Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Produce a management report of a company, There are two learning objectives...

There are two learning objectives of this assessment. 1. The first relates directly to the operations management materials presented in the lectures 4 and 5. This assessment wil

Determine the critical path by activities and duration, Determine the criti...

Determine the critical path by activities and duration. Activity          Duration (Wks)       Preceded by A                     5                               -

Need for safety, Need for safety 1. Cost Saving: Two type  of costs ...

Need for safety 1. Cost Saving: Two type  of costs  are incurred by the management  when an accident  occurs. There are the  direct  costs in the  form  of compensation paya

Different between work and cost breakdown structure, What are the different...

What are the different between Work and Cost breakdown structure? Different between Work and Cost breakdown structure: Work breakdown structure produces a detailed list of e

Line Balancing, What du you understand by line balancing

What du you understand by line balancing

Execution of the project, The researcher should see that the project is exe...

The researcher should see that the project is executed in a systematic manner and in time. If the survey is to be conducted by means of structured questionnaires data can be rea

Objectives of a procurement system, Question 1: (a) Enumerate five obje...

Question 1: (a) Enumerate five objectives of public procurement systems contained in the UNCITRAL Model Law on Procurement of Goods and Construction. (b) Compare and c

Process of development, Q. Process of development? Figure shows the pro...

Q. Process of development? Figure shows the process of new product development in the form of a flow chart. As is evident, the process of development starts with the idea gene

Determine the best practices apply to project implementation, The objective...

The objectives of assignment are to determine what best practices apply to project implementation and close out, and to apply your individual knowledge of the quantitative topics t

Elaboration iteration, Perform a status assessment of the first Elaboration...

Perform a status assessment of the first Elaboration iteration. DO NOT GENERALISE. Assess each activity separately and assess it against the outcomes specified for the activity. Ge

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd