Explain what assignment minimizes the total traffic flow, Operation Management

Assignment Help:

Please kindly show step by step solutions.

Six processes are to be laid out in six areas along a long corridor at Linda Babat Accounting Services. The distance between adjacent work centres is 40 feet. The number of trips between work centres is given in the following table-

Trips between Processes
From A B C D E F
A 18 25 73 12 54
B 96 23 31 45
C 41 22 20
D 19 57
E 48
F

a) Assign the processes to the work areas in a way that minimizes the total flow, using a method that places processes with highest flow adjacent to each other.

b) What assignment minimizes the total traffic flow?


Related Discussions:- Explain what assignment minimizes the total traffic flow

Explain coupon rate with semi-annual coupon payments, Genny, Inc. bonds hav...

Genny, Inc. bonds have a 9% coupon rate with semi-annual coupon payments. They have 9 1/2 years to maturity and a par value of $1,000. Compute the value of Genny's bonds if investo

Explain streaming video, Streaming Video: The Job Market for Graduates DQ V...

Streaming Video: The Job Market for Graduates DQ Video Document Discussion Topic What is your opinion of the interviewing tips given in the video? Which tips of your own would you

Find the probability of event, The probability of Event 1 is P and the prob...

The probability of Event 1 is P and the probability of Event 2 is (1-p),for what values of P would you choose A?B?C? Values in the table are payoffs. Choice /Event Event 1 Event2

Why conduct training in management, Instructors recommended to conduct trai...

Instructors recommended to conduct training in management

Calculation, monthly production time for tep.

monthly production time for tep.

Productivity -numerically defined, Productivity -Numerically Defined T...

Productivity -Numerically Defined Total factor productivity (TFP) = Pt = Ot/(L+C+R+Q)  Partial factor productivity (PFP) = Ot/L or C or Ot/a combination of  inputs   Pt

Explain middle manager helping to implement a new corporate, You are a midd...

You are a middle manager helping to implement a new corporate cost-cutting strategy, and your meeting scepticism, resistance, and in some cases, outright hostility from your subord

Depict the project network using aon, Task time estimates for a production ...

Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows: Activity Time (in hours) Immediate Predecessors A 6.0 B 7.2 C 5.0 A D 6.0

Explain services from goods, Which of the following is not a characteristic...

Which of the following is not a characteristic that distinguishes services from goods? Service jobs are unskilled A service is intangible Services are perishable Services are heter

Reference Book, Hello Sir, This is Riddhi Trivedi I, am Faculty of Commerge...

Hello Sir, This is Riddhi Trivedi I, am Faculty of Commerge and Management. Subject is there Materials & Production Management, but i want a perfect reference book where i get all

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd