Family Planning, Project Management

Assignment Help:
Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?


Related Discussions:- Family Planning

Challenges in quality management, Question 1: Describe - Expected Quali...

Question 1: Describe - Expected Quality, Design Quality and Actual Quality and how they influence the customer satisfaction. A Defining Expected Quality, Design Quality a

Explain the integration of the work breakdown structure, Question: (a) ...

Question: (a) Risk has always been an intrinsic part of project management. With increasing market competition, technology, and globalization, risk management is continuously

What is project scheduling, Question 1 Briefly explain various activities ...

Question 1 Briefly explain various activities involved in project management Question 2 What is COCOMO? Write necessary steps for cost estimation Question 3 What is proj

How you would estimate the project management activity, Explain how you wou...

Explain how you would estimate the project management activity. Project management: This effort is dependent onto two things as whether a full-time project manager is to be

Explain phases of group development, Question 1: (a) While managing HR...

Question 1: (a) While managing HR projects, explain the different stages that ultimately lead to ‘crisis' in a conflict situation. (b) Despite that fact that conflicts bre

Matrix organisation structure, M a t r i x organisation A matrix o...

M a t r i x organisation A matrix organisation is a combination of functional and project organisation. A weak matrix organisation has most of the characteristics of a fun

Identify the characteristics of the organisation, M is a business that sell...

M is a business that sells custom made computer-based information systems. Every customer order is for a unique system, which will contain experts from many functional areas within

Control charts, C ontrol charts Control  charts  are  tools  used  for...

C ontrol charts Control  charts  are  tools  used  for  monitoring,  controlling  and  improving processes over time. These are applicable to administrative processes.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd