Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Scoping a project, QUESTION While scoping a project, as much informatio...

QUESTION While scoping a project, as much information as possible should be gathered about the wants and concerns of sponsors and end-users. What are the useful channels of

Explain the methodology of sequencing the activities, Question 1 For a...

Question 1 For an event manager, organizing an AGM would be a relatively 'dry' affair as the elements of entertainment, decoration and catering are missing in this event (some

Performance measurement - elements of tqm, Performance measurement: Pe...

Performance measurement: Performance measurement needs to be based upontimely measures of, and feedback on, performance. It provides information ontoday's service and gives an

What does have in the project management software, What does have in the pr...

What does have in the project management software? Project management software: Project management software onto the market today comprises Lotus Notes / Domino or Micros

Explain the features of the three organizational culture, QUESTION 1 ...

QUESTION 1 One way to classify team cultures is broadly to classify them as being closed cultures, partly-open cultures and fully open cultures. Explain the features of the t

Demonstration of work plan of national weather service, The National Weathe...

The National Weather Service The Scenario:The National Weather Service has recently faced downsizing due to a significantpersonnel shift in the Obama budget.  The White House budg

Benefits of quality, B enefits of quality The benefits of quality in p...

B enefits of quality The benefits of quality in project performance are: C ustomer satisfaction: is the result of a quality product or project. If customers requirem

What are the disadvantages of critical path analysis, What are the disadvan...

What are the disadvantages of critical path analysis? Disadvantages of critical path analysis (CPA): a. Supposes a trade off among time and money but most staff cost coul

Housekeeping, what is the thumb rule to calculate the housekeeping manpower...

what is the thumb rule to calculate the housekeeping manpower requirement in office

Factors affecting process design - nature of product, Factors affecting Pro...

Factors affecting Process Design - Nature of Product The operations management has to design the production systems to produce products/ service of the kind that customers wan

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd