Explain the statements about the critical path method, Civil Engineering

Assignment Help:

1. Determine a network diagram method that uses only finish-to-start relationships and may use dummy activities to define logical relationships. 

2.  Precedence diagramming is best described as:

3.  Explain the statements about the Critical Path Method?

Solution: The Arrow Diagramming Method is the only scheduling technique that employs dummy activities.

2. Precedence diagramming is also called Activity on Node (AON) diagramming.

3.  I.  A network analysis technique used to predict project duration by analyzing which sequence of activities has the least amount of schedule flexibility (float)

II. Early dates are calculated by a forward pass using a specified start date

III. Late dates are calculated by a backwards pass using a specified completion date (usually the early finish date)


Related Discussions:- Explain the statements about the critical path method

Kings of the world, i want to know more about civil engineering

i want to know more about civil engineering

Mechanism of taking up loads for concrete paving blocks, Mechanism of takin...

Mechanism of taking up loads for concrete paving blocks  Paving for concrete blocks comprises closely packed paving blocks in pre-determined patterns and tiny joint spaces bet

GNS 201, explain registers and factors influencing them

explain registers and factors influencing them

Define the pressure on a vertical plane, Define the Pressure on a vertical ...

Define the Pressure on a vertical plane Fluid pressure increases linearly with increasing depth. The average pressure on a vertical plane occurs at the average vertical depth.

Benchmark, 1. Where permanent bench of india located ? 2. use of Permanent ...

1. Where permanent bench of india located ? 2. use of Permanent BenchMark ?

Define abrasion of steel structures - inspection of bridge, Define Abrasion...

Define Abrasion of steel structures? Abrasion of steel structures can generally be recognised by a worn, smooth, polished appearance of the surface.  Abrasion is caused by cont

Define the hazard ranking system (hrs), Define the Hazard Ranking system (H...

Define the Hazard Ranking system (HRS) - A procedure for ranking uncontrolled hazardous waste sites in terms of the potential threat based upon the containment of the route of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd