Explain the statements about construction contract process, Civil Engineering

Assignment Help:

Explain the Statements about the Construction Contract Process

I. Surety bond assures the project owner a guarantee of funds equivalent to a promissory note. The surety bond is a promise to pay the owner a certain amount if the contractor fails in fulfilling the terms of a contract.

II. Performance bond is a surety bond issued by an insurance company or a bank to guarantee satisfactory completion of a project by a contractor. Performance bonds are issued upon Contract award and cost approximately 0.50% to 1.25% of the total contract value.

III. Builder's risk insurance is a special type of property insurance which indemnifies against damage to buildings while they are under construction. Risk insurance of Builder is coverage that protects a person's or an organization's insurable interest in materials, fixtures and/or equipment being utilized in the construction or renovation of a building or structure should those items sustain physical loss or damage from a covered cause

IV. A bid bond is issued as part of a bidding process by the surety to the project owner, to assurance that the winning bidder will undertake the contract under the terms at that they bid. The cash deposit is subject to full or partial forfeiture if the winning contractor fails to either execute the contract or provide the required performance and/or payment bonds. The bid bond assures and assurance that should the bidder be doing well, the bidder will execute the contract and provide the required surety bonds.

V. Bonds are not insurance. Bonds are a guarantee to pay made by a cosigner who is liable only if the principal fails to discharge the obligations under the Contract.


Related Discussions:- Explain the statements about construction contract process

Analyse the state of stress, Analyse the state of stress: For the cros...

Analyse the state of stress: For the cross-section shown in above figure, let us take b = 100 mm, d = 300 mm and M = 9 × 10 7 N mm and Q = 18 × 10 4 N and analyse the state

What is the meaning of untensioned reinforcement, Supplementary or Untensi...

Supplementary or Untensioned Reinforcement It is that reinforcement, provided in prestressed concrete member, which is not provided in a stretched condition like tendons.

Use single lock nuts or double lock nuts, Question In linking fenders t...

Question In linking fenders to pier organizations, would single lock nuts or double lock nuts be used? Answer In pier structures connection offenders to piers is a

Explain types of tiles, Q. Explain Types Of Tiles? Different types of t...

Q. Explain Types Of Tiles? Different types of tiles available in the market for floor and walls & dado are as under - 1. Glazed tiles , 2. Ceramic tiles , 3. Granit

Railway drawings, section of railway tracks in india ,all dimensions in met...

section of railway tracks in india ,all dimensions in meters

Define steel substructure - underwater inspection of bridge, Define Steel s...

Define Steel substructure - underwater inspection of bridge? Steel is used as a structural material and as external protective cladding on concrete foundation elements. Steel f

State the short-term deflections, State the short-term deflections If  ...

State the short-term deflections If  short-term deflections are considered, the instantaneous deflection due to design loads may be calculated using elastic analysis based on t

Define special considerations for underwater inspection, Define Special con...

Define Special considerations for underwater inspection? Once a diver enters the water, there environment changes completely. Visibility decreases and is often reduced to near

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd