The following diagram shows a C.P.A.-network modeling the stages in the construction project. Each arc is labeled with the letter denoting the activity it represents and a weight that denotes the number of days needed to complete that activity. Activities A and B can start as soon as the project commences, and the project is finished when I and K have been completed. The arc labeled Z represents a dummy activity introduced to model the logical structure of the network.
(a) List the prerequisite activities for (i) G and (ii) I in this construction project. Explain why it is necessary to introduce the dummy activity Z to obtain the C.P.A.-network.
(b) Say what a vertex in a C.P.A.-network represents. Copy the network above and give its vertices an acyclic labeling v1, v2,..., v8, where v1 represents the start of the manufacturing process.
(c) Say what is meant by the early event time ET (v) and the late time event LT (v) for an event v. Calculate ET (v) and LT (v) for each event in this project, entering these times in the appropriate boxes on your diagram.
(d) What is the shortest time in which this project can be completed?
(e) Suppose an activity is represented by the arc vivj with weight w (vivj). Say how the total float time for this activity is calculated. Tabulate the total float time for each activity in this project.
(f) Identify all the critical activities in this project and find the critical path(s) in this C.P.A.-network.
You are a manager in the investment industry, whose role is to provide investment portfolio advice and managementto a client, who is your investorprincipal. You should identify t
QUESTION 1 (a) Based on the Strategic Implementation Framework, discuss the various factors that should be considered when implementing a strategic plan. (b) What are the ma
Q uality definition The initial step of project quality management is to define quality. The project manager and the team must identify and define the quality standar
STYLE OF A RESEARCH REVIEW: The review must be brief but complete in itself. Systematic review should be considered. The review should use statements of opinions, sparingly,
LIBRARY CATALOGUE-Introduction Library catalogue is an essential and important tool for any library. This tool has been developed to facilitate the use of reading materials in
HUMAN RESOURCES DEVELOPMENT (HRD) The effective participation and quality performance of human•beings in the various activities of an organisation result in an HRD process whi
QUESTION 1 You are required to (i) explain the concept of benchmarking (ii) identify and write short notes on the step involved in a benchmarking exercise QUESTION 2
Stereotype The tendency to judge someone is based on the perception of the group to which that person belongs. For example I might stereotype him as a "jock" if I know a person
1. What instructional technology and techniques does research prove are beneficial? Detrimental? 2. Does moving students from single-gender education to co-ed increase student achi
Question: A textile manufacturing company would like to implement a system for managing its production. The company does not have any in-house IT staff and has outsourced the c
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd