Explain what is the expected project length, Operation Management

Assignment Help:

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows-

a) 6.0 -

b) 7.2 -

c) 5.0 a

d) 6.0 b,c

e) 4.5 b,c

f) 7.7 d

g) 4.0 e,f

a) Draw the project network using AON.

b) Identify the critical path.

c) What is the expected project length?


Related Discussions:- Explain what is the expected project length

Control chart - sample mean chart & sample range chart, Control Chart - Sam...

Control Chart - Sample Mean Chart & Sample Range Chart As sample values are progressively plotted on the charts, they are examined for patterns which may be tested against a s

Explain traditionally non-user input environment, To what extent should end...

To what extent should end users be involved in the design of a database? How have our ideas of agile development environments affected this traditionally non-user input environment

MBA, Q3. What do you understand by “line balancing”? What happens if balanc...

Q3. What do you understand by “line balancing”? What happens if balance doesn’t exist?

Explain specifically about team incentive rewards, Do results from the surv...

Do results from the survey illustrate typical complaints about teams and specifically about team incentive rewards?

How import tariffs and exchange rate adjustments, 1. The company's shipment...

1. The company's shipments of newly-produced branded and private-label footwear from its plants to its regional distribution centers are subject to a. any applicable import tari

Find the average total setup cost and shortage cost, A manufacturer uses a ...

A manufacturer uses a purchase part who's demand over any time period of length t (in years) can assume to be normally distributed with mean 200t and variance 400t. The part cost $

Operational layout , Put Simply, operational layout is about deciding where...

Put Simply, operational layout is about deciding where to put all the facilities, machines, equipment and the staff with in the operation. For an organization of you choice discuss

Explain a key characteristic of a partnership, A key characteristic of a pa...

A key characteristic of a partnership is that each partner a. must contribute capital to the business b. shares in company assets upon the dissolution of the partnership c

Layout s problems, what are the problems of layouts like: functional , line...

what are the problems of layouts like: functional , line layout in production & operation mangement subject

Describe project should be clearly explained, The "ends" of the project sho...

The "ends" of the project should be clearly explained, measured, and communicated, prior to the "means" being decided

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd