Explain what is the expected project length, Operation Management

Assignment Help:

Task time estimates for a production line setup project
at Robert Klassen's Ontario factory are as follows:
Immediate
Activity Time (in hours) Predecessors
A 6.0 -
B 7.2 __
C 5.0 A
D 6.0 B, C
E 4.5 B, C
F 7.7 D
G 4.0 E, F
a) Draw the project network using AON.
b) Identify the critical path.
c) What is the expected project length?


Related Discussions:- Explain what is the expected project length

What is diversification, What is Diversification? Ans: Diversificati...

What is Diversification? Ans: Diversification is guiding activities into different lines of business.

Explain what are the optimal solution values of x and y, Suppose the firm i...

Suppose the firm in this example considers a second product that has a unit profit of $5 and requires 2 hours for each unit produced. Assume total production capacity remains 40. U

Explain intent or motive behind sexual harassment activities, Should be int...

Should be intent or motive behind Lewiston's conduct be considered when deciding sexual harassment activities? Explain

Explain path for data between two points on a network, Name 3 factors that ...

Name 3 factors that a router must consider when determining the best path for data between two points on a network?

Industrial society - operations function, Industrial Society - Operations F...

Industrial Society - Operations Function In the industrial society, estimated during the period of growth of industrialisation roughly 1820-1920, machines and the production o

Key issues when implementing an erp system, 1. Discuss how you interpret th...

1. Discuss how you interpret the statement 'ERP is the 'meat and potatoes' of the organisation'.  2. What are the key issues when implementing an ERP system?  3. How will tra

Explain the leadership characteristics, Provide two examples of current lea...

Provide two examples of current leaders and describe how they demonstrate their leadership characteristics. What separates these characteristics from management techniques? How eff

Make a mixed plan for this problem by permitting backordered, X-Print Manuf...

X-Print Manufacturing makes laser printers. One plant assembles the PL-4000 model. Standards indicate that one worker can assemble five printers per day. This model costs about $35

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd