Explain the statements about the critical path method, Civil Engineering

Assignment Help:

1. Determine a network diagram method that uses only finish-to-start relationships and may use dummy activities to define logical relationships. 

2.  Precedence diagramming is best described as:

3.  Explain the statements about the Critical Path Method?

Solution: The Arrow Diagramming Method is the only scheduling technique that employs dummy activities.

2. Precedence diagramming is also called Activity on Node (AON) diagramming.

3.  I.  A network analysis technique used to predict project duration by analyzing which sequence of activities has the least amount of schedule flexibility (float)

II. Early dates are calculated by a forward pass using a specified start date

III. Late dates are calculated by a backwards pass using a specified completion date (usually the early finish date)


Related Discussions:- Explain the statements about the critical path method

Pressure distribution under rigid and flexible footings, Pressure distribut...

Pressure distribution under rigid and flexible footings For rigid and thick footings, pressure distribution under the footings is generally presumed to be linear. If symmetric

Explain the geophysical methods, Why are undisturbed samples needed? Descri...

Why are undisturbed samples needed? Describe any one procedure of obtaining undisturbed samples for a multi-storeyed building project. For what purpose are geophysical methods u

Water or hydraulic horsepower (whp), Water Or Hydraulic Horsepower (whp) ...

Water Or Hydraulic Horsepower (whp) The work performed by a pump is a function of the head added by the pump (h A ), the flow rate required (Q) and the mass of the fluid (accou

Define marine growth - underwater inspection of bridge, Define Marine growt...

Define Marine growth - underwater inspection of bridge? Generally, in seawater marine growth takes place. Acid generated by the marine growth attacks concrete. This can lead to

Concrete, Determine the quantity of materials required per batch and probab...

Determine the quantity of materials required per batch and probable output from a concrete mixing plant of 1200lts capacity. The design per 1000lts of mixed concrete is as follows

Determine the stresses within the rod, Determine the stresses within the ro...

Determine the stresses within the rod: Two parallel walls are stayed together through a steel rod of 5 cm diameter passing through metal plates and nuts at both ends. The nuts

Contractor to continue concreting works, Question If on-site slump test fai...

Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by

Flash point test, Flash Point Test: The flash point is the temperatur...

Flash Point Test: The flash point is the temperature at which the bitumen gives off vapours which ignite in the presence of a flame. The flash point temperature gives the cri

Main problems related with prestressed concrete piles, Question What ar...

Question What are main problems related with prestressed concrete piles ? Answer Origin of Daido piles comes from Japan where these prestressed actual piles are used

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd