Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Allocation of resources, Explain how resource allocation can impact an orga...

Explain how resource allocation can impact an organisation?

Areas of key risk in project management, Areas of key risk in Project Manag...

Areas of key risk in Project Management Companies believe that the most critical risk they face is market or competitive risk. There are various other risks faced by organisati

Cost analysis, After analyzing the three models, and comparing all three us...

After analyzing the three models, and comparing all three using a paired-t test, we found out that the results of the modifications to the base model were statistically significant

Benefits and caveats, (a) What are the benefits and caveats of adopting a ...

(a) What are the benefits and caveats of adopting a standard methodology (such as PRINCE2) for the management of an organization's projects? (b) How might the size of an organi

#title.Discountingw., what is the principle of discounting and what issues ...

what is the principle of discounting and what issues are critical in this process

Objectives of iso 9000, Objectives of ISO 9000 The basic objectives o...

Objectives of ISO 9000 The basic objectives of ISO 9000are : 1. To facilitate international trade of goods and services. 2. To obtain competitiveness by obtaining

Methods used to performance appraisal of workers, What are the methods used...

What are the methods used to performance appraisal of workers? The methods used within performance appraisal of workers are ranking method, Paired Comparison Technique, Forced

Define role of work breakdown structure in project software, Define the rol...

Define the role of work breakdown structure in project management software. Work breakdown structure in project management software: Project software can assist with coordin

The type of culture to which s company now needs to change, S Company has f...

S Company has for many years been a long standing household name, designing and manufacturing electrical appliances for use in the kitchen. It has developed a strong culture over t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd