Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Parameters of facilities planning and design, Question 1: Distinguish b...

Question 1: Distinguish between innovation and renovation within the parameters of facilities planning and design. Question 2: Although security and safety at the work

What are the disadvantages of division of labour, What are the Disadvantage...

What are the Disadvantages of Division of Labour? Disadvantages of Division of Labour are as follows: a. Division of labour provides rise to loss of craftsmanship, workers t

Span of management-managerial function of organizing, Span of management ...

Span of management Span of management refers to the number of subordinates who directly report to one superior. If a manager has too many subordinates then his span is wide and

Types of accident, Types of Accident  Accident   are of different  ty...

Types of Accident  Accident   are of different  types. They may be  classified as major  and minor  ones, depending  upon  the severity of the  injury. An accident which  end

Strategy for project implementation, A strategy for project implementation ...

A strategy for project implementation Projects involving  small number  of  activities,  resources,  constraints  and inter-relationship can be visualized easily by the human m

Responsibilities associated with policy requirements, R esponsibilities ...

R esponsibilities Following responsibilities are associated with policy requirements: P roject leaders Project leaders notify federal government departments or agenc

What do you meant by change of scope in a project, Question: (a) (i) Wh...

Question: (a) (i) What do you meant by "a change of scope" in a project? (ii) Unplanned changes (for e.g, unplanned expenses) might occur during the implementation phase of

What is memory virtualization, 1. Enterprises always seek to enhance the q...

1. Enterprises always seek to enhance the quality of service delivered to customers and end users. Justify. 2. Describe briefly the concept of capital budgeting for information

Management of utilities for a estate complex, Question 1: (i) What are...

Question 1: (i) What are the various aspects you would consider while planning to build a new international airport? (ii) With relevant arguments discuss the necessity or

Components of strategy, Components of Strategy Strategy has four basic ...

Components of Strategy Strategy has four basic components: Scope: which refers to the position the firm wants to have in relation to its environment. Resource deploym

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd