Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

What are the disadvantages of bottom-up decentralised, What are the disadva...

What are the disadvantages of bottom-up decentralised approaches? Project budgets can be imposed by using bottom-up that is decentralised approaches for example project manager

Project management requires three important activities, Question (a) Pr...

Question (a) Project Management requires three important activities, namely planning, estimation and scheduling. Discuss the differences between them. (b) Scheduling of proj

Pareto charts, P areto charts It is a very helpful tool to identify th...

P areto charts It is a very helpful tool to identify the greatest opportunity for improvement among  various  possibilities  and  to  identify  the  small number  of  most inf

Preparation of manufacturing drawings, This is one of the most tedious a...

This is one of the most tedious and difficult phases of design yet quality literally depend upon the correctness and completeness of the manufacturing drawings and specifica

How could appraisals be made successful in organisations, Question: Per...

Question: Performance Appraisal "Is the process of evaluating the performance and qualifications of the employees in terms of the requirements of the job for which he is emp

Privatisation of public sector included undertakings, What are included in ...

What are included in the privatisation of public sector undertakings? Privatisation of public sector undertakings: It is consisting of witnessed the trend toward opening

Define incremental approach of system testing, Define the incremental appro...

Define the incremental approach by system testing. System test: In system testing, the developers are checking which the system gives the functionality described by the u

Internal factors of syringe management , Internal Factors Strengths ...

Internal Factors Strengths Strengths of the Syringe management plan are to increase people's manner to use the syringe. Secondly it would reduce the injury of needle ar

WBS and Network diagram, Network Diagram for my course project based upon t...

Network Diagram for my course project based upon the WBS. The Network Diagram should include the Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), Latest Finish (LF), a

Incremental approach to testing by integration test, Explain the incrementa...

Explain the incremental approach to testing represented by the orderly integration test. Integration test: The integration test is looking for to determine whether the mo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd