Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Design a construction and operation of a school, You are to design a School...

You are to design a School.  You are to design the School to the requirements of the client, who will be informed by customer choices - these will be determined by market surveys c

Secondary stakeholders and major risks in WAM organisation, The WAM Organis...

The WAM Organisation is one of the very successful supermarket chains within its own country. Reputation for innovation of it is unparalleled into its own country along with the wi

Selection criteria and importance of selecting the product, Q. Selection Cr...

Q. Selection Criteria and importance of selecting the product? Biscuits are one of the most common bakery products eaten all over the world. They are the most easily available

How do i organize and apply resources, Q. How do I organize and apply resou...

Q. How do I organize and apply resources? A. The first moreover most important step in the implementation phase is to re-visit the project plan (or the project brief) and to

Describe reck and long''s purchasing development model, Describe Reck and L...

Describe Reck and Long's purchasing development model. Supply is now accepted as a more fundamental and strategic method when compared to purchasing. Twenty years ago Reck and

Work breakdown structure, I have a project that I would like to have a work...

I have a project that I would like to have a work breakdown structure developed for.

Kilbridge and wester method of line balancing, Kilbridge and Wester Method ...

Kilbridge and Wester Method of line Balancing Kilbridge and Wester propose this method. Here numbers are assigned to each operations describing how many predecessors it has.

Areas of business excellence, A reas of Business Excellence Typically,...

A reas of Business Excellence Typically, we think about business excellence in the terms of superiority, but in practice, it is frequently translated into features of the busi

Pareto charts, P areto charts It is a very helpful tool to identify th...

P areto charts It is a very helpful tool to identify the greatest opportunity for improvement among  various  possibilities  and  to  identify  the  small number  of  most inf

Redundancy in public sector organisations, Question: (i) What are the d...

Question: (i) What are the different measures taken by Government so far to address problems of redundancy in public sector organisations in Mauritius? (ii) What reasonable

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd