Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Advantages of fms, Advantages of FMS Flexible manufacturing system...

Advantages of FMS Flexible manufacturing systems are regarded as one of the most efficient methods to employ in reducing or eliminating problems in manufacturing industrie

Computerized relative allocation of facilities technique, Computerized Rela...

Computerized Relative Allocation of Facilities Technique (CRAFT): The previous difficulty can now be alleviated because of the availability of computer software packages like

What is buffering in risk management, What is Buffering in risk management?...

What is Buffering in risk management? Buffering: Buffering or slack is the allowance of additional cost, resources or time for example ‘just in case’ specific events or r

Project risk custodians , Project risk custodians  The quality risk fun...

Project risk custodians  The quality risk function is carried out by the project risk custodians. The responsibility of project risk custodians is to:    Integrate all po

Global Project Management, You have been hired as the Senior Global Project...

You have been hired as the Senior Global Project Manager by the Timm Coconut Transnational Motor Corporation to manage their newly created Project Management Office. You are in c

Give an example of critical path by activity and duration, Give an example ...

Give an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Preceded by

Swot analysis, SWOT Analysis is constituted with strengths, weaknesses, opp...

SWOT Analysis is constituted with strengths, weaknesses, opportunities and threats. It is the analysis that to identify the internal and external factors relate to the organization

If i am empowered, Q. If I am empowered, why do I need project management? ...

Q. If I am empowered, why do I need project management? A. If you have been authorize it probably or must mean that you have been given the authority and responsibility to un

Areas of key risk in project management, Areas of key risk in Project Manag...

Areas of key risk in Project Management Companies believe that the most critical risk they face is market or competitive risk. There are various other risks faced by organisati

Internal factors of syringe management , Internal Factors Strengths ...

Internal Factors Strengths Strengths of the Syringe management plan are to increase people's manner to use the syringe. Secondly it would reduce the injury of needle ar

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd