Explain the statements about the critical path method, Civil Engineering

Assignment Help:

1. Determine a network diagram method that uses only finish-to-start relationships and may use dummy activities to define logical relationships. 

2.  Precedence diagramming is best described as:

3.  Explain the statements about the Critical Path Method?

Solution: The Arrow Diagramming Method is the only scheduling technique that employs dummy activities.

2. Precedence diagramming is also called Activity on Node (AON) diagramming.

3.  I.  A network analysis technique used to predict project duration by analyzing which sequence of activities has the least amount of schedule flexibility (float)

II. Early dates are calculated by a forward pass using a specified start date

III. Late dates are calculated by a backwards pass using a specified completion date (usually the early finish date)


Related Discussions:- Explain the statements about the critical path method

Kerb overflow weirs – horizontal bars vs. vertical bars, Q. Kerb overflow w...

Q. Kerb overflow weirs – horizontal bars vs. vertical bars? Overflow weirs must be provided for steep roads (longitudinal gradient>5%), flat roads (longitudinal gradient Ess

Soil mechanics, what is the total volume required for the gravel material o...

what is the total volume required for the gravel material of 6.5mx2314mx0.1m with a relative density of 2.919 and a loose bulk density of 1668kg/m3

What do you understand by percolation of water, Q. What do you understand b...

Q. What do you understand by Percolation of water? Percolation of water into the ground or embankment takes place, causing rise in water table and / or saturation of the body.

Estimate the net present worth - construction management, Three alternative...

Three alternatives are being considered for improving a street intersection.The annual dollar savings on account of the improvement is shown below.  Assume that the intersection wi

Main function of followers in driven h-piles, Question What is main fun...

Question What is main function of followers in driven H-piles ? Answer A follower is an extension between pile head and hammers which transfers blow to pile in which

Design a 10 unit rapid sand filter system, Design a 10 unit rapid sand filt...

Design a 10 unit rapid sand filter system for a flow of 6.3 MGD with a filtration rate of 2 gpm/sq ft. and an L: W ratio of 1.3.   Design flow (Q) = 6.3 MGD = 6.3x106 gpd =

Determine the final volume of the compacted soil, 30,000-yd 3 of banked so...

30,000-yd 3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite.  The soil has 28% swell and shrinkage of 18%.  The final volume of the compacted so

Compute the maximum allowable concentrated live load, Given for the section...

Given for the section shown in Figure, M * = 250 kNm, f sy = 500 MPa and f c ′ = 25 MPa. Compute A st and (if necessary) A sc . You may assume that eac

Explain the ion exchange water softening, Explain the Ion Exchange water So...

Explain the Ion Exchange water Softening Softening is usually done using a resin (natural or synthetic long chain chemical with a sodium ion attached). When water containing ha

Necessity of pile tip cover for rock-socketed H-piles, Q. Necessity of pile...

Q. Necessity of pile tip cover for rock-socketed H-piles? In current practice concrete cover is generally provided at the pile tips of pre-bored H-piles socketed in rock. The o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd