Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

The purpose of project management, QUESTION a) The purpose of project m...

QUESTION a) The purpose of project management is to achieve successful project completion with the resources available. Regardless of the method that is used to handle a projec

Critical analysis, Need to get critical analysis of the Document, Project M...

Need to get critical analysis of the Document, Project Management Body of Knowledge 1996 by the Standard committee of the PMI 8 pages. how much would this cost?

Advantage of in-house project management service, Question: Using the e...

Question: Using the example of Back~to~Future International, a newly setup organization and taking advantage of in-house project management service as set out in Question (

Describe quality control, Question 1 There cannot be a single ideal str...

Question 1 There cannot be a single ideal structure for all organisations as different organisations have different size, environment, resources, technologies, and goals. There

Steps to create run chart, The steps to create a run chart are: 1.   Id...

The steps to create a run chart are: 1.   Identify the process to be observed: Ensure that the process involves some kind of repeatable activity in which results remain consis

Skills helpful in project and programm support office, What skills are help...

What skills are helpful when working in Project and Programme support office? The skills which are most helpful probably include in Project and Programme support office: a.

What does positive and negative npv indicate, Net Present Value (NPV) analy...

Net Present Value (NPV) analysis is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflow and outflow to the

Relationship between project manager and project team, Project manager and ...

Project manager and project team The project board will ultimately choose whether changes are executed or not and it will then be the responsibility of the project manager to m

Empowering the staff - element of tqm, Empowering the staff assists to acco...

Empowering the staff assists to accomplish optimal business results through team work. Empowerment occurs when employees are adequately trained, provided with all relevant inf

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd