Explain what is the expected project length, Operation Management

Assignment Help:

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows-

a) 6.0 -

b) 7.2 -

c) 5.0 a

d) 6.0 b,c

e) 4.5 b,c

f) 7.7 d

g) 4.0 e,f

a) Draw the project network using AON.

b) Identify the critical path.

c) What is the expected project length?


Related Discussions:- Explain what is the expected project length

Performance measurement in organisations, Performance Measurement 1. A...

Performance Measurement 1. An effective performance measurement framework rarely is derived from one single approach.  2. Each of the methods outlined comes with its own un

Explain when the doctor dictates a decimal such as point1, What do you do w...

What do you do when the doctor dictates a decimal such as "point 1"?

Explain unethical for advertisers to pitch products, Do you feel it's uneth...

Do you feel it's unethical for advertisers to pitch products to patients and students in this fashion? why?

Therefore by searching newspapers, You have successfully prepared yourself ...

You have successfully prepared yourself for the career of your choice but the recruiters visiting your school have not offered you a job. Now you must look on your own. So by searc

Compute the slope and the intercept of the trend equation, Demand for a sur...

Demand for a surgical procedure at St. Elsewhere Hospital has increased steadily over the past few years: Year 1 2 3 4 5 Heart Transplants 45 50 52 56 61 Use the

Case studies, Bloomsday Outfitters produces T-shirts for road races. They n...

Bloomsday Outfitters produces T-shirts for road races. They need to acquire some new stamping machines to produce 30,000 good T-shirts per month. Their plant operates 200 hours per

Why company declines to correct the flaw, Scenario 2: A supervisor discover...

Scenario 2: A supervisor discovers a design flaw, which she believes is a safety hazard. She informs the company through the proper channels. The company declines to correct the fl

MBA 2ND SEM, Q3. What do you understand by “line balancing”? What happens i...

Q3. What do you understand by “line balancing”? What happens if balance doesn’t exist?

Explain responsibility of improving automobile loans, A loan manager for Ba...

A loan manager for Bank of Cascades has the responsibility of improving automobile loans. To assist her in this matter, she has compiled data on 428 cars and trucks. This data are

What is the objective of the total productive maintenance, What is the obje...

What is the objective of the total productive maintenance? Total productive maintenance (TPM) aims to shorten lead times by making sure production and machine maintenance staff

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd