East Coast Manufacturing, Inc. plans to locate a new production facility in Hartford, Philadelphia, or Baltimore. Six location factors are important: cost per product unit, labor availability, union activities, local transportation, proximity to similar industry and proximity to raw materials. The weighting of these factors, the scale for each factor and the scores for each location are shown below. Different SME's (subject matter experts) scored each of the non-economic factors. So, unfortunately, the scores for the non-economic factors are scaled differently. The scales are indicated on the table. On the scale, the highest score is always the best value. For example, for the scale 1-5, the best value is 5. For each of the Non-economic factors, it is possible to score the maximum.
Location Factor
Factor Weight
Scale
Hartford
Philadelphia
Baltimore
Cost per product unit
0.55
$48
$59
$52
Labour availability
0.15
0-5
2.5
4.0
Union activities
0.10
0-3
2.7
1.8
0.9
Local transportation
1.2
2.4
Proximity to similar industry
0.05
0-1
0.5
1.0
0.7
Proximity to raw materials
0.6
0.4
For the following, calculate all results three decimal place (example, 0.xxx or x.xxx).
a) Using the factor scoring (or equivalent the factor rating) approach we studied in class and modified as appropriate, which site do you recommend? Why?
b) With everything else remaining the same as in the problem statement, what must the cost per product unit for Philadelphia be so that its total factor score is equal to the total factor score for Hartford?
Does anyone know how to do aon in Excel 2010 and if so can they contact me and wlk me through it sso that I can understand it
I was watching a telethon on the TV late on evening. I was so moved by the telethon; I called and pledged $10,000. In the morning when I informed my husband what I pledged, he w
1) What is job evaluation? What method(s) of job position evaluation does employer use? Explain why. (Remember, "Job Evaluation" is not the same as "Performance Evaluation.") 2) Wh
1. What 'span of process' choices do you think have been made by the Graduate School of Business? Answer: Most core administrative processes are carried out by GSB staff; some,
Statistical Process Control - Mean and Range Charts 1. SPC can be used as a means of preventing product non-conformance 2. Causes of variability may be categorised as comm
a small assembly line for the assembly of power steering pumps needs to be balanced. exhibit 8.11 is the precedence diagram. the cycle time is determined to be 1.5 minutes. how wou
Define Product Management,functions of Product management
1) List the four schools of thought along with the basic cause of the labour problem and solution to the labour problem for each. 2) Explore the online exhibit about the 1911 Tr
What are three considerations in the wage determination criterion "ability to pay"? Why, by itself, can't the ratio of labour cost to total cost always be the formula of a company'
Frequently, at the time the project charter is prepared there is only a very general understanding of the project, so if a budget is prepared it can only be a crude estimate.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd