largest, if not the largest infrastructure projects completed in the 21st century. Clearly, there were a number of key risks that the

Explain the flexibility plans, Question 1: In order to meet the constan...

Question 1: In order to meet the constant changing requirements of the modern business world, organisations are compelled to develop flexibility plans. (a) Explain the vario

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd