East Coast Manufacturing, Inc. plans to locate a new production facility in Hartford, Philadelphia, or Baltimore. Six location factors are important: cost per product unit, labor availability, union activities, local transportation, proximity to similar industry and proximity to raw materials. The weighting of these factors, the scale for each factor and the scores for each location are shown below. Different SME's (subject matter experts) scored each of the non-economic factors. So, unfortunately, the scores for the non-economic factors are scaled differently. The scales are indicated on the table. On the scale, the highest score is always the best value. For example, for the scale 1-5, the best value is 5. For each of the Non-economic factors, it is possible to score the maximum.
Location Factor
Factor Weight
Scale
Hartford
Philadelphia
Baltimore
Cost per product unit
0.55
$48
$59
$52
Labour availability
0.15
0-5
2.5
4.0
Union activities
0.10
0-3
2.7
1.8
0.9
Local transportation
1.2
2.4
Proximity to similar industry
0.05
0-1
0.5
1.0
0.7
Proximity to raw materials
0.6
0.4
For the following, calculate all results three decimal place (example, 0.xxx or x.xxx).
a) Using the factor scoring (or equivalent the factor rating) approach we studied in class and modified as appropriate, which site do you recommend? Why?
b) With everything else remaining the same as in the problem statement, what must the cost per product unit for Philadelphia be so that its total factor score is equal to the total factor score for Hartford?
A simple moving average_____. (may be more than 1 answer) A) lags a trend B) is best to use when product demand is unstable. C) cannot be used to filter out random fluctua
As a new entry-level manager, how important is to find ways to compensate for your relative lack of expertise when trying to determine which alternative before you is most likely t
An operation setback chart _____. is based on lead times that typically include move and queue times and indicates a schedule for when to make a part. is a schedule for when
Create the document with consideration to the following: E-Commerce business plan Use Word Title Page Table of Contents Use of the auto generated table of contents
What are the advantages of predetermined time standards (PTS)? Answer: Quicker and cheaper than time study; likely to be more reliable; valuable for estimating new jobs; can be
Q. What software applications can support inbound logistics? The following software applications can support inbound logistics: Bar coding for the receipt, movement and
Essentially relativism reject the notion that there is are no absolutes that govern our behaviour. How then do we determine how we behave? How reasonable and plausible is this posi
Global Supply Chain Issues Global supply chains bring problems of their own. As companies begin to apply organisational efficiencies achieved in their home markets to oversea
Matrix structures allow for workers to be shared on multiple projects and at a lower than usual cost. Answer To be shared on multiple projects and at a lower than usual cost
define the following key terms in product layout; product interval time, product duration, assembly line balancing
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd