Task time estimates for a production line setup project
at Robert Klassen's Ontario factory are as follows:
Immediate
Activity Time (in hours) Predecessors
A 6.0 -
B 7.2 __
C 5.0 A
D 6.0 B, C
E 4.5 B, C
F 7.7 D
G 4.0 E, F
a) Draw the project network using AON.
b) Identify the critical path.
c) What is the expected project length?


Related Discussions:- Explain what is the expected project length

Is focused factory concept applicable in service sector, Is the 'focused fa...

Is the 'focused factory' concept described by Skinner applicable in the service sector? Answer:  Yes, think of Schmenner's service-process matrix and the lower quadrant entitled

Benefits of e-business, Benefits of E-Business There are many benefits...

Benefits of E-Business There are many benefits claimed for e-business, including: 1.      Increased capacity 7 days, 24 hours  2.      Reduced transaction costs/ cost of

Explain how you would mitigate each risk identified, Imagine you are consid...

Imagine you are considering opening a specialty pet store in your area. Create a list of the five most significant risks that you must address prior to making your decision regardi

Describe what specific planning challenges, Someone Help Please! Select one...

Someone Help Please! Select one of the following companies to study in depth over the next 4 weeks. BP Oil Kimberly-Clark Kroger Nucor Walgreens Wells Fargo Kaiser Permanente Ascen

How marketing consultant brought in to help a company, Imagine you are a ma...

Imagine you are a marketing consultant brought in to help a company who has a product that is so successful they cannot keep up with customer demand. What questions would you as

Explain how can a wireless network compensate for fading, How can a wireles...

How can a wireless network compensate for fading and delay?

Normal time, a time study was made of a punch press operator. the average o...

a time study was made of a punch press operator. the average observed time after discounting non normal occurrence was 0.52 minutes per unit. the operator performance was judged to

Explain characteristics of a definable sample group, Which of the following...

Which of the following requires the opinion of an expert to determine the location and characteristics of a definable sample group? Judgment sample Simple random sample S

Explain comparison of processes with a direct adversary, 1. A simulation mo...

1. A simulation model goes one step further than possible with analysis tools, because it can show how the process performs ____________ over time. 2. A(n) ____________ is a met

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd