Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Process of diagnosing the system, Question 1: What are the steps involv...

Question 1: What are the steps involved in the process of diagnosing the system? Steps involved in the process of diagnosing the system. Question 2: What are the maj

Design changes during production, Even when the design has been released...

Even when the design has been released for production it cannot be considered to be absolutely final requiring no further changes. Certain problems may be faced during produ

Factor affecting process planning - choice of plant layout, Factor Affectin...

Factor Affecting Process Planning - Choice of Plant Layout While deciding the sequence of operations the plant layout is to be taken into consideration. The sequence of operat

Objectives of a work breakdown structure, Question: (a) Explain the typ...

Question: (a) Explain the typical contents of the project selection rationale document, drafted at the end of the conception phase. (b) (i) Describe the purpose and objecti

Explain about privatisation of public sector undertakings, Explain about th...

Explain about the privatisation of public sector undertakings. The privatisation of public sector undertakings : After independence India opted for mixed economy. The priv

Housekeeping, what is the thumb rule to calculate the housekeeping manpower...

what is the thumb rule to calculate the housekeeping manpower requirement in office

Explain about the work breakdown structure, Explain about the work breakdow...

Explain about the work breakdown structure. Work breakdown structure (WBS): The concept of work breakdown structure (WBS) is to assist plan effectively for a project by b

Project organisation structure, P roject organisation In this type of ...

P roject organisation In this type of organisation, the project management needs of all divisions of the company are served by a centralized separate division of skilled manag

Brown &b hyer, Chapter 6 presents several tools that can be useful when ass...

Chapter 6 presents several tools that can be useful when assessing for project uncertainties. Compare and contrast risk mapping, FMEA, and the gut-feeling method. Which method do y

What is the primary objective of controlling, What is the primary objective...

What is the primary objective of controlling? The main objective of controlling is to bring the actual operational performance of enterprise onto the accurate track according t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd