Explain what output rate will be achieved, Operation Management

Assignment Help:

An assembly line with 30 activities is to be balanced. The total amount of time to complete all 30 activities is 42 minutes. The longest activity takes 2.4 minutes and the shortest takes .3 minutes. The line will operate for 480 minutes per day. a. What are the maximum and minimum cycle times? b. What output rate will be achieved by each of those cycle times?


Related Discussions:- Explain what output rate will be achieved

Explain administrative issues, Unit IV: At the Bargaining Table Unit V: Gri...

Unit IV: At the Bargaining Table Unit V: Grievances and Arbitration Unit VI: Wage Issues and Economic Supplements Unit VII: Institutional Issues Unit VIII: Administrative Issues

Explain effectively manage supply risks, To effectively manage supply risks...

To effectively manage supply risks, the supply manager must: inform the corporate risk officer of a potential risk, await instructions, and implement the directive. Seek input from

Explain main reasons businesses safe guard the environment, What are the ma...

What are the main reasons businesses don't conserve natural resources or safe guard the environment?

Explain the market testing stage of the new-product process, The market tes...

The market testing stage of the new-product process often involves test markets or purchase laboratories in which the dependent variable is consumer attitudes. price. adve

How you would address project management situation, MBTI and Keirsey Temper...

MBTI and Keirsey Temperament Sorter Describe the challenges you foresee in using the MBTI instrument or Keirsey Temperament Sorter in a project management situation and how you wo

Explain what is the annual ordering cost, If annual demand is 24,000 units,...

If annual demand is 24,000 units, orders are placed every 0.5 months, and the cost to place an order is $50, what is the annual ordering cost?

Find forecasted sales for week first, In the table given below the Distribu...

In the table given below the Distribution Manager is expected to service these DCs as per the demands placed. If the actual sales after completing week one is as follows, what woul

Gantt chart, Gantt Chart The Gantt chart were made by Henry L. Gantt ...

Gantt Chart The Gantt chart were made by Henry L. Gantt approximately a century ago. Their aim is to provide an immediate comparison between schedule and realty( i.e. among p

Dipict the network diagram, Four parts (A, B, C, and D) are processed throu...

Four parts (A, B, C, and D) are processed through a sequence offour operations (1, 2, 3, and 4). Not all parts are processed inall operations. Part A, which has weekly quantities o

Describe home improvement project or charity project, Risk is often describ...

Risk is often described as the event that "might" happen during the course of a project. Explain how risk has impacted a project that you have been associated with as a team member

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd