Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

#beauty parlour, i want to know about the codes of a beauty parlour managem...

i want to know about the codes of a beauty parlour management website.

What do project managers do, Q.  What do project managers do? First of ...

Q.  What do project managers do? First of all project managers have to take responsibility for leading the project effort towards the stated and agreed upon goals and objective

Risk management , Introduction to Risk Management Let us begin with def...

Introduction to Risk Management Let us begin with defining Risk. Risk, is an integral part of the business scenario, and can be termed as a potential event that can have opport

Transaction cost theory could help the head of insurance, The Head of Insur...

The Head of Insurance at JKL Bank has been considering how to make efficiencies in the operation of the Car Insurance Business Unit. One option under consideration is to outsource

What is memory virtualization, 1. Enterprises always seek to enhance the q...

1. Enterprises always seek to enhance the quality of service delivered to customers and end users. Justify. 2. Describe briefly the concept of capital budgeting for information

Family planning research center of nigeria, 1. Some of the tasks in this pr...

1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the proj

External factors of swot analysis, This plan will build a good image for Ma...

This plan will build a good image for Maribyrnong Council, even Melbourne. The opportunity for Maribyrnong Council, there maybe will attract more investment for the company. It als

Production planning, PRODUCTION PLANNING AND SCHEDULING OF A GARMENTS MANUF...

PRODUCTION PLANNING AND SCHEDULING OF A GARMENTS MANUFACTURING COMPANY 1. Introduction TREND SHOPS SDN BHD is a manufacturing unit of (mid-upmarket) ladies garments.  It

How can management get more number of goods, How can management get more nu...

How can management get more number of goods? Management can get more number of goods (output) though the similar amount of resources input as given below: • Through reducing

Enterprising management, Hi dear my presentation is ready I need to do my B...

Hi dear my presentation is ready I need to do my Business Plan on it for 2500 words.. can u do it please

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd