East Coast Manufacturing, Inc. plans to locate a new production facility in Hartford, Philadelphia, or Baltimore. Six location factors are important: cost per product unit, labor availability, union activities, local transportation, proximity to similar industry and proximity to raw materials. The weighting of these factors, the scale for each factor and the scores for each location are shown below. Different SME's (subject matter experts) scored each of the non-economic factors. So, unfortunately, the scores for the non-economic factors are scaled differently. The scales are indicated on the table. On the scale, the highest score is always the best value. For example, for the scale 1-5, the best value is 5. For each of the Non-economic factors, it is possible to score the maximum.
Location Factor
Factor Weight
Scale
Hartford
Philadelphia
Baltimore
Cost per product unit
0.55
$48
$59
$52
Labour availability
0.15
0-5
2.5
4.0
Union activities
0.10
0-3
2.7
1.8
0.9
Local transportation
1.2
2.4
Proximity to similar industry
0.05
0-1
0.5
1.0
0.7
Proximity to raw materials
0.6
0.4
For the following, calculate all results three decimal place (example, 0.xxx or x.xxx).
a) Using the factor scoring (or equivalent the factor rating) approach we studied in class and modified as appropriate, which site do you recommend? Why?
b) With everything else remaining the same as in the problem statement, what must the cost per product unit for Philadelphia be so that its total factor score is equal to the total factor score for Hartford?
how to solve aggregate planning
Review the week 6 info. in course material regarding the Apple iPhone supply chain. What issue/s do you think could be helped with a Pert/CPM plan for the supply chain? sk questi
There is a puzzle in regard to risk. What is management's responsibility regarding risk? At what level(s) does each aspect of risk management lie?
Principle of Scheduling First Principle optimum Task Size : scheduling tens to achieve its maximum efficient task sizes are small and all tasks are of the same order of magnit
phases of Operations Research
Explain how process technology is chosen for an operation.
As a result of testing 20,00 electric bulbs manufactured by a company it was found that the lifetime of the bulbs was normally distributed with a mean of life of 2040 hours with st
The Bawl Corporation supplies alloy ball bearings to auto manufacturers in Detroit. Because of its specialized manufacturing process, considerable work-in-process and raw materials
What is the difference between using an exact optimization technique and a heuristic to solve a problem?
1. Is Skinner's idea of operational focus just as relevant today? (Give a considered opinion - with examples.) Answer: The answer is yes. There are physical limitations in many
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd