Explain time-phased product structure, Operation Management

Assignment Help:

The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make X, 2 weeks to make Y, and 1 week to make Z. A) Construct a product structure, identify all levels, parents, and components. b) Prepare a time-phased product structure


Related Discussions:- Explain time-phased product structure

Five forms of waste within manufacturing organisations, Describe FIVE forms...

Describe FIVE forms of waste within manufacturing organisations that lean process improvement aims to eliminate. Inventory (all components, work in progress and ended produ

Hospitality industry , Can I have a process strategy matrix , which has 5...

Can I have a process strategy matrix , which has 5 key performance objectives, people processes, technology and information in one of the accor chain hotel?

Explain what are the steps for process improvement, What are the steps for ...

What are the steps for process improvement? And examples of companies that have used this.

Describe the correlation between realization factor, Can anyone please expl...

Can anyone please explain the correlation between Realization Factor, Capacity, Utilization, and Rolled Throughput Yield, please? Equations would also be nice.

Explain capacity is the maximum rate of output of a process, 1. Capacity is...

1. Capacity is the maximum rate of output of a process. 2. Capacity decisions should be made separate from strategic decisions. 3. Capacity can be expressed by output or inpu

Explain critical path, Explain Critical Path. This is that sequence of ...

Explain Critical Path. This is that sequence of activities that decide the complete project duration. Critical Path is formed by critical activities. This path consumes maximum

Describe the leadership style, Discuss the leadership style, visionary, coa...

Discuss the leadership style, visionary, coaching or afflictive, that would be the best in the given situation below and provide support for your choice. 1) A non-profit agency wis

Competence - customer satisfaction and service quality, Competence - Custom...

Competence - Customer Satisfaction and Service Quality Means possession of the required skills and knowledge to perform the service. It involves: knowledge and skill of the c

Explain what are the pros and cons of the control system, What kind of cont...

What kind of control systems are being used to measure the performance of hospitals and their different kinds of employees such as doctors and nurses? What are the pros and cons

Explain the generic product development process, Describe the generic produ...

Describe the generic product development process described in this chapter. How does this process change for "technology push" products?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd