Explain the statements about construction contract process, Civil Engineering

Assignment Help:

Explain the Statements about the Construction Contract Process

I. Surety bond assures the project owner a guarantee of funds equivalent to a promissory note. The surety bond is a promise to pay the owner a certain amount if the contractor fails in fulfilling the terms of a contract.

II. Performance bond is a surety bond issued by an insurance company or a bank to guarantee satisfactory completion of a project by a contractor. Performance bonds are issued upon Contract award and cost approximately 0.50% to 1.25% of the total contract value.

III. Builder's risk insurance is a special type of property insurance which indemnifies against damage to buildings while they are under construction. Risk insurance of Builder is coverage that protects a person's or an organization's insurable interest in materials, fixtures and/or equipment being utilized in the construction or renovation of a building or structure should those items sustain physical loss or damage from a covered cause

IV. A bid bond is issued as part of a bidding process by the surety to the project owner, to assurance that the winning bidder will undertake the contract under the terms at that they bid. The cash deposit is subject to full or partial forfeiture if the winning contractor fails to either execute the contract or provide the required performance and/or payment bonds. The bid bond assures and assurance that should the bidder be doing well, the bidder will execute the contract and provide the required surety bonds.

V. Bonds are not insurance. Bonds are a guarantee to pay made by a cosigner who is liable only if the principal fails to discharge the obligations under the Contract.


Related Discussions:- Explain the statements about construction contract process

Concrete, What is Under vibration of fresh concrete?

What is Under vibration of fresh concrete?

Calculate the final volume of the compacted soil, 1. 130,000-yd 3 of banke...

1. 130,000-yd 3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite. The soil has 18% swell and shrinkage of 8%.  The final volume of the compacted

Relief features, characteristics of ridge characteristics of escarpment cha...

characteristics of ridge characteristics of escarpment characteristics of plateau characteristics of knoll characteristics of conical hill

Compute the ultimate settlement, A 2 m wide strip footing is to be constru...

A 2 m wide strip footing is to be constructed in a sandy stratum of 2 m thick. The depth of the footing is 1 m below ground surface. The sand layer is underlain by lm thick cla

Explain about void ratio drops, A clay layer 25 metres thick has a saturate...

A clay layer 25 metres thick has a saturated unit weight of 19.2 kN/m 2 . Ground water level occurs at a depth of 5 metres. It is proposed to construct a reinforced concrete founda

Matrices, How to invert a matrix

How to invert a matrix

Beam stress, what is the bending stress for a simply supported beam with th...

what is the bending stress for a simply supported beam with three equal concentrated loads that are equally spaced?

Airport lighting, Airport Lighting: Lighting of Approach to Runway ...

Airport Lighting: Lighting of Approach to Runway A good system of identification of the runway when landing is to provide six transverse cross-bars of lights placed a

Marked., who invented the first LA abrasion test machine

who invented the first LA abrasion test machine

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd