Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Marketing project, Step 1 Advise the instructor in writing if you will be w...

Step 1 Advise the instructor in writing if you will be working on the project individually or with another class member(s). Choose your team member (s),carefully, as you will have

Project risk manager , Project risk manager  As the project manager man...

Project risk manager  As the project manager manages the project, the project risk manager manages the project risks in the similar way. The responsibilities of project risk ma

Lack of specialized supervision, Lack of Specialized Supervision There...

Lack of Specialized Supervision There will be greater difficulty in securing specialized supervision. Because line layout consists of several machines requiring a wide range o

Explain the procedure of modi method, Q1.  Explain the procedure of MODI me...

Q1.  Explain the procedure of MODI method of finding solution through optimality test. Q2.  a. Explain the steps in Hungarian method. b. Solve the following assignment proble

Illustrate the product life cycle, Q. Illustrate the Product life cycle? ...

Q. Illustrate the Product life cycle? Every food product passes through different phases throughout its life and therefore, the need for development of a new product arises. Ea

Audits, A udits Audits are independent examinations to determine wheth...

A udits Audits are independent examinations to determine whether processes and procedures achieve the specified objective. They are an essential tool to identify problem areas

Can surprises be reduced, Q. Can surprises be reduced? Yes absolutely! ...

Q. Can surprises be reduced? Yes absolutely! By their vary nature projects are uncertain business and uncertainty can lead to both risk and opportunities. As a result a very im

Global Project Management, You have been hired as the Senior Global Project...

You have been hired as the Senior Global Project Manager by the Timm Coconut Transnational Motor Corporation to manage their newly created Project Management Office. You are in c

Usage of risk breakdown structure , Usage of RBS  Once an organisation ...

Usage of RBS  Once an organisation defines a Risk Breakdown Structure (RBS), then it can be used in a number of ways. These RBS is relevant across the project and helps in the

Disadvantages of fms, Disadvantages of FMS Limited ability t...

Disadvantages of FMS Limited ability to adapt to changes in product Substantial preplanning and capital Tooling and fixture requirements

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd