Explain the statements about the critical path method, Civil Engineering

Assignment Help:

1. Determine a network diagram method that uses only finish-to-start relationships and may use dummy activities to define logical relationships. 

2.  Precedence diagramming is best described as:

3.  Explain the statements about the Critical Path Method?

Solution: The Arrow Diagramming Method is the only scheduling technique that employs dummy activities.

2. Precedence diagramming is also called Activity on Node (AON) diagramming.

3.  I.  A network analysis technique used to predict project duration by analyzing which sequence of activities has the least amount of schedule flexibility (float)

II. Early dates are calculated by a forward pass using a specified start date

III. Late dates are calculated by a backwards pass using a specified completion date (usually the early finish date)


Related Discussions:- Explain the statements about the critical path method

What do you mean by stock verification sheets, Q. What do you mean by Stock...

Q. What do you mean by Stock Verification Sheets? The proper custody and accountal of stores is the prime duty and function of an executive or the stockholder. To ensure this v

Example for productivity analysis and improvement, Example for Productivity...

Example for Productivity Analysis and Improvement An excavator with a bucket capacity of 3-yd 3 has a standard production rate of 2,160-yd 3 for an 8-hour day.  The job site

Define pavement design - transportation, Define Pavement Design - Transport...

Define Pavement Design - Transportation 1. Asphalt surface a. Estimate Design Traffic b. Determine the Structural Number (SN) for the given traffic, roadway, and soil cha

Define hammer efficiency and coefficient of restitution, Q. Define Hammer e...

Q. Define Hammer efficiency and coefficient of restitution? Hammer efficiency refers to ratio of kinetic energy of hammer to the rated energy (or potential energy). Basically i

Pavement drainage, Pavement Drainage: Water enters the pavement layer...

Pavement Drainage: Water enters the pavement layers through cracks, joints and open spaces in the pavement surface. The water reaches the soil sub-grade on which the pavement

Tests on cement, Tests on Cement: The following tests are conducted o...

Tests on Cement: The following tests are conducted on cement in a project site: Setting Time Initial setting time Final setting time Compressive Streng

Determine the ground elevation, The trigonometric levelling from the survey...

The trigonometric levelling from the surveyor's notes is shown below. The ground elevation of T (ft) is most nearly: Solution:  The elevation of point P can be found from: E

Surveying, Distance ABC was measured with a 30m. Chain tested and found to ...

Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd