Explain the statements about the critical path method, Civil Engineering

Assignment Help:

1. Determine a network diagram method that uses only finish-to-start relationships and may use dummy activities to define logical relationships. 

2.  Precedence diagramming is best described as:

3.  Explain the statements about the Critical Path Method?

Solution: The Arrow Diagramming Method is the only scheduling technique that employs dummy activities.

2. Precedence diagramming is also called Activity on Node (AON) diagramming.

3.  I.  A network analysis technique used to predict project duration by analyzing which sequence of activities has the least amount of schedule flexibility (float)

II. Early dates are calculated by a forward pass using a specified start date

III. Late dates are calculated by a backwards pass using a specified completion date (usually the early finish date)


Related Discussions:- Explain the statements about the critical path method

Wmm, why use wmm upon gsb can be laid dbm directly upon gsb

why use wmm upon gsb can be laid dbm directly upon gsb

Assignment help job, Can I apply for "online assignment help job" for civil...

Can I apply for "online assignment help job" for civil engineering,physics & maths etc?

Void ratio and dry density of a soil, Q. Define water content, void ratio ...

Q. Define water content, void ratio and dry density of a soil. If wet density of a soil is 1.9 gm per cm at a moisture content of 24%, what will be its dry density?  Ans. - W

Expansion joints in basement, I have building 50 m * 53 m 3 floors without ...

I have building 50 m * 53 m 3 floors without expansion joint in basement what are opinion please ? thanks

Inspection of girder bridge, Q. As an AEN in charge, what inspection will...

Q. As an AEN in charge, what inspection will you under taken at the time of inspection of Girder Bridge 3 x 60 feet. Please explain the important items to be o

Leveling, cooke''s reversable level

cooke''s reversable level

Ranging, describe reciprocal ranging

describe reciprocal ranging

Define the hazard ranking system (hrs), Define the Hazard Ranking system (H...

Define the Hazard Ranking system (HRS) - A procedure for ranking uncontrolled hazardous waste sites in terms of the potential threat based upon the containment of the route of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd