Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Explain the Statements about the Construction Contract Process
I. Surety bond assures the project owner a guarantee of funds equivalent to a promissory note. The surety bond is a promise to pay the owner a certain amount if the contractor fails in fulfilling the terms of a contract.
II. Performance bond is a surety bond issued by an insurance company or a bank to guarantee satisfactory completion of a project by a contractor. Performance bonds are issued upon Contract award and cost approximately 0.50% to 1.25% of the total contract value.
III. Builder's risk insurance is a special type of property insurance which indemnifies against damage to buildings while they are under construction. Risk insurance of Builder is coverage that protects a person's or an organization's insurable interest in materials, fixtures and/or equipment being utilized in the construction or renovation of a building or structure should those items sustain physical loss or damage from a covered cause
IV. A bid bond is issued as part of a bidding process by the surety to the project owner, to assurance that the winning bidder will undertake the contract under the terms at that they bid. The cash deposit is subject to full or partial forfeiture if the winning contractor fails to either execute the contract or provide the required performance and/or payment bonds. The bid bond assures and assurance that should the bidder be doing well, the bidder will execute the contract and provide the required surety bonds.
V. Bonds are not insurance. Bonds are a guarantee to pay made by a cosigner who is liable only if the principal fails to discharge the obligations under the Contract.
Maintenance of Drainage: Maintenance of drainage will ensure that the run-off is taken away from the runway efficiently. The side ditches and buried pipes should be cleaned r
Rolling - Binder: The layer thickness is 40-50 mm. Rolling is done in three stages : Initial Rolling By 80-100 kN smooth wheeled roller. Intermediate Rolling B
Movement accommodation factor is normally specified by manufacturers of joint sealants for designers to design dimension of joints. It is stated as the total movement that a joint
A nearly horizontal, 12 ft wide rectangular channel carries 60 cfs at a depth of 3.0 ft. The width of the channel is smoothly contracted to 6 ft at the downstream section. (a) Dete
Question What is designing level of landings in piers? Answer Landings are designed as resting place for passengers throughout berthing and deserting of vessels. I
whether the wall has adequate sliding resistance
Q. Necessity of pile tip cover for rock-socketed H-piles? In current practice concrete cover is generally provided at the pile tips of pre-bored H-piles socketed in rock. The o
concrete strength
what are the necessary data required for foundation recommendation other than SPT value ? why can''t we go for SPT value alone?
A retaining wall, 4.5 m high, retains a soil with c = 2 N/cm 2 , φ = 30° and g = 20 kN/m 3 , with horizontal surface level with the top of the wall. The backfill carries a surch
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd