Explain what is the theoretical number of workstations, Operation Management

Assignment Help:

Tasks: A - 20 sec - no precedence B - 7 sec - preceded by A C - 20 sec - preceded by B D - 22 sec - preceded by B E - 15 sec - preceded by C F - 10 sec - preceded by D G - 16 sec - preceded by E,F H - 8 sec - preceded by G The workday is seven hours long. Demand for completed to product is product is 750 per day. a) Find the cycle time. b) What is the theoretical number of workstations? c) Draw the precedence diagram. d) Balance the line using sequential restrictions and the longest-operating-time rule. e) What is the efficiency of the line balanced as in d? f) Suppose the demand rose from 750 to 800 units per day. What would you do? Show any amount or calculations. g) Suppose that demand rose from 750 to 1,000 units per day. What would you do? Show any amount or calculations.


Related Discussions:- Explain what is the theoretical number of workstations

Technological infrastructure, Identity technological infrastructure that su...

Identity technological infrastructure that supports operations management

Explain switching methods, Which of the following switching methods is fast...

Which of the following switching methods is faster? A. cut-through mode B. source-route C.store and forward D. translational

Find the critical path, Using the information given in the following table:...

Using the information given in the following table: (A) Identify the critical path. (B) Determine expected project duration. Activities Precedes Duration Start a,b,c - a d 5 d f 6

Find number of job requests, Value: 10.00 points Problem 3-4 An electrical ...

Value: 10.00 points Problem 3-4 An electrical contractor's records during the last five weeks indicate the number of job requests: Week: 1 2 3 4 5 Requests: 16 18 14 17 18 Predict

Explain responsibility towards importers and exporters, The U.S. State Depa...

The U.S. State Department has some responsibility towards Importers and Exporters. What are these responsibilities?

Compute number of workers needed for each department, Calculate number of w...

Calculate number of workers needed for each department to produce 2000 units per day and complete the table below to assist you in answering questions e.)è?j.). (e) What is the tot

Explain schedule performance index, Question at the end of one of my chapte...

Question at the end of one of my chapters. Would like to see an example of cost and schedule performance index completed. I appreciate the help A sales-related venture had an ac

What is decomposition principle, Solve the following linear program using t...

Solve the following linear program using the decomposition principle: minimize z = ?2x1 ? 5x2 subject to x1 + 2x2 = 13.5 x1 + 3x2 = 18.0 x1 ? 9 x2 ? 5 x1, x2 ? 0. Let the first two

Assuming these are the critical attributes for perfect order, An analysis o...

An analysis of order and shipment data shows that the order fill rate is 97.1% and ABBA collected the following data concerning customer service performance: Late delivery-5 per

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd