East Coast Manufacturing, Inc. plans to locate a new production facility in Hartford, Philadelphia, or Baltimore. Six location factors are important: cost per product unit, labor availability, union activities, local transportation, proximity to similar industry and proximity to raw materials. The weighting of these factors, the scale for each factor and the scores for each location are shown below. Different SME's (subject matter experts) scored each of the non-economic factors. So, unfortunately, the scores for the non-economic factors are scaled differently. The scales are indicated on the table. On the scale, the highest score is always the best value. For example, for the scale 1-5, the best value is 5. For each of the Non-economic factors, it is possible to score the maximum.
Location Factor
Factor Weight
Scale
Hartford
Philadelphia
Baltimore
Cost per product unit
0.55
$48
$59
$52
Labour availability
0.15
0-5
2.5
4.0
Union activities
0.10
0-3
2.7
1.8
0.9
Local transportation
1.2
2.4
Proximity to similar industry
0.05
0-1
0.5
1.0
0.7
Proximity to raw materials
0.6
0.4
For the following, calculate all results three decimal place (example, 0.xxx or x.xxx).
a) Using the factor scoring (or equivalent the factor rating) approach we studied in class and modified as appropriate, which site do you recommend? Why?
b) With everything else remaining the same as in the problem statement, what must the cost per product unit for Philadelphia be so that its total factor score is equal to the total factor score for Hartford?
how will you influencepeople to strive willingly for group objectives in your organisation(target based industry)apply your interpersonal influence through communication process to
Operations and Supply Chain Management : CELL PHONE DESIGN PROJECT 1. Draw a project network that includes all the activities 2. Calculate the start and finish times for each
1. What are the order winning criteria for this organisation? Where does the company sit in Schmenner's Service-Process matrix and can you detect the adoption of the principles und
what is characterstics of operation research
Why do you think many managers are surprised by environmental changes and hence are less able to help their organizations adapt?
Priorities for Improving Customer Satisfaction - Operation Strategy The graphical presentation in this figure (adapted from Johnston, 1997) shows clearly the opportunities for
Value: 15.00 points Problem 3-2 National Scan, Inc., sells radio frequency inventory tags. Monthly sales for a seven-month period were as follows: Month Sales (000) Units Feb. 17 M
When linking marketing requirements and manufacturing strategy, what design approaches for shop floor system should be considered? JIT and Lean MRP and PAC MRP and JIT
• Explain why some states do and other states don't have a public-sector bargaining law or laws that cover some public employees but not others. • From the second e-Activity, co
What is a current, struggling product?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd