Explain what is the maximum possible output per week, Operation Management

Assignment Help:

An assembly line with 7 tasks is to be balanced. The longest task is 8 minutes, the shortest task is 2 minutes, and the sum of the task times is 53 minutes. The line will operate for 6 hours per shift, 1 shifts per day, 6 days per week.

What is the maximum possible output per week for this line?


Related Discussions:- Explain what is the maximum possible output per week

Explain drink equally appealing to men, Do you think Diet Coke could have b...

Do you think Diet Coke could have been repositioned to change consumers' perceptions of it enough to be considered a drink equally appealing to men? Why or why not?

Explain important part of strategic training, Why is evaluating training an...

Why is evaluating training an important part of strategic training?

Describe the structure of the appellate courts, You have successfully held ...

You have successfully held your first training session on the common law tradition and sources of law! Now that everyone has an understanding of the origins of law, your next prime

Explain cars tend to break down at the rate of two per hour, During the cam...

During the campus Spring Fling, the bumper car amusement attraction has a problem of cars becoming disabled and in need of repair. Repair personnel can be hired at the rate of $20

Upper bound, Customers arrive at a fast food restaurant with one server at ...

Customers arrive at a fast food restaurant with one server at a mean rate of 30 per hour. The server has just resigned, and the two candidates for the replacement are X (fast but

Calculate the standard production, Calculate the standard production  per s...

Calculate the standard production  per shift  of 8 hours duration  with the followings data: Observed time  per unit 5 minutes  Rating  factor 120 %  Total allowances 33.3

Explain how to negotiate for more compensation, Describe how to negotiate f...

Describe how to negotiate for more compensation. Explain why one must be assertive to earn what he or she deserves. Relate four things not to do when asking for a raise. How much c

Explain a process capacity methodology, A process capacity methodology that...

A process capacity methodology that is used to show how well parts being produced fit into a range specified by design limits is which of the following? Answers- a. Answer n

Explain path for data between two points on a network, Name 3 factors that ...

Name 3 factors that a router must consider when determining the best path for data between two points on a network?

Decisions making and profit maximization, Question 1. It is often said...

Question 1. It is often said that profit maximization is the sole objective of business conduct. Do you agree with this view? Justify your answer using at least one example /

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd