East Coast Manufacturing, Inc. plans to locate a new production facility in Hartford, Philadelphia, or Baltimore. Six location factors are important: cost per product unit, labor availability, union activities, local transportation, proximity to similar industry and proximity to raw materials. The weighting of these factors, the scale for each factor and the scores for each location are shown below. Different SME's (subject matter experts) scored each of the non-economic factors. So, unfortunately, the scores for the non-economic factors are scaled differently. The scales are indicated on the table. On the scale, the highest score is always the best value. For example, for the scale 1-5, the best value is 5. For each of the Non-economic factors, it is possible to score the maximum.
Location Factor
Factor Weight
Scale
Hartford
Philadelphia
Baltimore
Cost per product unit
0.55
$48
$59
$52
Labour availability
0.15
0-5
2.5
4.0
Union activities
0.10
0-3
2.7
1.8
0.9
Local transportation
1.2
2.4
Proximity to similar industry
0.05
0-1
0.5
1.0
0.7
Proximity to raw materials
0.6
0.4
For the following, calculate all results three decimal place (example, 0.xxx or x.xxx).
a) Using the factor scoring (or equivalent the factor rating) approach we studied in class and modified as appropriate, which site do you recommend? Why?
b) With everything else remaining the same as in the problem statement, what must the cost per product unit for Philadelphia be so that its total factor score is equal to the total factor score for Hartford?
Please read through the question, then answer each item of my question to get full points. Review the following short article by visiting the link below then answer the question
Performance and Productivity Measurement The Performance and Productivity Measurement is divided into two parts: ? Performance measurement and ? Productivity measu
Ques: What do you consider to be the challenges facing operations managers today? 1. Interfacing with other managerial functions 2. Dealing with increased rates of change
Work Measurement: Work measurement goes hand in with method design. Whereas the method design are directed towards the study of the components of a single or multiple
Explain your views on the 'international cultural impact' of the current banking crisis and support your answer. If it is your opinion that there is no 'international cultural impa
..explain the relationship of capacity and location planning
All of the following statements about profit sharing are true/ except/1.profit sharing plan reward staff based on organization profits/2.profit reward a person according to measure
Can every company identify their target market? Advise as to why this is important or why it isn't important.
Siting Departments for Process Layout - Service Operations In determining the relative position of service departments the costs of movement may be less important than other,
Important skills required to increase productivity, how a person will manage this in time. Please response fast. Tomorrow is my interview
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd