Explain the statements about construction contract process, Civil Engineering

Assignment Help:

Explain the Statements about the Construction Contract Process

I. Surety bond assures the project owner a guarantee of funds equivalent to a promissory note. The surety bond is a promise to pay the owner a certain amount if the contractor fails in fulfilling the terms of a contract.

II. Performance bond is a surety bond issued by an insurance company or a bank to guarantee satisfactory completion of a project by a contractor. Performance bonds are issued upon Contract award and cost approximately 0.50% to 1.25% of the total contract value.

III. Builder's risk insurance is a special type of property insurance which indemnifies against damage to buildings while they are under construction. Risk insurance of Builder is coverage that protects a person's or an organization's insurable interest in materials, fixtures and/or equipment being utilized in the construction or renovation of a building or structure should those items sustain physical loss or damage from a covered cause

IV. A bid bond is issued as part of a bidding process by the surety to the project owner, to assurance that the winning bidder will undertake the contract under the terms at that they bid. The cash deposit is subject to full or partial forfeiture if the winning contractor fails to either execute the contract or provide the required performance and/or payment bonds. The bid bond assures and assurance that should the bidder be doing well, the bidder will execute the contract and provide the required surety bonds.

V. Bonds are not insurance. Bonds are a guarantee to pay made by a cosigner who is liable only if the principal fails to discharge the obligations under the Contract.


Related Discussions:- Explain the statements about construction contract process

Application of levelling, how do I draw sections(longitudinal and cross sec...

how do I draw sections(longitudinal and cross sections)?

#title, how to convewrt wcb into rcb

how to convewrt wcb into rcb

Higway engineering, Ask question Design the pavement by group index method ...

Ask question Design the pavement by group index method for heavy traffic using following subgrade data Soil passing 75micron sieve =65%,liquid limit =40%plastic limit =20% #Min

Hydraulics, What is the head loss in 350 ft of 12 inch diameter 20 years ol...

What is the head loss in 350 ft of 12 inch diameter 20 years old cast iron pipe carrying 1.2 MGD?

Concrete, types of concrete and its uses

types of concrete and its uses

What do you mean by base fixity, Q. What do you mean by Base fixity? B...

Q. What do you mean by Base fixity? Base fixity When structures such as portal frames are associated to the base foundation, engineers have to determine the degree of fix

Verify the coefficient of elastic uniform compression, Verify the coefficie...

Verify the coefficient of elastic uniform compression if a vibration test on a concrete block of 1 m cube gave a resonant frequency of 36 Hz in vertical vibration. The weight of

Amount of borrow needed to bring area to elevation of 90-ft, Surveyed eleva...

Surveyed elevations are shown in Figure for a 50' x 50' grid at a proposed parking lot location. The amount of borrow needed to bring the area to an elevation of 90-ft is most near

WMM, gradation of materials used in wet mix macadam

gradation of materials used in wet mix macadam

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd