Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Group technology or cellular manufacturing (cm) layout, Group Technology or...

Group Technology or Cellular Manufacturing (CM) Layout In group Technology /Cellular Manufacturing ( C M ) Machines are grouped into cells and the cells function somewhat like

Program planning , Program planning  An effective and disciplined plann...

Program planning  An effective and disciplined planning of a project is directly related to customer satisfaction. Since customer expectations always include timely delivery as

Process of development, Q. Process of development? Figure shows the pro...

Q. Process of development? Figure shows the process of new product development in the form of a flow chart. As is evident, the process of development starts with the idea gene

Mil standards, MIL standards were introduced in 1974. In 1975 BSI 517...

MIL standards were introduced in 1974. In 1975 BSI 5179 in these parts drawn from the contents of defiance standards 05-21 series. This standard was not written in man

System engineering and deployment of Envirobat, i need a 5000 words report,...

i need a 5000 words report, i have already submitted a project plan from a material. i want report from already available material and some portion from yours as well.

Degree of customer contact, Degree of Customer Contact The extent to w...

Degree of Customer Contact The extent to which customers get involved in the production system has important implications for the design of production processes. In custom bui

What type of symbols used to create a network diagram, What type of symbols...

What type of symbols used to create a network diagram? Symbols used to create a network diagram are as illustrated: An arrow is utilized to represent each activity or even

Operating characteristic curve, O perating characteristic curve The op...

O perating characteristic curve The operating characteristic curve for a sampling plan quantifies the risks. The OC curve for an attribute plan is a graph of the percentage de

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd