Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Process control, All processes are subject to various influences such as ...

All processes are subject to various influences such as mechanical electrical and environmental changes which is tend to deviate the process from its initial setting. The

Essential pre-requisites of a grievance procedure, Problem 1: Show the ...

Problem 1: Show the essential pre-requisites of a grievance procedure. Essential pre-requisites of a grievance procedure Problem 2: What are the objectives of Trade

Processes and customer involvement, Processes and Customer Involvement ...

Processes and Customer Involvement Many processes are designed keeping in mind that value is provided by involving the customer in the delivery of the final product.  The invo

Line balancing., What do you understand by "line balancing"?

What do you understand by "line balancing"?

Communication-coordination beneficial in project management, How are commun...

How are communication and coordination beneficial in project management software? Communication and coordination: Project software can give automatic report templates al

Good project planning, Over the years, E has had a number of business succe...

Over the years, E has had a number of business successes in the building trade and property development. Her latest venture is to build a hotel in YX town. E has already gained the

Role and nature of estimation in project management, Question: (a) Th...

Question: (a) The Local Government Service Commission has advertised a post of "CLERK" on the L'Express newspaper on the April 1, 2004. The closing date for the submissio

Super Bowl, Do you have an assignment which has WBBS and project plan for p...

Do you have an assignment which has WBBS and project plan for planning of Super Bowl Half time planning?

What does positive and negative npv indicate, Net Present Value (NPV) analy...

Net Present Value (NPV) analysis is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflow and outflow to the

Benefits of having a clear mission for pv company, T has recently been appo...

T has recently been appointed as the new Chief Executive of PV Company which manufactures cosmetics and toiletries. She has spent the first three months meeting with her senior man

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd