Tasks: A - 20 sec - no precedence B - 7 sec - preceded by A C - 20 sec - preceded by B D - 22 sec - preceded by B E - 15 sec - preceded by C F - 10 sec - preceded by D G - 16 sec - preceded by E,F H - 8 sec - preceded by G The workday is seven hours long. Demand for completed to product is product is 750 per day. a) Find the cycle time. b) What is the theoretical number of workstations? c) Draw the precedence diagram. d) Balance the line using sequential restrictions and the longest-operating-time rule. e) What is the efficiency of the line balanced as in d? f) Suppose the demand rose from 750 to 800 units per day. What would you do? Show any amount or calculations. g) Suppose that demand rose from 750 to 1,000 units per day. What would you do? Show any amount or calculations.


Related Discussions:- Explain what is the theoretical number of workstations

Explain earned value measurement is a technique, Earned value measurement i...

Earned value measurement is a technique: Answer Suitable for risk monitoring and control Unsuitable for risk monitoring and control Suitable for risk monitoring but uns

Explain the bargaining unit as technical workers, Jack is a 2nd level manag...

Jack is a 2nd level manager at Johnson Controls. His department includes 2 supervisors, 5 night shift security guards, 5 technical workers, 10 janitorial staff, and 25 manufacturin

Public and private service sector - education, Public and Private Service S...

Public and Private Service Sector - Education 1. Life long learning; increased personal cost 2. Increase in competency/vocational qualifications 3. Global study on the

Human Resource, 1. What in your view are the central human resources issues...

1. What in your view are the central human resources issues involved in this case?

Define what would the average inventory be for this lot size, A chemical fi...

A chemical firm produces sodium bisulfate in 100-pound bags. Demand for this product is 20 tons per day. The capacity for producing the product is 50 tons per day. Setup costs $100

Explain europe and japan to adopt the new product, What triggered the new p...

What triggered the new product strategy at Minnesota Biolabs? 2. What prediction would you make for the success of getting the country general managers in Europe and Japan to adopt

How to view intermingling of management, The chapter notes that in 2010, in...

The chapter notes that in 2010, in roughly two-thirds of U.S. firms, the CEO is also the chair of the board of directors. More broadly this can be viewed as an intermingling of man

Case Study, Combine your list with the lists of a few other class members a...

Combine your list with the lists of a few other class members and categorize the items under a series of major headings.

Effect of statistical process control, Effect of Statistical Process Contro...

Effect of Statistical Process Control The essence of this approach is that, having set up a process and established that it is stable, sample measurements of the process outpu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd