Explain the unit hydrograph method, Civil Engineering

Assignment Help:

Q.- Explain the Unit hydrograph Method for estimation of peak flood discharge in a river.

Ans.-

Unit hydrograph Method

A hydrograph is a representation of hydraulic characteristic of river discharge . A point on the hydrograph shows the available discharge at that time . The area under the hydrograph came between any two intervals of time say t1 to t2 shows the volume of water that has passed the measuring point in time t1 to t2.

A concept of unit hydrograph is based on the fact that for a given point in a given stream of a basin the storm of different intensity but of the same unit duration produces hydrograph of surface run off of equal length of time and of the similar shape. The ordinates are proportional to the magnitude of rain fall with the assumption that the rain fall is distributed uniformly over the entire area.

The unit hydrograph is thus defined as the hydrograph which is produced by a rainfall of given duration uniformly distributed over the catchment and which produces a direct run off volume of a unit depth of 1 cm over the entire catchment area.

Hydrograph method consists of constructing a unit hydrograph or distribution graph for the catchment and then by use of given rainfall data, the hydro graph runoff is calculated.


Related Discussions:- Explain the unit hydrograph method

Kicker of reinforced concrete cantilever retaining walls, Q. Kicker of rein...

Q. Kicker of reinforced concrete cantilever retaining walls located at the position of largest moment and shear force - why? Generally for reinforced concrete cantilever retai

Conturing, radial line method practical

radial line method practical

Define fatigue load test of shock transmission unit, Define Fatigue load te...

Define Fatigue load test of shock transmission unit? This test was carried out for 100,000 cycles for maximum capacity of STU, assuming the worst case that the 'Lock Up Load' i

Abc, uses concrete slump test

uses concrete slump test

Concrete, What is compacting factor

What is compacting factor

WATER SUPPLY, THE DESIGN PERIOD AVERAGE DAILY DEMAND CALCULATE. THE DESIGN ...

THE DESIGN PERIOD AVERAGE DAILY DEMAND CALCULATE. THE DESIGN DEMAND FOR THE WATER RETICULATION OR DISTRIBUTION PERIOD.

Levelling, principle of direct levelling

principle of direct levelling

Surveying, tracing paper method for solving three point problem?

tracing paper method for solving three point problem?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd