Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

What is trial balance, What is Trial Balance? Trial Balance: Afte...

What is Trial Balance? Trial Balance: After posting each and every journal entries within the ledger, a statement termed as trial balance is prepared to check the accurac

How to measures defect ratios for the product, Defects found after product ...

Defects found after product delivery per function point Defects found after product delivery per LOC Pre-delivery defects: yearly post-delivery defects Defects per functio

Explain how effective teamwork is beneficial, Question: (a) Explain how...

Question: (a) Explain how effective teamwork is beneficial to both the individual and the organisation. (b) Team leaders have to be on the lookout for symptoms of ineffecti

International quality certification, The international organization for s...

The international organization for standardization ( ISO) is the specialized international agency for standardization and at present comprises the national bodies of 91 c

What if i need more money for my project, Q. What if I need more money? ...

Q. What if I need more money? The similar applies here as in Question 17. Though the options that are open will depend on how far the project has already advanced. In general t

System engineering and deployment of Envirobat, i need a 5000 words report,...

i need a 5000 words report, i have already submitted a project plan from a material. i want report from already available material and some portion from yours as well.

Computerized relative allocation of facilities technique, Computerized Rela...

Computerized Relative Allocation of Facilities Technique (CRAFT): The previous difficulty can now be alleviated because of the availability of computer software packages like

Give the definition of a team, Problem: (a) Give the definition of a te...

Problem: (a) Give the definition of a team and elaborate on the purpose of having teams in the organisation. (b) Describe the different processes that take place in a team a

Define the term scenario planning in risk management, Define the term Scena...

Define the term Scenario Planning in risk management. Scenario planning: It is about perceiving uncertainties for example identification of risks and the growth of pre-em

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd