Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Social media strategy - design, Part 1- Social Media Strategy Design For...

Part 1- Social Media Strategy Design For this phase of the project you are required to formulate a social media strategy for a product/service/business/concept/charity...etc. th

Project management structure, what are the segments involved in project man...

what are the segments involved in project management structure?

Privatisation of public sector included undertakings, What are included in ...

What are included in the privatisation of public sector undertakings? Privatisation of public sector undertakings: It is consisting of witnessed the trend toward opening

What does have in the project management software, What does have in the pr...

What does have in the project management software? Project management software: Project management software onto the market today comprises Lotus Notes / Domino or Micros

Problems associated with policies-planning function, Problems associated wi...

Problems associated with policies 1) Policies are liable to different interpretations since they allow discretion and are usually broad. If made specific they become rules and th

Components of participative management, COMPONENTS OF PARTICIPATIVE MANAGEM...

COMPONENTS OF PARTICIPATIVE MANAGEMENT: The involvement of staff in the decision making process of the organization and having increased awareness of the organization's purpos

What is the primary objective of controlling, What is the primary objective...

What is the primary objective of controlling? The main objective of controlling is to bring the actual operational performance of enterprise onto the accurate track according t

Quantitative layout analysis - correlation chart, Quantitative Layout Analy...

Quantitative Layout Analysis - Correlation Chart  In this technique we draw a gird with rows presenting alternative solutions. Plant item can be a ground floor (G >F) First fl

Tqm in manufacturing , Quality is actually built into the product durin...

Quality is actually built into the product during its manufacturing. The manufacturing of a product requires a host of activates involving different departments and sect

Aim and objective of syringe management plan, Aim The purpose of the Sy...

Aim The purpose of the Syringe management plan is to protect the social community against injury by syringe and help people manage syringe in proper manner. According to the re

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd