East Coast Manufacturing, Inc. plans to locate a new production facility in Hartford, Philadelphia, or Baltimore. Six location factors are important: cost per product unit, labor availability, union activities, local transportation, proximity to similar industry and proximity to raw materials. The weighting of these factors, the scale for each factor and the scores for each location are shown below. Different SME's (subject matter experts) scored each of the non-economic factors. So, unfortunately, the scores for the non-economic factors are scaled differently. The scales are indicated on the table. On the scale, the highest score is always the best value. For example, for the scale 1-5, the best value is 5. For each of the Non-economic factors, it is possible to score the maximum.
Location Factor
Factor Weight
Scale
Hartford
Philadelphia
Baltimore
Cost per product unit
0.55
$48
$59
$52
Labour availability
0.15
0-5
2.5
4.0
Union activities
0.10
0-3
2.7
1.8
0.9
Local transportation
1.2
2.4
Proximity to similar industry
0.05
0-1
0.5
1.0
0.7
Proximity to raw materials
0.6
0.4
For the following, calculate all results three decimal place (example, 0.xxx or x.xxx).
a) Using the factor scoring (or equivalent the factor rating) approach we studied in class and modified as appropriate, which site do you recommend? Why?
b) With everything else remaining the same as in the problem statement, what must the cost per product unit for Philadelphia be so that its total factor score is equal to the total factor score for Hartford?
Enumerate the major segmentation variables and provide real-life examples of segmentation done by firms for their products/services.
outsourcing as external source of capacity
Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into three activities. The first activity is designed to solicit in
Freight car loadings over a 12-year period at a busy port are as follows: Week Number Week Number Week Number 1 220 7 350 13 488 2 245 8 360 14 475 3 274 9 440 15 499 4 275 10 380
define Operational Management Evolution
A firm plans to begin production of a new small appliance. The manager must decide whether to purchase the motors for the appliance from a vendor for $7 each or to produce them in-
Which behaviours, thinking approaches, emotional stances, decisions, and business management actions can be found in the two readings that pertain to adaptability, resilience, and/
Regarding Social Responsibility, who do you agree with more, Leonard (2013) or Friedman (1970)? Why?
What is a ledger account?
Describe the S&OP process. What are the major trade-offs that must be considered?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd