Explain what is the minimum number of workstations output, Operation Management

Assignment Help:

An assembly line with a number of tasks is to be balanced. The sum of the task times is 100 minutes. The line will operate for 7 hours per day.

What is the minimum number of workstations that will ensure an output rate of 50 units per day? (Assume that all of the individual task times are smaller than the obtained cycle time.)


Related Discussions:- Explain what is the minimum number of workstations output

Explain statistical cost estimation technique, The technique that estimates...

The technique that estimates long-run costs and the minimum efficient scale by determining the scale of operation at which most firms in an industry are concentrated is called the-

Explain terms national economy and manufacturing sector, As a library or in...

As a library or internet assignment, find the U.S. productivity rate (increase) last year for (a) national economy, (b) manufacturing sector, and (c) service sector.

Explain what type of information must mititech''s suppliers, 1 To ensure th...

1 To ensure that its supply chain can handle a surge in demand, MitiTech should: a. hire additional manufacturing employees b. modify its design to speed up production time

#Process design plant locatiom.., Relation with types of manufacturing plan...

Relation with types of manufacturing plant location and layout.?

Explain company is operating at full capacity, Develop a decision tree for ...

Develop a decision tree for the case of a company is operating at full capacity and with product demand rising. The choice is between new equipment and overtime. A 20% rise in sale

Define what will be the average number of jobs in the system, A single mach...

A single machine work center has five jobs assigned to it. They are labelled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only

Forecasting adn Time Series Anlaysis, To answer Question 1: Use the forecas...

To answer Question 1: Use the forecasting module that you opened in the POM-QM for Windows software to solve the Southwestern University case study at the end of Chapter 4 of the H

What are the steps you took to address the issue, Consider a time when you ...

Consider a time when you have acted as a leader in the past and had to mitigate an issue. Examine how you resolved the issue. If the issue was not resolved, examine the steps you t

How minimizes the number orders waiting in the queue, Which of the followin...

Which of the following rules maximizes the number of orders processed in a center and minimizes the number orders waiting in the queue? Shortest operation next First-come/fir

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd