Explain which station is the bottleneck station, Operation Management

Assignment Help:

A production line at A's machine shop has three stations. The first station can process a unit in 10 minutes. The second station has two identical machines, each of which can process a unit in 12 minutes (each unit only needs to be processed on one of the two machines). The third station can process a unit in 8 minutes. Which station is the bottleneck station? Please explain in detail


Related Discussions:- Explain which station is the bottleneck station

Explain what difference does it make, Use a dystopian narrative within Mart...

Use a dystopian narrative within Martin Luther King's speech. What difference does it make?

Explain performance appraisals are they necessary, 1.What purpose do they s...

1.What purpose do they serve under a performance management system? 2.Performance appraisals are they necessary or not? 3.What to do if an performance appraisal is unsatisfac

Production efficiencies and reducing unit costs, A manufacturer concerned m...

A manufacturer concerned mainly with production efficiencies and reducing unit costs is known as Production oriented.

Number of shiments and number of defective shiments, The quesstion is to de...

The quesstion is to develop a scattr diagram using total number of shiments and number of defective shiments. This is for Project management mgmt. can some one help me with this

Process Design, Discuss how the five Operational Performance Objectives may...

Discuss how the five Operational Performance Objectives may influence decision-making associated with process design and layouts.

Explain developing or enhancing their organization, There are several diffe...

There are several different models of business development that entrepreneurs can utilize when developing or enhancing their organization. Research on stages of business developmen

Explain bp''s first problem, Describe BP'S first problem, which involved th...

Describe BP'S first problem, which involved the firms IT function. Discuss BP'S solution to this problem.

Define the areas for environmental responsibility, Define the areas for env...

Define the areas for environmental responsibility. Bennett and James areas for environmental responsibility: • Production for example, minimising waste and toxic emissions.

Define critical path, Define Critical Path. Critical Path: Computatio...

Define Critical Path. Critical Path: Computation of Earliest and Latest Values of the events of the specified network is as follows:-  Event              EOT

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd