On day 51, a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the health of the project on day 51? Explain.


Related Discussions:- Explain what is your assessment of the health of the project

Explain employer disciplinary actions, Identify how the issues of due proce...

Identify how the issues of due process and just cause are linked to employer disciplinary actions

Explain what are four significant pieces of legislation, What are four sign...

What are four significant pieces of legislation that evolved from the civil rights act of 1964

Explain organizational strategic planning, Human resource practice competen...

Human resource practice competencies are a core set of competencies that: Answer A)relate to human capital development B) include knowledge and skills that make a company profitabl

Explain what is the utilization of pharma, Pharma Blitz develops and market...

Pharma Blitz develops and markets new technological products to be used in health care. The development of a new product operates as follows. When a new technology meets the requis

Explain identify the basic control issues at unilever, Identify the basic c...

Identify the basic control issues at Unilever from all three levels? How do you think the control function should be organized and managed at Unilever?

Explain the differences unsecured credit and secured credit, Compare and co...

Compare and contract unsecured credit and secured credit, and explain the key differences. Provide an example for each.

Transportation cost, a. Assign any value arbitrarily to a row or column var...

a. Assign any value arbitrarily to a row or column variable u or v j . generally a value 0 zero (zero) is assigned to the first row i, e, u = 0. b.Consider every occupied cell

Explain what output rate will be achieved, An assembly line with 30 activit...

An assembly line with 30 activities is to be balanced. The total amount of time to complete all 30 activities is 42 minutes. The longest activity takes 2.4 minutes and the shortest

Confidence interval of the population mean life, A sample of 36 "AA" Alkali...

A sample of 36 "AA" Alkaline batteries has a mean life of 6 months. The standard deviation of the population is known to be 3 months. Find the 95% confidence interval of the popual

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd