East Coast Manufacturing, Inc. plans to locate a new production facility in Hartford, Philadelphia, or Baltimore. Six location factors are important: cost per product unit, labor availability, union activities, local transportation, proximity to similar industry and proximity to raw materials. The weighting of these factors, the scale for each factor and the scores for each location are shown below. Different SME's (subject matter experts) scored each of the non-economic factors. So, unfortunately, the scores for the non-economic factors are scaled differently. The scales are indicated on the table. On the scale, the highest score is always the best value. For example, for the scale 1-5, the best value is 5. For each of the Non-economic factors, it is possible to score the maximum.
Location Factor
Factor Weight
Scale
Hartford
Philadelphia
Baltimore
Cost per product unit
0.55
$48
$59
$52
Labour availability
0.15
0-5
2.5
4.0
Union activities
0.10
0-3
2.7
1.8
0.9
Local transportation
1.2
2.4
Proximity to similar industry
0.05
0-1
0.5
1.0
0.7
Proximity to raw materials
0.6
0.4
For the following, calculate all results three decimal place (example, 0.xxx or x.xxx).
a) Using the factor scoring (or equivalent the factor rating) approach we studied in class and modified as appropriate, which site do you recommend? Why?
b) With everything else remaining the same as in the problem statement, what must the cost per product unit for Philadelphia be so that its total factor score is equal to the total factor score for Hartford?
Since its release in 2001, the iPod has become a music player phenomenon. In your opinion, how would the QFD approach have helped Apple in developing the iPod? What are the limi
a small assembly line for the assembly of power steering pumps needs to be balanced. exhibit 8.11 is the precedence diagram. the cycle time is determined to be 1.5 minutes. how wou
The five types of leadership styles are most applicable in certain situations. Discuss the applicability of each of the five types in project leadership situations and its usefulne
Diagram a complex system (a series of causal loops and their interconnections) for the ecosystem of your choice (desert, rainforest, tidal marsh, etc.).
A
suppose the manufacturer has an inflated demand forecast as follows: Quantity Probability 2,200 5% 2,300 6% 2,400 10% 2,500 17% 2,600 30% 2,700 17% 2,800 12% 2,900 3% (a) Suppose t
Activities and Types of Scheduling Scheduling includes the followings activities 1. Allocation of quality and rate of output of the plant or department. And 2. Allocation
Order Losers - Operations Strategy These are characteristics which denote poor performance in the operations management function and can cause losses in current or future busi
By 2015, projections indicate that the largest category of households will be composed of a. childless married couples and empty nesters b. singles living with non
techniques & applicationa
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd