Explain the statements about construction contract process, Civil Engineering

Assignment Help:

Explain the Statements about the Construction Contract Process

I. Surety bond assures the project owner a guarantee of funds equivalent to a promissory note. The surety bond is a promise to pay the owner a certain amount if the contractor fails in fulfilling the terms of a contract.

II. Performance bond is a surety bond issued by an insurance company or a bank to guarantee satisfactory completion of a project by a contractor. Performance bonds are issued upon Contract award and cost approximately 0.50% to 1.25% of the total contract value.

III. Builder's risk insurance is a special type of property insurance which indemnifies against damage to buildings while they are under construction. Risk insurance of Builder is coverage that protects a person's or an organization's insurable interest in materials, fixtures and/or equipment being utilized in the construction or renovation of a building or structure should those items sustain physical loss or damage from a covered cause

IV. A bid bond is issued as part of a bidding process by the surety to the project owner, to assurance that the winning bidder will undertake the contract under the terms at that they bid. The cash deposit is subject to full or partial forfeiture if the winning contractor fails to either execute the contract or provide the required performance and/or payment bonds. The bid bond assures and assurance that should the bidder be doing well, the bidder will execute the contract and provide the required surety bonds.

V. Bonds are not insurance. Bonds are a guarantee to pay made by a cosigner who is liable only if the principal fails to discharge the obligations under the Contract.


Related Discussions:- Explain the statements about construction contract process

Theory on the horizontal reactions of portal frames, Determine the horizont...

Determine the horizontal abutment reaction of a rectangular portal frame under increasing central concentrated load

Determine the required stirrup size and spacing requirement, A rectangular ...

A rectangular concrete beam is subjected to a factored design shear force of 200 kips.  For the beam shown below, determine the required stirrup size and spacing requirement. H = 3

Determine the preliminary settlement analysis, Preliminary settlement analy...

Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an  ultimate  settlement  of  250 mm.  The average pressure increment in the clay stra

#title, Explain couple. What are the characteristics of a couple?

Explain couple. What are the characteristics of a couple?

Timber, uses of timber in civil engineering field and its physical state an...

uses of timber in civil engineering field and its physical state and chemical formula or symbol?

Reason of skin reinforcement for deep beams, Question What is reason of sk...

Question What is reason of skin reinforcement for deep beams ? Answer In BS8110, it declares that secondary reinforcement have to be provided for beams greater than 750mm deep

Roads, how to calculate number of passes while compaction

how to calculate number of passes while compaction

Backward and forward curved vanes in pumps, Backward curved vanes vs. forwa...

Backward curved vanes vs. forward curved vanes in pumps  Power of a pump is related to discharge as follows: Power = k 1 Q + (k 2 Q 2 / tan A) Where K 1 and K 2 are

Cross Section Method, Cut and Fill Calculation Using Cross Section Method

Cut and Fill Calculation Using Cross Section Method

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd