The following diagram shows a C.P.A.-network modeling the stages in the construction project. Each arc is labeled with the letter denoting the activity it represents and a weight that denotes the number of days needed to complete that activity. Activities A and B can start as soon as the project commences, and the project is finished when I and K have been completed. The arc labeled Z represents a dummy activity introduced to model the logical structure of the network.
(a) List the prerequisite activities for (i) G and (ii) I in this construction project. Explain why it is necessary to introduce the dummy activity Z to obtain the C.P.A.-network.
(b) Say what a vertex in a C.P.A.-network represents. Copy the network above and give its vertices an acyclic labeling v1, v2,..., v8, where v1 represents the start of the manufacturing process.
(c) Say what is meant by the early event time ET (v) and the late time event LT (v) for an event v. Calculate ET (v) and LT (v) for each event in this project, entering these times in the appropriate boxes on your diagram.
(d) What is the shortest time in which this project can be completed?
(e) Suppose an activity is represented by the arc vivj with weight w (vivj). Say how the total float time for this activity is calculated. Tabulate the total float time for each activity in this project.
(f) Identify all the critical activities in this project and find the critical path(s) in this C.P.A.-network.
L C Descriptive Rules: Library of Congress. Rules for Descriptive cataloging at the Library of Congress Adopted by the American Library Association. - Washington, D.C.: Libra
Q uality assurance plan The quality assurance plan is to establish the goals, the process and the responsibilities needed to implement the effective quality assurance function
M ergers Merger happens when two companies, mostly of the same size, agree to go forward as a single new company in the best interest of both. The shareholders of the involved
A d v antages of an EPM System Let us now see some of the advantages of EPM are: One of the key rewards of converting to an EPM system is that projects have superior
QUESTION 1 The Proven Path consists of a number of discrete steps. Explain the different steps of the proven path. QUESTION 2 One major step in getting organized is to
Critically analyze Mr. Vincent''s reasoning?
Question 1 Write break down or corrective or remedial maintenance. Question 2 Explain the planning principles in maintenance management, Question 3 The principles used i
QUESTION You are given the task to draft a Code of Ethics for your organization (a) Define a Code of Ethics (b) What are the different aspects/issues that you might incl
Methods Following is a brief description of the prevalent methods of stock taking. Stock Verification by Accession Numbers: The accession numbers of the books from t
manufacturing firms
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd