Explain what additional steps should the quality assurance, Operation Management

Assignment Help:

A quality analyst wants to construct a sample mean chart for controlling a packaging process. He knows from past experience that the process standard deviation is two ounces. Each day last week, he randomly selected four packages and weighed each. The data from that activity appears below.

Weight
Day Package 1 Package 2 Package 3 Package 4
Monday 23 22 23 24
Tuesday 23 21 19 21
Wednesday 20 19 20 21
Thursday 18 19 20 19
Friday 18 20 22 20

(a) Calculate upper and lower control limits for both sample means and ranges.

(b) Is this process in control? Explain--a simple Yes or No is insufficient.

(c) What additional steps should the quality assurance team take?


Related Discussions:- Explain what additional steps should the quality assurance

What is need of computer aided manufacturing to operations, Q. What is need...

Q. What is need of computer aided manufacturing to manufacturing operations? Computer aided manufacturing (CAM) automates production for illustration programmable and robotic p

Line balancing, what is line balancing and what happens if it doesn''t exis...

what is line balancing and what happens if it doesn''t exist?

Lean Synchronisation, Examples of organisations that practice Lean synchron...

Examples of organisations that practice Lean synchronisations

What is the number of orders per year if the manager uses, A flower shop us...

A flower shop uses 800 clay pots a month. The pots are purchased at $2 each. Annual carrying costs are estimated at $0.60 per pot per year and ordering costs are $20 per order. The

Explain the management-research question hierarchy, Build the management-re...

Build the management-research question hierarchy for penton media

Explain golden rules apply to all projects, Consider how these 10 Golden Ru...

Consider how these 10 Golden Rules apply to all projects and apply three of them to your project.

Determine the full study sample size, 1. An element of work has been measur...

1. An element of work has been measured 6 times, with the following results (units of 0.01 minutes): 18, 20, 19, 21, 19, 22. What should be the full-study sample size?  Answer:

Depict a layout for the assembly operation, Base on the case study: Weldon ...

Base on the case study: Weldon Hand Tools; Design a layout for the assembly operation (to include the fly press work) including the tasks to be performed at each part of the system

Explain procurement management, Which of the nine knowledge areas defined i...

Which of the nine knowledge areas defined in the Project Management Body of Knowledge includes the activities of generating, collecting, distributing, storing, retrieving and dispo

Explain factors contributing to competitive rivalry include, Factors contri...

Factors contributing to competitive rivalry include A) The corporate attitudes toward marketing strategies B) Nature of the product and homogeneity of market C) The suppor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd