Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Traditional forms of organisation, T raditional forms of organisation ...

T raditional forms of organisation Traditional forms of organisations were classified into five types based on the following differentiations. Functional differentiati

Different between work and cost breakdown structure, What are the different...

What are the different between Work and Cost breakdown structure? Different between Work and Cost breakdown structure: Work breakdown structure produces a detailed list of e

How to measures customer satisfaction for the product, Quality ultimately i...

Quality ultimately is calculated in terms of customer satisfaction.) Surveyed before product delivery and after product delivery (and on-going on a periodic basis, using standar

Disadvantages of product layout - inflexibility, Disadvantages of Product L...

Disadvantages of Product Layout - Inflexibility Inflexibility is a drawback of this type of layout. The equipment laid out is designed to perform specific operations. No machi

Discuss the project management knowledge areas, Question: (a) Project ...

Question: (a) Project Integration Management refers to the integration of the nine knowledge areas and project phases involved in coordinating project activities to ensure th

Explain any two benefits of an erp implementation, Question 1 Differentiat...

Question 1 Differentiate between Commercial and Open Source ERPs software packages Question 2 For a successful MRP system three types of information are very essential. Descr

Shareholder value - measure for project management value, S hareholder val...

S hareholder value Project management initiative brings a renewed interest among the shareholders. The major investors show more interest by becoming active in the organisati

Framework for organisational culture, According to Schein (2004),culture is...

According to Schein (2004),culture is essentially an established pattern of behavior built on shared basic assumptions generated by tackling crucial external adaptions and internal

Line balancing., What do you understand by "line balancing"?

What do you understand by "line balancing"?

What do you mean by line balancing in management, What do you mean by Line ...

What do you mean by Line Balancing in management? Line Balancing: It means balancing the line among the product lines or assembly lines. This aims at grouping assists an

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd