Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Address the issue of time, J Company is a retailer of fashion goods operati...

J Company is a retailer of fashion goods operating in a highly competitive market place. The Board of the company has given the go-ahead to redesign the company's website to make i

Define inventory procurement and inventory carrying cost, Define the invent...

Define the inventory procurement cost and inventory carrying cost. Inventory Procurement Cost and Inventory Carrying Cost: Inventory is a detailed list of such movable it

What are the distinguishing characteristics of a project, Question : (a...

Question : (a) What are the distinguishing characteristics of a project? (b) What are the four types of consequences of risk? (c) Explain what you understand by the term

Functional requirements for an exhibition management system, Question: ...

Question: (a) Consider the following quality goals and provide a way to make the goal more tangible such that it can be easily verified: ?Software should be user friendl

How to measures defect removal efficiency for the product, Number of post-r...

Number of post-release defects (found by clients in field operation), categorized by level of severity Ratio of defects found internally prior to release (by inspections and tes

Objectives of quality control, To assesses the quality of the raw materials...

To assesses the quality of the raw materials semi finished goods and finished products at various stages of production process. To see whether the product conforms to the predet

Illustrate the division of work in economics, Illustrate the division of wo...

Illustrate the division of work in Economics? Division of Work (or Labour): It s a famous principle of Economics, invented through the traditional economist as defined by

Benefits from quality efforts, Benefits from Quality Efforts The benefi...

Benefits from Quality Efforts The benefit obtained from quality is creation of more efficient and effective operations. It helps to increase the customer satisfaction and their

Line balancing methods, Line Balancing Methods  The various line balan...

Line Balancing Methods  The various line balancing methods or techniques used are: Heuristic Methods Linear Programming Kilbride and waste Methods

Management of change, Problem 1: a) ‘Project Management is closely link...

Problem 1: a) ‘Project Management is closely linked with the management of change' Explain why. b) Elaborate on two models of change. Explain the relevance, applicability

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd