Explain the statements about the critical path method, Civil Engineering

Assignment Help:

1. Determine a network diagram method that uses only finish-to-start relationships and may use dummy activities to define logical relationships. 

2.  Precedence diagramming is best described as:

3.  Explain the statements about the Critical Path Method?

Solution: The Arrow Diagramming Method is the only scheduling technique that employs dummy activities.

2. Precedence diagramming is also called Activity on Node (AON) diagramming.

3.  I.  A network analysis technique used to predict project duration by analyzing which sequence of activities has the least amount of schedule flexibility (float)

II. Early dates are calculated by a forward pass using a specified start date

III. Late dates are calculated by a backwards pass using a specified completion date (usually the early finish date)


Related Discussions:- Explain the statements about the critical path method

Write short notes on numerical rating of bridges, Q. Write short notes on N...

Q. Write short notes on Numerical rating of Bridges? In the numerical rating system, the condition of a bridge is represented by a number consisting eight digits. This eight di

Hydrolic, how can i caculate volicity and tank capacity ?

how can i caculate volicity and tank capacity ?

SURVEYING II LAB, Explain Designation of bearings. Calculate included angle...

Explain Designation of bearings. Calculate included angle from bearings

Residual stresses in steel after welding, Q. Residual stresses in steel aft...

Q. Residual stresses in steel after welding? Considerable residual stresses are persuaded in connecting steel members after welding operation. Local temperature of steel where

How do you determine specific gravity of cement, Cement is usually purchase...

Cement is usually purchased as a powdery substance that is mixed with sand, aggregate, gravel, and water to form concrete. As the cement itself is usually a powder, it is hard to c

Explain procedure of remote sensing in satellites, Q. Explain procedure of ...

Q. Explain procedure of remote sensing in Satellites? Satellites used for remote sensing are of two types, viz, geostationary and polar orbiting. Geostationary stationary satel

Underwater problems in bridge construction, Q. Underwater problems in bridg...

Q. Underwater problems in bridge construction? The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as binding

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd