Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Production control system, Question 1: What is understand by a producti...

Question 1: What is understand by a production control system and how are the elements of control systems categorized? Description of production control system Catego

Write short notes on earned value method, 1 Write short notes on Earned Val...

1 Write short notes on Earned Value Method (EVM) 2 What are the common features available in PM software packages? 3 A project should earn sufficient return on the investment

What are the steps in organisation design, What are the steps in organisati...

What are the steps in organisation design? Steps comprised in Organisation Design are as illustrated below: a. Understand and formulate the goals and things of the organisat

Project approches, Describe your approach to tracking a project?

Describe your approach to tracking a project?

Need for safety, Need for safety 1. Cost Saving: Two type  of costs ...

Need for safety 1. Cost Saving: Two type  of costs  are incurred by the management  when an accident  occurs. There are the  direct  costs in the  form  of compensation paya

Worker engagement, what is worker engagement? What are worker engagement a...

what is worker engagement? What are worker engagement approaches?

Define the revolution of changing in information technology, Define the rev...

Define the revolution of changing in information technology. Conversely, revolution of changing in the field of information technology has posed some of challenges for various

Unit rate contracts , Unit rate contracts  In a unit-rate contract, the...

Unit rate contracts  In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item. Engineered m

Virtual museum project, Building design - You can select any building to ho...

Building design - You can select any building to house your museum.  It may be a historical building that we study (i.e. the Pantheon), it may be a current museum anywhere in the w

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd