Explain what is the average completion time of all jobs, Operation Management

Assignment Help:

A single machine work center has five jobs assigned to it. They are labelled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest (earliest) due date rule, what is the average completion (flow) time of all jobs?

A) 4.0
B) 12.6
C) 2.6


Related Discussions:- Explain what is the average completion time of all jobs

Explain a marketing plan, You have a novel product idea and a working proto...

You have a novel product idea and a working prototype for floating fishing pliers. You use an extrusion process to manufacture the pliers, and your family assembles them out of you

Explain assess the strategy of wal-mart in china, Give your assessment of t...

Give your assessment of the requirements for Cuba to develop a free and independent trade union. Determine if it is essential for a free society. Assess the strategy of Wal-Mart

Manager case, In the table given below the Distribution Manager is expected...

In the table given below the Distribution Manager is expected to service these DCs as per the demands placed. If the actual sales after completing week one is as follows, what woul

Why jobs needed to produce the shopping carts, A company that makes shoppin...

A company that makes shopping carts for supermarkets and other stores recently purchased some new equipment that reduces the labour content of the jobs needed to produce the shoppi

Describe the types of evidence that you would look for, Discuss the types o...

Discuss the types of evidence that you would look for in order to determine whether a needs analysis has been improperly conducted. How would you know? Why?

Explain what the average number of accounts payable checks, An accounts pay...

An accounts payable manager processes 200 checks per day with an average processing time of 15 working days. What is the average number of accounts payable checks being processed i

Explain insufficient to handle the increased workload, A company that produ...

A company that produces pleasure boats has decided to expand one of its lines. Current facilities are insufficient to handle the increased workload, so the company is considering t

Describe confidence interval calculator, Practical Application Scenario ...

Practical Application Scenario To complete this scenario, use the Confidence Interval Calculator and the Area Gas Prices %u2013 Random Sample documents, provided in the Resource

Explain how will you account for any wastage, You are the branch operations...

You are the branch operations manager for a leading manufacturing company. The following are the bill of materials (BOM), Master Production Schedule, and Inventory Record Sheet for

Effect on costs and employer, Effect on Costs and Employer: Accidents  are...

Effect on Costs and Employer: Accidents  are harmful when  we take into account  the business  of the  concern.  It adds to the  costs of production  directly  as well  as  indire

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd