Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Describe problems with functional project coordination, Question 1: "Ma...

Question 1: "Matrix structures are becoming more common and are likely to continue to do so in the future" (Field and Keller, 1998). a) Describe likely problems with functio

Quantitative layout analysis - correlation chart, Quantitative Layout Analy...

Quantitative Layout Analysis - Correlation Chart  In this technique we draw a gird with rows presenting alternative solutions. Plant item can be a ground floor (G >F) First fl

Describe who should carry out an investigation, Question: (a) An emplo...

Question: (a) An employee in an organisation has suffered a major injury in an accident during working hours. Describe who should carry out an investigation into the accident

"simultaneous loose?tight" by Peters, Discuss the concept of "simultaneous ...

Discuss the concept of "simultaneous loose?tight" by Peters and Waterman

Production and purchasing management, A) Hierarchical planning in Operation...

A) Hierarchical planning in Operations/Production management and types of time frames in each hierarchy. (B) Explain who role players are in each level and what they are respons

Eassy, Written Assessment Assessment Title Essay Task Description Task ...

Written Assessment Assessment Title Essay Task Description Task Your task is to consider the contents of:- SEBoK Kerzner">http://www.sebokwiki.org Kerzner (2013) AS/NZS 1

Assignment 2 intro to project manage, Assignment #2 . Assignment #2 Yo...

Assignment #2 . Assignment #2 You will need to first develop a customer''s Request for Proposal (RFP), then go to the simplified Project Proposal on pages 76-78 of your text a

Kilbridge and wester method of line balancing, Kilbridge and Wester Method ...

Kilbridge and Wester Method of line Balancing Kilbridge and Wester propose this method. Here numbers are assigned to each operations describing how many predecessors it has.

What work goes on previous to project start-up, What work goes on previous ...

What work goes on previous to project start-up? Before project start-up, work is required to establish the things and scope of the project. This is essential to establish the d

IT Project Management Task #1, IT Project Management Task #1, I need help w...

IT Project Management Task #1, I need help with my course.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd