Factor rating method, Operation Management

Assignment Help:

East Coast Manufacturing, Inc. plans to locate a new production facility in Hartford, Philadelphia, or Baltimore.  Six location factors are important:  cost per product unit, labor availability, union activities, local transportation, proximity to similar industry and proximity to raw materials.  The weighting of these factors, the scale for each factor and the scores for each location are shown below.   Different SME's (subject matter experts) scored each of the non-economic factors.  So, unfortunately, the scores for the non-economic factors are scaled differently.  The scales are indicated on the table.  On the scale, the highest score is always the best value.  For example, for the scale 1-5, the best value is 5.  For each of the Non-economic factors, it is possible to score the maximum. 

Location Factor

Factor Weight

Scale

Hartford

Philadelphia

Baltimore

Cost per product unit

0.55

 

$48

$59

$52

Labour availability

0.15

0-5

2.5

4.0

4.0

Union activities

0.10

0-3

2.7

1.8

0.9

Local transportation

0.10

0-3

1.2

2.4

2.4

Proximity to similar industry

0.05

0-1

0.5

1.0

0.7

Proximity to raw materials

0.05

0-1

0.7

0.6

0.4

For the following, calculate all results three decimal place (example, 0.xxx or x.xxx).

a) Using the factor scoring (or equivalent the factor rating) approach we studied in class and modified as appropriate, which site do you recommend?  Why?

b)  With everything else remaining the same as in the problem statement, what must the cost per product unit for Philadelphia be so that its total factor score is equal to the total factor score for Hartford?


Related Discussions:- Factor rating method

Explain what does the term product positioning refer to, What does the term...

What does the term product positioning refer to? A careful analysis of cross tabulations Shelf locations in major chain, grocery, and department stores Geographic segmenta

Determine the optimal solution nonlinear programming model, The Hickory Cab...

The Hickory Cabinet and Furniture Company makes chairs and tables. The company has developed the following nonlinear programming model to determine the optimal number of chairs (x1

Process technology life cycle , Process Technology Life Cycle Process ...

Process Technology Life Cycle Process technologies have life cycles related to product life cycles as shown in figure below. Over time unit manufacturing costs diminish for ma

How import tariffs and exchange rate adjustments, 1. The company's shipment...

1. The company's shipments of newly-produced branded and private-label footwear from its plants to its regional distribution centers are subject to a. any applicable import tari

What is a quality management system, Question: (a) What is a Quality Ma...

Question: (a) What is a Quality Management System (QMS) and why should an organization implement a Quality Management System? (b) Explain the eight fundamental Quality Manag

Explain permissive actions act, Why do unions emphasize the need for cohesi...

Why do unions emphasize the need for cohesiveness? So they can issue calls for "solidarity" to members during periods of threat Because group members tend to behave different

Explain what the average inventory be for this lot size, 1.What would the a...

1.What would the average inventory be for this lot size? (Round your intermediate calculations to 2 decimal places and final answer to the nearest whole number.) 2. Determine th

Explain risk management, Risk management is exposure to the consequences of...

Risk management is exposure to the consequences of uncertainty culture, processes and structures directed towards the management of potential opportunities determining if risk is t

Explain job market which favours the employer, Broad Bands - How does this ...

Broad Bands - How does this concept work today in a period of high unemployment, low pay increases, and a job market which favours the employer?

Deliberate sampling, Deliberate Sampling : Also  known  as purposive o...

Deliberate Sampling : Also  known  as purposive or non probability sampling this  sampling methods involves purposive or deliberate selection of  particular  unit  of the univ

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd