Explain what is the critical path, Operation Management

Assignment Help:

Shirley Hopkins is developing a problem in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activities Immediate Predeccesor(s) Time (days)

A -- 2
B -- 5
C -- 1
D B 10
E A,D 3
F C 6
G E,F 8

a) Develop an AON network for this problem.

b) What is the critical path?

c)What is the total project completion time?

d)What is the slack time for each individual activities?


Related Discussions:- Explain what is the critical path

Explain different levels of diversification firms, What are the different l...

What are the different levels of diversification firms can purpsue by using different corporate level strategies and what are the advantages to diversifying their operations?

Explain line balancing, Explain Line Balancing. Line Balancing: It m...

Explain Line Balancing. Line Balancing: It means balancing the line between the product lines or assembly lines. This aims at grouping facilities and workers in an efficient

Process Technology, what are the types of process technologies that can be ...

what are the types of process technologies that can be applied to the problems experienced in registration centers at school and how can they be integrated ?

When needed extra money to spend, Please explain in detail the answer for t...

Please explain in detail the answer for the following scenario: Your boss looks at his budget in April and realizes that he has extra money to spend, so he tells you to create and

Explain significance of the brainstorming suggestions, Assess the significa...

Assess the significance of the brainstorming suggestions and determine how you might use this information to improve the chances of the project's success

Discuss the existence of an agency at the time the contract, Paul Gett is a...

Paul Gett is a well-known wealthy financial expert living in the city of Torris. Adam Wade, Gett's friend, tells Timothy Brown that he is Gett's agent for the purchase of rare coin

Systems approach to process planning and design, Systems Approach to Proces...

Systems Approach to Process Planning and Design Knowledge about operations strategies, product / service designs, technologies of the production system, and markets are used t

Factors affecting scheduling - external factors, Factors Affecting Scheduli...

Factors Affecting Scheduling - External Factors The following factors govern the scheduling and are to be considered before establishing scheduling plan: External Factors:

Explain the utilization and the efficiency of each situation, Determine the...

Determine the utilization and the efficiency for each of these situations: a. A loan processing operation that processes an average of 7 loans per day. The operation has a design c

How to develop an aggregate plan for product line, DAT, Inc, company needs ...

DAT, Inc, company needs to develop an aggregate plan for its product line. Relevant data are Production time: 1 hour per unit Average labor cost: $10/hour Workweek: 5 d

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd