Explain which path is the critical path, Operation Management

Assignment Help:

Given the information below:

1. Construct a network using the AON (Activity on Network method) like we did in class. See problem 3.4 on page 90 and its answer in the Appendix on page A8.

2. Show how you calculate the path in weeks for each of the three paths.

3. Which path is the critical path?

Immediate Time

Activity Predecessor (weeks)

A --- 1

B --- 4

C A 1

D B 2

E B 5

F C, D 7

G E 2

H F, G 3


Related Discussions:- Explain which path is the critical path

Benefits of e-business, Benefits of E-Business There are many benefits...

Benefits of E-Business There are many benefits claimed for e-business, including: 1.      Increased capacity 7 days, 24 hours  2.      Reduced transaction costs/ cost of

Describe how trade lowers the costs of making computer parts, closing case:...

closing case: Logitech Best known as one of the world's largest producers of computer mice, Logitech is in many ways the epitome of the modern global corporation. Founded in 198

Elements, what are the elements of production forecasting?

what are the elements of production forecasting?

Thus the best decision isn''t always made, As a manager, you are expected t...

As a manager, you are expected to make logical, rational decisions that are in the best interests of the organization. However, the best decision isn't always made. Let's discuss w

Explain early retirement, Assume you are the project manager for a software...

Assume you are the project manager for a software company and your team is in charge of delivering an update to tax preparation software for the next tax season. The project team h

Describe system safety program, You are the System Safety Engineer for a ma...

You are the System Safety Engineer for a major aerospace firm. You have been assigned to lead the system safety program for a newly developed aircraft. What are some of the key tas

Transportation cost, a. Assign any value arbitrarily to a row or column var...

a. Assign any value arbitrarily to a row or column variable u or v j . generally a value 0 zero (zero) is assigned to the first row i, e, u = 0. b.Consider every occupied cell

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd