Explain the statements about construction contract process, Civil Engineering

Assignment Help:

Explain the Statements about the Construction Contract Process

I. Surety bond assures the project owner a guarantee of funds equivalent to a promissory note. The surety bond is a promise to pay the owner a certain amount if the contractor fails in fulfilling the terms of a contract.

II. Performance bond is a surety bond issued by an insurance company or a bank to guarantee satisfactory completion of a project by a contractor. Performance bonds are issued upon Contract award and cost approximately 0.50% to 1.25% of the total contract value.

III. Builder's risk insurance is a special type of property insurance which indemnifies against damage to buildings while they are under construction. Risk insurance of Builder is coverage that protects a person's or an organization's insurable interest in materials, fixtures and/or equipment being utilized in the construction or renovation of a building or structure should those items sustain physical loss or damage from a covered cause

IV. A bid bond is issued as part of a bidding process by the surety to the project owner, to assurance that the winning bidder will undertake the contract under the terms at that they bid. The cash deposit is subject to full or partial forfeiture if the winning contractor fails to either execute the contract or provide the required performance and/or payment bonds. The bid bond assures and assurance that should the bidder be doing well, the bidder will execute the contract and provide the required surety bonds.

V. Bonds are not insurance. Bonds are a guarantee to pay made by a cosigner who is liable only if the principal fails to discharge the obligations under the Contract.


Related Discussions:- Explain the statements about construction contract process

Doors, types of doors with there prices

types of doors with there prices

Necessity of air valves in pressurized pipelines, Q. Necessity of air valve...

Q. Necessity of air valves in pressurized pipelines? Air valves are broadly categorized into two major types: single air valves and double air valves. Single air valve comprise

Slope IN Civil, How to calculate the slope in civil engineering?????

How to calculate the slope in civil engineering?????

Show constituents of bricks, Q. Show Constituents of bricks? The brick ...

Q. Show Constituents of bricks? The brick is manufactured out of special. Type of brick earth consisting of clay and sand the proportion of clay and earth should be such that w

Concrete compaction in piling works, Question What is the reason that v...

Question What is the reason that vibrators not used in concrete compaction in piling works ? Answer Concrete for piles must be a high-slump self-compacting mix that i

Define the cavitation - underwater inspection of bridge, Define the Cavitat...

Define the Cavitation - underwater inspection of bridge? Cavitation damage is caused by repeated impact forces caused by collapse of vapour bubbles in rapidly flowing water. Th

Borrow pits - embankment construction, Borrow Pits Borrow pits are th...

Borrow Pits Borrow pits are the locations from where the embankment soil is obtained. The following guidelines govern the location of borrow pits : (a) They should be pref

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd