Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Define the revolution of changing in information technology, Define the rev...

Define the revolution of changing in information technology. Conversely, revolution of changing in the field of information technology has posed some of challenges for various

Challenges in quality management, Question 1: Describe - Expected Quali...

Question 1: Describe - Expected Quality, Design Quality and Actual Quality and how they influence the customer satisfaction. A Defining Expected Quality, Design Quality a

What is the rationale behind the concept of earned value, Question: (a)...

Question: (a) What are the checks/actions to be carried out in a project monitoring meeting? (b) What is the rationale behind the concept of "earned value" in project moni

Production and purchasing management, A) Hierarchical planning in Operation...

A) Hierarchical planning in Operations/Production management and types of time frames in each hierarchy. (B) Explain who role players are in each level and what they are respons

JJ Electronics Product Development Case, i need an assignment to be done by...

i need an assignment to be done by microsoft project 2010 . it should contain all details like critical path,and gantt chart etc in .mpp .

Project risk custodians , Project risk custodians  The quality risk fun...

Project risk custodians  The quality risk function is carried out by the project risk custodians. The responsibility of project risk custodians is to:    Integrate all po

What is the estimated cost of the whole project, Question 1: (a) Using...

Question 1: (a) Using information from Table 1, build a network diagram for the project. (b) Perform a Forward Pass on the network diagram and deduce the duration of the p

Linear programming methods of line balancing, Linear Programming Methods of...

Linear Programming Methods of Line Balancing Assume that a job is broken down into elements tasks and the total duration of all such tasks is 28 minutes. The cycle time i, e,

Project cost accounting, P o w e rful cost reduction The project co...

P o w e rful cost reduction The project cost accounting will track the quality-related costs which can be an important management tool. For example, suppose there are some

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd