Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Design and implementation of the pms, Question: Performance appraisal (...

Question: Performance appraisal (PA) and management play an important role in the effective management of employees in every viable organisation. However, for many Human Resour

Develop and agree a process model for a project, Why is it significant that...

Why is it significant that the project team and the users develop and agree a process model for a project? Any project is a cooperative venture among the clients/users and the

MSc PM, Hi I would like to know if you assist on the dissertation or what s...

Hi I would like to know if you assist on the dissertation or what services you can provide. Thanks,

Network Security and Support, Choose a case study from the readings or use ...

Choose a case study from the readings or use your own workplace or organisation to discuss these questions. 1. What are the key elements of a sustainability statement? 2. What ar

Performance problem or challenge, • You also found that over the past 6 mon...

• You also found that over the past 6 months, the Senior Leadership had been very proactive in their attempt to drive a much different strategic vision and had communicated strong

Cost benefit analysis, How to determine which project have larger net benef...

How to determine which project have larger net benefit between two projects

What types of errors disclosed in trial balance, What types of errors discl...

What types of errors disclosed in Trial Balance? A Trial Balance discloses the given types of errors as illustrated follows: a. An item posted two times. b. A mistake int

Rules-planning function, Rules Rules are prescriptions for how members ...

Rules Rules are prescriptions for how members of a group ought to or not to behave. They are specific and allow no discretion. In any group situation, and more so in the formal

Tools and techniques of layout planning - line balancing, Tools and Techniq...

Tools and Techniques of layout planning - Line Balancing Line balancing is the phases of assembly line study that nearly equally divides the work to be done among the workers

Develop a integrated management project, You are not expected to submit a f...

You are not expected to submit a formal proposal. However, you will be able to access Subject Tutors via HenleyConnect and you may seek feedback from them as to the suitability and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd